Medium Neutral Citation: Tan v Champion Homes Sales Pty Ltd [2021] NSWCATAP 236
Hearing dates: 24 May 2021
Date of orders: 6 August 2021
Decision date: 06 August 2021
Jurisdiction: Appeal Panel
Before: D Cowdroy AO QC ADCJ, Principal Member
D Robertson, Senior Member
Decision:
(1) Leave to appeal is refused.
(2) The appeal is dismissed.
Catchwords:
BUILDING AND CONSTRUCTION – No issue of principle REASONS FOR DECISION
By a decision published on 12 February 2021, the Tribunal ordered the appellants, Hua Hong Tan, Lui Sing Ling and Matthew Jin Lin to pay the respondent, Champion Homes Sales Pty Ltd, the sum of $41,707.09, and dismissed an application brought by the appellants.
The appellants appeal and seek leave to appeal against that decision.
The appellants are the owners of a property at Kensington, New South Wales. The appellants contracted in writing with the respondent on 21 April 2018 to construct a duplex on the appellants’ property with a contract price of $759,980. We will refer to the appellants as the owners and the respondents as the builder.
The owners had previously paid a tender fee of 25,000inrelationtoatenderdated2February2018issuedbythebuilder,brin784,980.
Under the contract, the tender price was fixed provided that building work commenced by 18 January 2019, which was 350 days from the tender date. Clause 44.2 of the building contract provided that the builder was to commence building works within 20 working days after the owner satisfied a number of specified requirements including “completion by the owner of demolition of existing dwelling on site to enable the builder to commence building works”. If work did not commence by 18 January 2019, the builder was entitled to a contract price adjustment in the amount of $18,999.50.
The building work did not commence before 18 January 2019. It appears that demolition, which was to be carried out by the owners, had not even commenced by 18 January 2019.
The builder filed proceedings HB 20/13125 on 17 March 2020 claiming what was said to be moneys owing in respect of the contract, comprising the contract price adjustment of 18,999.50,variation13fortrafficmanagemen10,317.30 and variation 14 of $12,390.29 for structural steel frames.
The owners filed application HB 20/20818 on 12 May 2020 by which they sought an order that they were not liable to pay the contract price adjustment of 18,999.50andalsosoughtcompensationof50,000 for alleged defective works plus damages for delay.
The owners also resisted liability for variations 13 and 14 as excessive, including on the basis that the builder had not efficiently organised deliveries so as to minimise the traffic control charge, and on the basis that the variation claims were not properly verified or authorised.
By their Notice of Appeal the owners challenged the Tribunal’s findings in relation to each of:
The contract price adjustment;
The variation relating to traffic management costs;
The variation for structural steel frames; and
The Tribunal’s failure to award the owners compensation in respect of damage to the footpath allegedly caused by the builder.
At the hearing of the appeal Mr Vardas, the builder’s business manager, conceded that the builder had agreed, in the course of the hearing at first instance, that the builder would credit the owners with the amount of $2,238.50 in respect of the footpath. As that was the amount the owners had sought, it is apparent that that issue has been resolved without intervention by the Tribunal and it is not necessary to make any orders in that regard.