| Day 0 (Q-End) | - Period close begins- Kickoff mtg: Assign owners, review prior filings | Controller, FP&A, Legal | Close checklist, project plan | Kickoff Gate: Team alignment (CFO sign-off) |
| Day +1 (T-39) | - Flash financials- IT: Data extracts for XBRL | Accounting, IT | P&L/Balances prelim | - |
| Day +5 (T-35) | - Final close books- Risk factors update starts | Accounting, Tax, Legal | Trial balance, tax prov. | Close Gate: Book close certified (Controller + Auditor prelim) |
| T-30 | - MD&A draft (financials + narrative)- Notes to FS draft | FP&A, Accounting, IR | MD&A v1, Notes v1 | - |
| T-25 | - Controls testing (SOX)- Biz unit inputs (e.g., contingencies) | Internal Audit, Business Units | SARBOX certs draft | - |
| T-20 | - Full draft complete (shell populated)- Auditor field start | All Internal + External Auditor | First full draft | Draft Gate #1: Legal comfort letter (no major issues) |
| T-15 | - Auditor review comments- CEO/CFO narrative review | External Auditor, CEO/CFO | Revised draft v2 | - |
| T-10 | - Finalize exhibits (e.g., press releases)- XBRL tagging | Accounting, Legal, IT | XBRL iXBRL files | Review Gate: Audit Committee prelim review |
| T-7 | - Management rep letter to auditors | CFO, Controller, Legal | Rep letter signed | - |
| T-5 | - Final reviews + redlines | All | Clean draft | - |
| T-3 | - CEO/CFO/Audit Committee sign-off- Board review (if req'd) | CEO/CFO, Audit Comm, Board | All certs signed | Approval Gate: Full exec sign-off |
| T-1 | - EDGAR test filing- IR prep (earnings call sync) | Legal, IR | Test submission | - |
| T (File Day) | - Submit to EDGAR- Distribute internally | Legal (Securities Counsel) | Filed 10-Q | Filing Gate: Confirmation + archive |