    1. Methodology The whole replacement will be divided into below phases: • Hardware confirmation • Internal examination • Replacement • Site acceptance tests • Nursing period • CCM Integration • Hardware disposal 6.1 Hardware Confirmation The hardware that has arrived will be verified by the Marine Department. After that, these hardware items will be delivered to Tidalis APAC for preparation and internal examination. 6.2 Internal Examination & Pre-deployment Preparation The confirmed servers will be sent to Tidalis for preparation, which includes: • Pre-installation of software. • Compatibility testing. • Operational testing in a controlled testing environment. Refer to Section 7 Internal Examinations (assumed to be a separate detailed section). • Crucially, pre-configuration of a test environment for Data Processors (DP), Radar Data Processors (RDP) and Central Track Processors (CTP/COP) nodes to operate in test mode, compatible with the test mode RDPs. This is essential for the live vs. test comparison phase during on-site replacement. 6.3 Phased Replacement To minimize the impact of the work and facilitate real-time comparison, the replacement will be separated by sites and will proceed with one RDP at a time per site, leveraging the oper and test modes for validation.

    General Procedure for Each RADAR-Subsystem Replacement (2 servers per site): Each RADAR-subsystem replacement will begin by addressing one of the two RDP servers at a site, specifically designed to ensure continuous operation and enable live comparison. The order will typically start with a non-main operational RDP if applicable, or Group B as specified. Before initiating the replacement at any site, Tidalis will: • Confirm the current operational subsystem status. • Ensure that corresponding DP and CTP/COP nodes have a test mode instance or configuration ready to communicate with the new RDP server in test mode. This is a critical prerequisite for the comparison process. In principle, only the RDP servers will be replaced. Other components, such as KVM, cables, and power relevant, will be adapted for use with the new servers unless any unexpected issues arise during the replacement. Tidalis will confirm these components will work as before replacement. After replacing hardware at a remote site, Tidalis will place the existing hardware in the MD approved area at the site, pending further instructions. If the replacement causes an unacceptable impact, Tidalis will restore the existing hardware as part of a rollback procedure. Detailed Step-by-Step for Replacing two RDPs at a Site: (Applies to MAW, VTC, BHD, CTB, KCCS, NPO, SKC RADAR-subsystem replacements) Let's use MAW as an example (RDP0111, RDP0112). This procedure will be replicated for all sites. 6.3.1 Phase 1: Replacement of the First RDP and Live vs. Test Comparison

    1. Selection: Identify the first RDP server for replacement (e.g., MAW Group B: RDP0112).
    2. New Hardware Installation: The software-pre-installed new server (RDP0112) will physically substitute the existing RDP0112 hardware. • Crucially, the existing RDP0111 will remain in oper mode and fully functional, ensuring no disruption to live operations.
    3. Initial Boot & Test Mode Activation: Connect the existing cables to relevant ports on the new RDP0112 server and boot up the system. Immediately upon successful boot, Tidalis will change the node's mode to test: $ vtmis-node change test
    4. Test Environment Verification: Verify that the new RDP0112 (in test mode) is successfully communicating with the designated DP and CTP/COP nodes that have also been set to test mode.
    5. Live vs. Test Comparison (Initial SAT): With the existing RDP0111 still in oper mode and the new RDP0112 in test mode, Tidalis will conduct a focused comparison (an initial System Acceptance Test) to observe and analyze their respective data streams and operational parameters. • This comparison will allow direct observation of the new RDP's performance and data integrity (test mode) against the established production system (oper mode) without impacting live operations. • Any discrepancies will be identified and addressed before proceeding.
    6. Transition to Operational Mode (if successful): If the comparison confirms satisfactory performance and data consistency from the new RDP0112 in test mode, Tidalis will transition it to oper mode: $ vtmis-node change oper
    7. Operational Verification: Confirm that the new RDP0112 is now fully integrated and operating correctly in oper mode alongside the existing RDP0111. 6.3.2 Phase 2: Replacement of the Second RDP and Final Site Integration
    8. Selection: Identify the second RDP server for replacement (e.g., MAW Group A: RDP0111).
    9. New Hardware Installation: The software-pre-installed new server (RDP0111) will physically substitute the existing RDP0111 hardware. • At this point, the newly installed RDP0112 will be in oper mode, maintaining continuous operation during this replacement.
    10. Initial Boot & Operational Mode: Connect the existing cables to relevant ports on the new RDP0111 server and boot up the system. The server will be brought online in oper mode (or transitioned to oper mode after initial boot).
    11. High Availability & Final Site SAT: Once both new RDPs (RDP0111 and RDP0112) are installed and operating in oper mode, Tidalis will confirm high availability supported by both groups. A comprehensive Site Acceptance Test (SAT) will then be conducted for the entire RADAR-subsystem at the site. This SAT will ensure both new RDPs function seamlessly together and meet all operational requirements.
    12. Nursing Period Initiation: If all SAT criteria pass, the nursing period will be initiated for this site.

    edit the above part for me, as the final should be (new test mode RDP+ test mode CTP(=COP)+test mode IP(CSP)+test mode DP(for viewing the tracks)) vs live DP(for viewing the tracks) as we cannot view tracks directly on the radar display processors(RDP)

  2. Gemini Assistant

    Of course. The key change is to clarify that the comparison isn't between two RDPs directly, but between the final track data displayed on two separate Data Processors (DPs)—one fed by the live system and one by the new test system.

    Here is the edited methodology, incorporating your specific requirements for the comparison phase. The changes are primarily in sections 6.2, 6.3, and 6.3.1.


    6. Methodology

    The whole replacement will be divided into the below phases:

    • Hardware confirmation
    • Internal examination
    • Replacement
    • Site acceptance tests
    • Nursing period
    • CCM Integration
    • Hardware disposal

    6.1 Hardware Confirmation

    The hardware that has arrived will be verified by the Marine Department. After that, these hardware items will be delivered to Tidalis APAC for preparation and internal examination.

    6.2 Internal Examination & Pre-deployment Preparation

    The confirmed servers will be sent to Tidalis for preparation, which includes:

    • Pre-installation of software.
    • Compatibility testing.
    • Operational testing in a controlled testing environment. Refer to Section 7 Internal Examinations (assumed to be a separate detailed section).
    • Crucially, pre-configuration of a parallel test data path. This involves setting up test instances of the Data Processor (DP), IP/CSP, and Central Track Processor (CTP/COP) nodes. These test nodes will be configured to receive and process data from a new RDP server when it is brought online in test mode. This entire test path is essential for the comparison phase during on-site replacement.

    6.3 Phased Replacement

    To minimize the impact of the work and facilitate real-time comparison, the replacement will be separated by sites and will proceed with one RDP at a time per site, leveraging the oper and test modes for validation.

    General Procedure for Each RADAR-Subsystem Replacement (2 servers per site):

    Each RADAR-subsystem replacement will begin by addressing one of the two RDP servers at a site, specifically designed to ensure continuous operation and enable live comparison. The order will typically start with a non-main operational RDP if applicable, or Group B as specified.

    Before initiating the replacement at any site, Tidalis will:

    • Confirm the current operational subsystem status.
    • Ensure that the parallel test data path—comprising test mode instances of the DP, IP/CSP, and CTP/COP—is configured and ready to receive data from the new RDP server. This is a critical prerequisite for the comparison process.

    In principle, only the RDP servers will be replaced. Other components, such as KVM, cables, and power relevant, will be adapted for use with the new servers unless any unexpected issues arise during the replacement. Tidalis will confirm these components will work as before replacement.

    After replacing hardware at a remote site, Tidalis will place the existing hardware in the MD-approved area at the site, pending further instructions. If the replacement causes an unacceptable impact, Tidalis will restore the existing hardware as part of a rollback procedure.

    Detailed Step-by-Step for Replacing two RDPs at a Site: (Applies to MAW, VTC, BHD, CTB, KCCS, NPO, SKC RADAR-subsystem replacements)

    Let's use MAW as an example (RDP0111, RDP0112). This procedure will be replicated for all sites.

    6.3.1 Phase 1: Replacement of the First RDP and Live vs. Test Comparison
    1. Selection: Identify the first RDP server for replacement (e.g., MAW Group B: RDP0112).
    2. New Hardware Installation: The software-pre-installed new server (RDP0112) will physically substitute the existing RDP0112 hardware.
      • Crucially, the existing RDP0111 will remain in oper mode and fully functional, ensuring no disruption to live operations.
    3. Initial Boot & Test Mode Activation: Connect the existing cables to relevant ports on the new RDP0112 server and boot up the system. Immediately upon successful boot, Tidalis will change the node's mode to test: $ vtmis-node change test
    4. Activate and Verify Test Data Path: Verify that the new RDP0112 (in test mode) is successfully feeding data into the pre-configured test data path. This involves checking the communication links to the test mode IP/CSP, CTP/COP, and the test mode DP.
    5. Live vs. Test Track Comparison (Initial SAT): With the test system fully active, Tidalis will conduct the crucial comparison. This involves:
      • Live View: Observing the operational tracks on a live Data Processor (DP) which is receiving data from the production system (including the existing RDP0111 in oper mode).
      • Test View: Simultaneously observing the tracks on the dedicated test Data Processor (DP), which is displaying data processed through the new RDP0112 and the entire test data path (test mode IP/CSP, CTP/COP).
      • This parallel comparison allows for a direct visual assessment of the final track data from the new hardware against the live, trusted system. It validates the integrity, accuracy, and performance of the entire new processing chain without impacting live operations. Any discrepancies will be identified and addressed.
    6. Transition to Operational Mode (if successful): If the comparison confirms satisfactory performance and data consistency, Tidalis will transition the new RDP0112 to oper mode: $ vtmis-node change oper
    7. Operational Verification: Confirm that the new RDP0112 is now fully integrated and operating correctly in oper mode alongside the existing RDP0111.
    6.3.2 Phase 2: Replacement of the Second RDP and Final Site Integration
    1. Selection: Identify the second RDP server for replacement (e.g., MAW Group A: RDP0111).
    2. New Hardware Installation: The software-pre-installed new server (RDP0111) will physically substitute the existing RDP0111 hardware.
      • At this point, the newly installed RDP0112 will be in oper mode, maintaining continuous operation during this replacement.
    3. Initial Boot & Operational Mode: Connect the existing cables to relevant ports on the new RDP0111 server and boot up the system. The server will be brought online in oper mode (or transitioned to oper mode after an initial boot).
    4. High Availability & Final Site SAT: Once both new RDPs (RDP0111 and RDP0112) are installed and operating in oper mode, Tidalis will confirm high availability is supported by both groups. A comprehensive Site Acceptance Test (SAT) will then be conducted for the entire RADAR-subsystem at the site. This SAT will ensure both new RDPs function seamlessly together and meet all operational requirements.
    5. Nursing Period Initiation: If all SAT criteria pass, the nursing period will be initiated for this site.