How does the project approval process work for the Australian Energy Market Operator? I…
- User
How does the project approval process work for the Australian Energy Market Operator? I saw that there were newly actionable projects under the ISP, but each of them already has a proponent. So does it mean that an interested developer has to apply with AEMO first and their project, if selected, will become one of the actionable projects? Or is the project still up for tender after being announced as an actionable project?
- Assistant
The Australian Energy Market Operator (AEMO) doesn't actually approve transmission projects or select developers - that's a common misconception about how the Integrated System Plan (ISP) process works.
Here's how it actually functions:
AEMO's ISP identifies needed transmission projects based on system modeling and planning, but AEMO itself doesn't run a tender process or select proponents. Instead, the process typically works like this:
-
AEMO identifies the need: Through the ISP, AEMO identifies transmission projects that will be needed to support the energy transition, categorizing them as actionable, future, or committed projects.
-
Jurisdictional planning bodies take over: Once a project is identified as actionable in the ISP, the relevant Transmission Network Service Provider (TNSP) in that jurisdiction - like Transgrid in NSW, AEMO Victorian Planning in Victoria, or Powerlink in Queensland - becomes responsible for progressing it.
-
Regulatory Investment Test: The TNSP must complete a Regulatory Investment Test for Transmission (RIT-T), which includes consulting on options and selecting the most economically beneficial solution.
-
Proponent selection varies by project type:
- For most transmission lines and substations, the incumbent TNSP typically develops the project themselves
- For some projects (particularly renewable energy zones or special infrastructure), states may run competitive tender processes
- Some jurisdictions have introduced contestability frameworks where third parties can bid to develop certain projects
The reason you see proponents already attached to newly actionable ISP projects is usually because the incumbent TNSP is the default developer for transmission infrastructure in their region. They don't need to "win" the project - they're automatically responsible for progressing it unless the state government decides to make it contestable.
If you're a developer interested in transmission projects, your opportunities typically come through state-run competitive processes for specific infrastructure, or through the limited contestability frameworks that exist in some jurisdictions.
-