Institutional Repository Digitization Sprint Plan
Sprint Overview
Duration: 4 weeks (20 working days), assuming a cross-functional team of 6-8 members: Project Lead (1), Digitizers (2), Catalogers/Metadata Specialists (2), QC Analyst (1), Copyright/Legal Specialist (1), IT/Preservation Archivist (1).
Goal: Digitize 500 high-priority items (e.g., rare books, manuscripts, photos) from the institutional repository, ensuring compliance, quality, and long-term preservation. Target: 80% completion rate with <2% error rate.
Tools: CONTENTdm or Islandora for ingest; Adobe Photoshop/Lightroom for processing; Archivematica for preservation; shared project board (Trello/Jira).
Success Metrics: Items digitized, copyright-cleared, QC-passed, preserved; user feedback loop post-sprint.
Daily Standups: 15-min meetings; retrospective at end.
1. Prioritization (Week 1, Days 1-3)
Prioritize based on a scoring matrix to focus on high-impact, low-risk items. Audit ~2,000 items initially.
Prioritization Criteria (Score 1-10 per category; total >30 = Sprint Candidate)
| Category | Weight | Examples/Scoring |
|---|
| User Demand | 30% | High (10): Top 20% circulations; Medium (5): Recent queries; Low (1): No use. |
| Uniqueness/Rarity | 25% | High (10): One-of-a-kind; Medium (5): Regional importance. |
| Condition Risk | 20% | High (10): Fragile/degrading; Low (1): Stable. |
| Cultural/Strategic Value | 15% | High (10): Aligns with institutional mission (e.g., local history). |
| Ease of Digitization | 10% | High (10): Flat items <A3; Low (1): Oversize/3D. |
Workflow:
- Day 1: Team audits collection database; generate ranked list (Excel/Google Sheets).
- Day 2: Select top 500 items; assign to "Sprint Backlog."
- Day 3: Stakeholder review/approval.
- Output: Prioritized backlog with metadata stubs (title, creator, date).
2. Copyright Clearance (Ongoing, Weeks 1-4; Dedicated Days 1-5, 10)
Ensure all items are cleared for open access (CC0 or equivalent).
Workflow
- Pre-Digitization Audit (per batch of 100 items):
- Check database: Publication date (>1928 US = public domain?); Creator death (>70 years?).
- Orphan works: Use diligent search (HathiTrust tool, WATCH database).
- Permissions: Email templates for rights holders; 48-hour response SLA.
- Decision Tree:
| Status | Action | Flag |
|---|
| Public Domain | Clear ✓ | Green |
| Permission Granted | Document license | Green |
| Fair Use (e.g., education) | Legal review; restrict access | Yellow |
| Uncertain/Orphan | Defer or low-res access only | Red |
- Documentation: Rights statement in METS/XML metadata; audit trail spreadsheet.
- Milestone: 100% of digitized items cleared by ingest.
- Escalation: Weekly legal review meeting.
3. Digitization & Quality Control (QC) (Weeks 2-3)
Standards:
- Hardware: Phase One/XF scanner or Epson flatbed; 600 DPI grayscale/color.
- Formats: Uncompressed TIFF (master, 500MB avg.); JPEG2000 (access, <50MB); PDF/A (text-based).
- Metadata: Dublin Core minimum + technical (e.g., checksums).
Workflow (Batch Processing: 100 items/day)
- Digitization (Days 6-15):
- Prep: Clean/align items; non-destructive handling.
- Scan: Calibrate daily; capture recto/verso.
- Post-Process: Crop, levels, OCR (ABBYY FineReader for text).
- QC Checklist (Dedicated QC Queue; 20% time buffer):
| Check | Pass Criteria | Tool/Action |
|---|
| Image Quality | Sharpness >90% (Imatest); No artifacts | Visual + automated (ImageMagick) |
| Color/Contrast | DeltaE <5; histogram balanced | Photoshop |
| Completeness | All pages; no skew >1° | Manual spot-check (10%) |
| Metadata Accuracy | 100% match to physical | Schema validation |
| File Integrity | MD5 checksum matches | Fixity tool |
- Process: 1st pass (automated); 2nd pass (manual, 20% sample); reject/redo <2%.
- Output: QC-approved packages ready for preservation.
4. Preservation (Week 4, Days 16-20)
Follow OAIS model for long-term viability.
Workflow
- Ingest:
- Package: METS bag with masters, derivatives, metadata, checksums.
- Repository: Upload to DSpace/Fedora; auto-generate IIIF manifests.
- Storage Strategy:
| Tier | Copies | Format/Location | Refresh Cycle |
|---|
| Master | 3 | TIFF on LTO-9 tape + cloud (AWS S3 Glacier Deep Archive) | Annual migration |
| Access | 2 | JPEG2000 on NAS + CDN | Quarterly fixity |
| Backup | 1 | Encrypted offsite (e.g., Iron Mountain) | Daily incremental |
- Preservation Actions:
- Generate PREMIS events (e.g., "ingested 2023-10-01").
- Automated monitoring: JHOVE validation; fixity checks weekly.
- Succession Plan: Format migration triggers (e.g., TIFF to ISO-based).
- Milestone: 100% items preserved with verified fixity.
Timeline & Milestones
| Week/Day | Focus Areas | Deliverables | Dependencies |
|---|
| W1 (1-5) | Prioritization + Copyright (Batch 1) | Ranked backlog; 100 cleared | Collection DB access |
| W2 (6-10) | Digitize/QC Batch 1-2 + Copyright | 200 QC-passed packages | Scanners ready |
| W3 (11-15) | Digitize/QC Batch 3-5 + Copyright | 500 total packages | QC capacity |
| W4 (16-20) | Preservation + Final QC/Copyright | Live repository items; Report | IT storage provisioned |
| Day 20 | Retrospective & Handover | Sprint report; Lessons learned | - |
Risks & Mitigations
| Risk | Likelihood/Impact | Mitigation |
|---|
| Copyright delays | High/Med | Parallel processing; pre-clear high-risk. |
| Equipment failure | Med/High | Backup scanners; remote digitization fallback. |
| QC bottlenecks | Med/Med | Train all on QC; automate 70%. |
| Storage overflow | Low/High | Pre-allocate 5TB; monitor usage. |
| Team burnout | Med/Med | 4-day weeks optional; rotate tasks. |
This plan is scalable—adjust batch sizes based on team velocity. Post-sprint, iterate for next sprint targeting next-priority tier. Questions on specifics?