| R1 | Feedstock Supply | Volatility in green H₂ or e-fuel feedstock prices/availability disrupting carrier production. | All (Ammonia: H₂/N₂; Methanol: H₂/CO₂; LOHC: H₂) | M/H (6) | Long-term H₂ PPAs; multi-supplier contracts; on-site electrolysis. | H₂ cost >$4/kg; Supply downtime >10%; DSCR <1.2x. | L/M (2) |
| R2 | Production Efficiency | Lower-than-expected conversion efficiency in hydrogenation process. | Ammonia: M/M (4)Methanol: H/M (6)LOHC: H/H (9) | Pathway-specific | Technology qualification pilots; performance guarantees in EPC; modular scale-up. | Efficiency <90% (Ammonia), <85% (Methanol), <95% wt% H₂ (LOHC); OPEX +20%. | M/L (3) |
| R3 | Storage/Handling | Safety hazards from toxicity, flammability, or corrosion during storage. | Ammonia: H/H (9)Methanol: M/H (6)LOHC: L/M (2) | Pathway-specific | HAZOP studies; double-walled tanks; ATEX-certified equipment; insurance wrappers. | Incident rate >0.1/MT; Storage utilization <80%; Insurance premium >2% capex. | M/M (4) |
| R4 | Transportation | Infrastructure gaps or mode-specific risks (ship/road/pipe) leading to delays/costs. | All (Ammonia: Existing; Methanol: Tankers; LOHC: Road/ship) | M/M (4) | Feeder studies; long-term charters; retrofitted carriers. | Transport cost >$0.5/kg H₂-eq; Delivery reliability <95%; Freight rate +30%. | L/M (2) |
| R5 | Cracking/Release | Inefficient/expensive dehydrogenation/cracking to recover H₂ at destination. | Ammonia: M/H (6)Methanol: H/M (6)LOHC: H/H (9) | Pathway-specific | Catalyst R&D partnerships; heat integration; off-take with integrated crackers. | Cracking efficiency <95% (Ammonia), <90% (Methanol), <99% (LOHC); H₂ purity <99.97%; Energy penalty >20%. | M/M (4) |
| R6 | Market/Offtake | Weak H₂ demand or low carrier premiums eroding economics. | All | H/M (6) | Bankable offtake MOUs (>70% volume); price indexation to H₂ spot; export credits. | Offtake volume <80%; Carrier margin <$2/kg H₂-eq; IRR <8%. | M/L (3) |
| R7 | Capex/Opex Overrun | Cost inflation in EPC due to supply chain or tech immaturity. | Ammonia: L/M (2)Methanol: M/H (6)LOHC: H/M (6) | Pathway-specific | Fixed-price EPC/LSTK contracts; contingency reserves (15-20%); forex hedges. | Capex overrun >15%; OPEX >$1.5/kg H₂-eq; EPC delay >6 months. | L/M (2) |
| R8 | Regulatory/Permitting | Delays in approvals for novel pathways or emissions rules. | Ammonia: M/M (4)Methanol: L/M (2)LOHC: M/H (6) | Pathway-specific | Early engagement with regulators; pre-permitted sites; EU CBAM compliance. | Permitting delay >12 months; Carbon tax >€100/tCO₂-eq; Fine >1% revenue. | L/L (1) |
| R9 | HSE/Environmental | Emissions leaks, spills, or community opposition. | Ammonia: H/M (6)Methanol: M/M (4)LOHC: M/L (3) | Pathway-specific | ESG frameworks; third-party audits; spill response plans. | LTIF <0.1; CO₂ intensity >2 kg/kg H₂; Downtime >5% from incidents. | L/M (2) |
| R10 | Financing/Lender | Debt refusal due to unproven tech or covenants breach. | All (LOHC highest) | M/H (6) | DSCR carve-outs for ramp-up; ECAs/MFIs; sensitivity modeling in IM. | DSCR <1.2x (stress); LLCR <1.5x; Equity overrun >10%. | M/M (4) |
| R11 | Geopolitical/Force Majeure | Supply chain disruptions (e.g., catalysts from Asia) or trade barriers. | All | M/M (4) | Dual-sourcing; inventory buffers; political risk insurance (MIGA). | Catalyst delay >3 months; Project delay >20%; Force majeure claims >5% capex. | L/M (2) |