| Term | Practical Completion (PC) | Practical Completion (PC) | Completion |
| Definition Basis | Complete except minor omissions/defects | Complete except minor omissions/defects | Meets Acceptance Criteria |
| Assessment Focus | Compliance with Employer's Design | Compliance with ER via Contractor's Proposals | Compliance with Defined Criteria |
| Assessor | Contract Administrator (CA) | Contract Administrator (CA) | Project Manager (PM) |
| Certification Trigger | Contractor's request | Contractor's request | Contractor's Notification |
| Certifier's Response Time | 14 days (to issue or notify defects) | 14 days (to issue or notify defects) | 4 weeks (to accept/reject; failure = accept) |
| Defects at PC/Completion | Minor defects noted; rectified in DLP | Minor defects noted; rectified in DLP | Defects preventing criteria met must be fixed first. Minor defects allowed. |
| Key Implication | Subjective judgment by CA | Subjective judgment by CA (re ER/Proposals) | Objective compliance; Contractor-driven notification |