| 001 | Target Product Profile v1.0 | Clinical Development | 2024-01-15 | N/A | 002, 003, 004 | Completed | High | Foundation document for program strategy |
| 002 | Clinical Development Plan | Clinical Development | 2024-02-10 | 001 | 010, 011, 012 | Completed | High | Approved by governance committee |
| 003 | Preclinical Development Plan | Toxicology | 2024-02-15 | 001 | 005, 006 | Completed | High | |
| 004 | CMC Development Strategy | CMC | 2024-02-20 | 001 | 007, 008, 009 | Completed | High | |
| 005 | In Vitro Pharmacology Report | Pharmacology | 2024-03-15 | 003 | 013 | Completed | Medium | |
| 006 | Animal Model Efficacy Study | Pharmacology | 2024-04-10 | 003 | 013 | Completed | High | |
| 007 | Cell Line Development | Process Development | 2024-05-20 | 004 | 014 | Completed | High | |
| 008 | Analytical Method Development | Analytical Development | 2024-05-25 | 004 | 015 | Completed | High | |
| 009 | Formulation Development | Formulation | 2024-06-10 | 004 | 016 | Completed | High | |
| 010 | Phase I Protocol Synopsis | Clinical Development | 2024-03-01 | 002 | 020 | Completed | Medium | |
| 011 | Phase II Protocol Synopsis | Clinical Development | 2024-03-15 | 002 | 050 | Completed | Low | |
| 012 | Phase III Protocol Synopsis | Clinical Development | 2024-03-30 | 002 | 070 | Completed | Low | |
| 013 | IND-Enabling Toxicology Study | Toxicology | 2024-06-30 | 005, 006 | 017 | Completed | Critical | |
| 014 | Master Cell Bank Creation | Manufacturing | 2024-07-15 | 007 | 018 | Completed | High | |
| 015 | Release Testing Methods Validation | Quality Control | 2024-07-20 | 008 | 018 | Completed | High | |
| 016 | Drug Product Formulation Report | Formulation | 2024-07-25 | 009 | 018 | Completed | High | |
| 017 | Final Toxicology Report | Toxicology | 2024-08-15 | 013 | 019 | Completed | Critical | |
| 018 | GMP Manufacturing - Phase I Material | Manufacturing | 2024-08-30 | 014, 015, 016 | 019 | Completed | Critical | |
| 019 | IND Submission Package | Regulatory Affairs | 2024-09-30 | 017, 018 | 020 | Completed | Critical | |
| 020 | Phase I Final Protocol | Clinical Development | 2024-10-15 | 010, 019 | 021, 022 | Completed | High | |
| 021 | Phase I IRB/EC Submission | Clinical Operations | 2024-10-30 | 020 | 023 | Completed | High | |
| 022 | Phase I eCRF Development | Data Management | 2024-11-15 | 020 | 024 | Completed | Medium | |
| 023 | Phase I Site Initiation | Clinical Operations | 2024-12-01 | 021 | 025 | Completed | High | |
| 024 | Phase I Database Build | Data Management | 2024-12-10 | 022 | 025 | Completed | Medium | |
| 025 | Phase I FPFV | Clinical Operations | 2025-01-10 | 023, 024 | 026 | In Progress | High | |
| 026 | Phase I Cohort 1 Completion | Clinical Operations | 2025-02-15 | 025 | 027 | Not Started | High | |
| 027 | Phase I Cohort 1 Safety Review | Clinical Development | 2025-02-28 | 026 | 028 | Not Started | High | |
| 028 | Phase I Cohort 2 Dosing Decision | Clinical Development | 2025-03-10 | 027 | 029 | Not Started | High | |
| 029 | Phase I Cohort 2 Completion | Clinical Operations | 2025-04-15 | 028 | 030 | Not Started | High | |
| 030 | Phase I Cohort 2 Safety Review | Clinical Development | 2025-04-30 | 029 | 031 | Not Started | High | |
| 031 | Phase I Cohort 3 Dosing Decision | Clinical Development | 2025-05-10 | 030 | 032 | Not Started | High | |
| 032 | Phase I Cohort 3 Completion | Clinical Operations | 2025-06-15 | 031 | 033 | Not Started | High | |
| 033 | Phase I LPLV | Clinical Operations | 2025-06-30 | 032 | 034 | Not Started | High | |
| 034 | Phase I Database Lock | Data Management | 2025-07-15 | 033 | 035 | Not Started | High | |
| 035 | Phase I Statistical Analysis | Biostatistics | 2025-07-30 | 034 | 036 | Not Started | High | |
| 036 | Phase I Clinical Study Report | Medical Writing | 2025-09-15 | 035 | 037, 050 | Not Started | High | |
| 037 | End of Phase I Meeting Request | Regulatory Affairs | 2025-09-30 | 036 | 038 | Not Started | Medium | |
| 038 | End of Phase I Meeting | Regulatory Affairs | 2025-11-15 | 037 | 039 | Not Started | Medium | |
| 039 | Phase II Development Decision | Clinical Development | 2025-11-30 | 038 | 040 | Not Started | Critical | Go/No-Go milestone |
| 040 | Process Scale-Up for Phase II | Manufacturing | 2025-12-15 | 039 | 041 | Not Started | High | |
| 041 | GMP Manufacturing - Phase II Material | Manufacturing | 2026-02-15 | 040 | 051 | Not Started | High | |
| 042 | Dose Range Finding Study | Toxicology | 2025-12-30 | 039 | 043 | Not Started | Medium | |
| 043 | Extended Toxicology Study | Toxicology | 2026-03-15 | 042 | 051 | Not Started | High | |
| 044 | Biomarker Assay Development | Biomarker | 2026-01-15 | 039 | 050 | Not Started | Medium | |
| 045 | PK/PD Model Refinement | Clinical Pharmacology | 2026-01-30 | 039 | 050 | Not Started | Medium | |
| 046 | Phase II Statistical Analysis Plan | Biostatistics | 2026-02-15 | 039 | 050 | Not Started | Medium | |
| 047 | Phase II Data Monitoring Plan | Data Management | 2026-02-28 | 039 | 050 | Not Started | Medium | |
| 048 | Phase II Safety Monitoring Plan | Pharmacovigilance | 2026-03-10 | 039 | 050 | Not Started | High | |
| 049 | Phase II Site Selection | Clinical Operations | 2026-03-20 | 039 | 051 | Not Started | Medium | |
| 050 | Phase II Final Protocol | Clinical Development | 2026-04-01 | 011, 036, 044, 045, 046, 047, 048 | 051, 052 | Not Started | High | |
| 051 | Phase II IRB/EC Submission | Clinical Operations | 2026-04-15 | 041, 043, 049, 050 | 053 | Not Started | High | |
| 052 | Phase II eCRF Development | Data Management | 2026-04-30 | 050 | 054 | Not Started | Medium | |
| 053 | Phase II Site Initiation | Clinical Operations | 2026-05-30 | 051 | 055 | Not Started | High | |
| 054 | Phase II Database Build | Data Management | 2026-06-15 | 052 | 055 | Not Started | Medium | |
| 055 | Phase II FPFV | Clinical Operations | 2026-07-01 | 053, 054 | 056 | Not Started | High | |
| 056 | Phase II Interim Analysis | Biostatistics | 2026-12-15 | 055 | 057 | Not Started | High | |
| 057 | Phase II Interim Results Review | Clinical Development | 2026-12-30 | 056 | 058 | Not Started | High | |
| 058 | Phase II Continuation Decision | Clinical Development | 2027-01-15 | 057 | 059 | Not Started | Critical | Go/No-Go milestone |
| 059 | Phase II LPLV | Clinical Operations | 2027-07-01 | 058 | 060 | Not Started | High | |
| 060 | Phase II Database Lock | Data Management | 2027-07-30 | 059 | 061 | Not Started | High | |
| 061 | Phase II Statistical Analysis | Biostatistics | 2027-08-30 | 060 | 062 | Not Started | High | |
| 062 | Phase II Clinical Study Report | Medical Writing | 2027-10-30 | 061 | 063, 070 | Not Started | High | |
| 063 | End of Phase II Meeting Request | Regulatory Affairs | 2027-11-15 | 062 | 064 | Not Started | Medium | |
| 064 | End of Phase II Meeting | Regulatory Affairs | 2028-01-15 | 063 | 065 | Not Started | Medium | |
| 065 | Phase III Development Decision | Clinical Development | 2028-01-30 | 064 | 066 | Not Started | Critical | Go/No-Go milestone |
| 066 | Commercial Process Development | Manufacturing | 2028-02-28 | 065 | 067 | Not Started | High | |
| 067 | Process Validation Plan | Manufacturing | 2028-04-15 | 066 | 068 | Not Started | High | |
| 068 | Commercial Scale Manufacturing | Manufacturing | 2028-07-15 | 067 | 071 | Not Started | Critical | |
| 069 | Chronic Toxicology Study | Toxicology | 2028-06-30 | 065 | 071 | Not Started | High | |
| 070 | Phase III Final Protocol | Clinical Development | 2028-03-15 | 012, 062, 065 | 071, 072 | Not Started | High | |
| 071 | Phase III IRB/EC Submission | Clinical Operations | 2028-08-01 | 068, 069, 070 | 073 | Not Started | High | |
| 072 | Phase III eCRF Development | Data Management | 2028-05-15 | 070 | 074 | Not Started | Medium | |
| 073 | Phase III Site Initiation | Clinical Operations | 2028-10-01 | 071 | 075 | Not Started | High | |
| 074 | Phase III Database Build | Data Management | 2028-07-15 | 072 | 075 | Not Started | Medium | |
| 075 | Phase III FPFV | Clinical Operations | 2028-11-01 | 073, 074 | 076 | Not Started | High | |
| 076 | Phase III Interim Analysis | Biostatistics | 2029-11-01 | 075 | 077 | Not Started | High | |
| 077 | Phase III IDMC Review | Clinical Development | 2029-11-30 | 076 | 078 | Not Started | High | |
| 078 | Phase III LPLV | Clinical Operations | 2030-11-01 | 077 | 079 | Not Started | High | |
| 079 | Phase III Database Lock | Data Management | 2030-12-01 | 078 | 080 | Not Started | High | |
| 080 | Phase III Statistical Analysis | Biostatistics | 2031-01-15 | 079 | 081 | Not Started | High | |
| 081 | Phase III Clinical Study Report | Medical Writing | 2031-03-15 | 080 | 082 | Not Started | High | |
| 082 | Pre-NDA/BLA Meeting Request | Regulatory Affairs | 2031-04-01 | 081 | 083 | Not Started | Medium | |
| 083 | Pre-NDA/BLA Meeting | Regulatory Affairs | 2031-05-15 | 082 | 084 | Not Started | Medium | |
| 084 | NDA/BLA Submission Decision | Clinical Development | 2031-06-01 | 083 | 085 | Not Started | Critical | Go/No-Go milestone |
| 085 | Commercial Manufacturing Validation Batches | Manufacturing | 2031-07-15 | 084 | 086 | Not Started | High | |
| 086 | Stability Data for Commercial Product | CMC | 2031-09-15 | 085 | 087 | Not Started | High | |
| 087 | Module 3 (Quality) Preparation | CMC | 2031-10-15 | 086 | 090 | Not Started | High | |
| 088 | Module 2 (Summaries) Preparation | Medical Writing | 2031-08-15 | 084 | 090 | Not Started | High | |
| 089 | Module 5 (Clinical) Preparation | Medical Writing | 2031-09-01 | 084 | 090 | Not Started | High | |
| 090 | NDA/BLA Submission | Regulatory Affairs | 2031-11-15 | 087, 088, 089 | 091 | Not Started | Critical | |
| 091 | FDA Filing Decision | Regulatory Affairs | 2032-01-15 | 090 | 092 | Not Started | High | |
| 092 | FDA Mid-Cycle Review | Regulatory Affairs | 2032-05-15 | 091 | 093 | Not Started | Medium | |
| 093 | FDA Advisory Committee Meeting | Regulatory Affairs | 2032-07-15 | 092 | 094 | Not Started | High | |
| 094 | FDA Approval Decision | Regulatory Affairs | 2032-09-15 | 093 | 095 | Not Started | Critical | |
| 095 | Label Negotiation | Regulatory Affairs | 2032-10-15 | 094 | 096 | Not Started | High | |
| 096 | Commercial Launch Preparation | Commercial | 2032-11-15 | 095 | 097 | Not Started | High | |
| 097 | Sales Force Training | Commercial | 2033-01-15 | 096 | 098 | Not | | |