A latent condition is a physical condition on or near a relevant site that could not have been reasonably anticipated by a contractor at the time of tendering. The contractor is required to have conducted all reasonable inspections of the site and obtained necessary reports including foundation data. The meaning of a latent condition and the options for relief will vary depending on the contract or project. It may depend on the amount of information available to the contractor before the entered into the contract. The smallest differences in written language and wording will result in substantially different outcomes.
Common examples of potential latent conditions include:
Hazardous materials;
Contaminated soil;
Conditions below the ground such as rocks, cavities, underground structures or soil density;
Hidden building services such as cabling, electricity, data or air conditioning ductwork that may be hidden above ceilings, below floors or behind walls; and
Any other types of physical features, active or redundant, that could not be reasonably be anticipated.
Latent conditions exclude weather. It is important to note that a condition treated as latent in one contract, may not be latent for the purposes of another. In each case, the wording of a contact must be carefully considered to determine whether the condition is in fact a latent condition.
A latent condition clause should answer these questions:
What types of conditions are covered?
What level of pre-contract due diligence is expected?
What is the reference point for assessment?
How and when must a claim be made? and
What relief will be available?
To determine whether a particular condition is a latent condition, an assessment will be made regarding what the contractor should have anticipated at a certain point in time. This point of time will typically be at the time of the contractor’s tender, the date of the contract; or a date after the date of the contract with a specific regime.
How do you manage the risk of latent conditions?
Before entering a contract or site investigation, it is important for both parties (including principals and contractors) to agree as to where the risk of latent conditions lies. Consideration should be given to a range of matters including:
If one party bear all the risk of latent conditions, or whether the risk and cost be shared;
If a contractor will be responsible for risk, they must be allowed reasonable time to carry out a risk assessment and a site inspection to ensure that they identify potential additional risks and the associated costs;
Whether any historical searches be available in relation to the subject site or neighbouring properties; and
Parties must decide on a process for sharing knowledge of any potential latent conditions that may be present or which are discovered during site investigations.
Latent conditions are physical conditions which are either on, under or adjacent to a site. They cannot easily be identified during a routine site inspection and may also remain hidden even after a certain amount of site investigation has been carried out based on information provided at the time a tender or contract was prepared.
What constitutes a latent condition will vary depending upon the site in question.
Examples of latent conditions you may encounter on a site include hidden utility services such as power and drainage lines (if not shown on tender documents), mine shafts and soil contamination.
Just who will be responsible for any latent site conditions is an important consideration in any tender or contract process. Ideally the question of responsibility for any latent conditions should be considered and addressed as early as possible in the tender or pre-contract phase of any development or build.
Ultimately, the question of who will bear the risk of additional costs associated with any latent conditions comes down to a question of ‘What does the contract provide’?
Principals generally would prefer to pass the risk of any latent defects on to contractors and, not surprisingly, contractors would generally prefer the risk to be at the expense of the principal or at least shared with the principal.
If in doubt check and double check your contract and tender documents and always seek legal advice as soon as possible to avoid a potential costly dispute developing down the track.
Managing the risk of latent conditions?
Prior to entering into any contract or site investigation stage it is important that both principals and contractors are clear as to where the risk of any latent conditions lies.
In particular, consideration should be given to a range of matters including:
Deciding whether one party will bear all the risk of latent conditions or whether the risk and cost associated with any latent conditions will be shared between the principal and any contractors;
If a contractor is going to be responsible for the risk of any latent conditions, allowing them, as far as any time limits permit, sufficient time to carry out their own risk assessment and site inspections so as to ensure they are aware of the potential risks and costs involved;
Deciding what site testing is to be undertaken and who will bear the cost of any testing;
Considering any historical searches available in relation to either the subject site or any neighbouring properties; and
Agreeing, or providing, a framework that requires all parties to share any knowledge of any potential latent conditions that they suspect may be present or which are uncovered during any routine site testing and investigation.
What if liability for latent conditions is excluded or limited by contract?
If you are a principal and wish to exclude any liability for latent conditions it is recommended that you seek legal advice prior to preparing any contract or tender documentation.
Similarly, if you are a contractor and you are being asked to sign up to a contract where you will bear the risk of any latent conditions it is prudent to obtain advice prior to signing any documentation that may mean the chances of you turning a profit on a project are severely limited.