Title: Work Instruction for Scheduling Production Order in Infor LN
Objective: This work instruction provides a detailed, step-by-step guide on how to schedule a production order in Infor LN, an enterprise resource planning (ERP) software.
Scope: This instruction is applicable to all personnel responsible for scheduling production orders in Infor LN.
Responsibilities: The Production Planner is responsible for following this work instruction when scheduling production orders.
Reference Documents: Infor LN User Manual, Production Planning and Control SOP
- Preparation
1.1. Ensure you have access to Infor LN and the necessary user permissions to create and schedule production orders.
1.2. Log in to your Infor LN account using your credentials.
- Access Production Order Management
2.1. On the Infor LN main menu, navigate to the 'Production' module.
2.2. Under the 'Production' module, click on 'Production Order Management.'
- Create a New Production Order
3.1. Click on 'New Production Order' to create a new production order.
3.2. Fill in the required fields, including the item to be produced, production quantity, and warehouse location.
3.3. Enter the requested delivery date, considering customer requirements and production lead times.
3.4. Click 'Save' to generate the production order number.
- Schedule the Production Order
4.1. In the 'Production Order Management' screen, locate the production order you just created.
4.2. Select the production order by clicking on the order number.
4.3. Click on the 'Schedule Production Order' button.
4.4. In the 'Scheduling Parameters' window, select the scheduling direction (forward or backward).
4.5. Choose the appropriate scheduling method: finite or infinite capacity.
4.6. Enter any additional scheduling parameters, if required.
4.7. Click 'OK' to start the scheduling process.
- Review the Production Schedule
5.1. Once the scheduling process is completed, review the production schedule to ensure the dates and resources are in line with the planned production.
5.2. Check for any conflicts or bottlenecks in the production schedule.
5.3. If necessary, adjust the schedule manually or re-run the scheduling process with different parameters.
- Confirm and Save the Production Schedule
6.1. After reviewing and finalizing the production schedule, click 'Confirm Schedule' to lock in the production plan.
6.2. Save the production order by clicking on the 'Save' button.
- Communicate the Production Schedule
7.1. Share the finalized production schedule with relevant stakeholders, including production supervisors, materials management, and sales teams.
7.2. Monitor the production order's progress and update the schedule as needed.
- Completion
8.1. Log out of Infor LN and close the application.
Document Control:
- Revision: 1.0
- Effective Date: 20th March 2023
- Reviewed by: [Name, Title]
- Approved by: [Name, Title]