Optimize schedule for 3 Jobs across 3 Machines to minimize makespan . Each job involves…
- User
Optimize schedule for 3 Jobs across 3 Machines to minimize makespan . Each job involves a series of Operations needing specific machines and times . Operations are processed in order , without interruption , on a single Machine at a time . Problem : Machine 0 is used for the following Operations : Job 0 Operation 0 duration 105 mins . Job 2 Operation 0 duration 78 mins . Job 1 Operation 2 duration 213 mins . Machine 1 is used for the following Operations : Job 0 Operation 1 duration 29 mins . Job 1 Operation 1 duration 18 mins . Job 2 Operation 2 duration 221 mins . Machine 2 is used for the following Operations : Job 1 Operation 0 duration 193 mins . Job 2 Operation 1 duration 74 mins . Job 0 Operation 2 duration 213 mins .