Consolidate Pre-release group chats across Taiwan & JPN
Create distinct communication channels, appoint specific roles.
(Lena) Audit Requests being sent in the last minute (e.g. Pre-release requests gets sent on 3/10 but QA testing has already concluded on 3/3 and the Dev. team would like the audit to start from the next business day)
Ask QA team to ensure that security audit has been requested as part of the checklist <— Suggested by Ryan
Add a note at the top of the request form to note that the request should be sent at least 1 month before the Dev. team’s desired audit start date
Audits with no scope listed → make it required field?
(Melody) Audit scope definition: We don't have a clear definition of how to calculate target and man days when using GraphQL API, SOAP API or even WebSocket
Some auditors are using “recycled” accounts that are originally created for ex-Rakutenians/auditors
(Simon) Security Audit shadow and parallel are not arranged beforehand. Some are added with short notice.
Make sure that Shadow and Parallel auditors are arranged before the kick off starts to ensure they can participate as much as they can.
(Annie) Rescheduling issue
Scheduling/Project Manager(Tiger PJM) The most rescheduling issue show that more than 50% of reschedule problems are from ''DEV Team QA/Dev Postpone'' (Ref: Pre-release Security Audit Statistics Report 2022)
Scheduling/Project Manager(Tiger PJM If large projects(more than 40man-hours?) reschedule cause other projects can not be arranged at that moment that place resources in a suitable timeframe
Billing/Project Manager(Tiger PJM Need to reduce the issue of resources being occupied and then released when rescheduling. If the billing method of the pre-release audit JP&TW team uses WINES code from April. Is there a chance to receive payment in advance(deposit) to reduce the possibility of changes in the development team?
Newcomers Training Process PJM's newcomers training is not systematic enough — Suggested by Peter