| 1 | Payroll Calculation Errors (tax, social security, ELStAM, collective-agreement rules) | High | Critical | • Parallel run for two full cycles (Admin Lead + Finance) – sign-off required before go-live. • External German payroll auditor reviews first live payroll file 48 h before submission (contracted, budget reserved). • Checklist of 25 critical test cases (new hire, sick pay, bonus, termination, etc.) – must pass 100 %. |
| 2 | Missing or Corrupted Employee Data (bank details, tax class, SV-IDs, historical balances) | Medium | High | • Data-reconciliation script run nightly during migration week (IT + new provider). • Employee self-validation portal open for 5 days before go-live – each employee confirms bank & address data (HR sends reminder mails). • Rollback plan: keep old provider on “hot-standby” for 4 weeks (contract clause). |
| 3 | Late or Failed File Transmission to Banks / Tax Office / Social Security | Medium | High | • Dry-run of all outbound interfaces 3 days before cut-off (IT + provider). • Dual submission path: primary SFTP + manual upload token stored in safe. • Daily cut-off calendar pinned in Admin & Finance Teams channels; escalation phone list printed. |
| 4 | Employee Panic / Queries Overload (new pay-slip layout, ESS login failures) | High | Medium | • “Payroll Change” FAQ & short video sent 10 days before go-live (HR). • Dedicated hotline (HR + provider help-desk) on pay-slip day; 2 extra staff scheduled. • Betriebsrat briefing 1 week prior to reinforce trust. |
| 5 | Works Council (Betriebsrat) Last-Minute Objection | Low | Critical | • Obtain written co-determination clearance (Betriebsvereinbarung) before system configuration starts (HR PM). • Include Betriebsrat rep in UAT sign-off to avoid surprises. |
| 6 | Key-Person Dependency – Admin Lead unavailable on go-live day | Medium | High | • Shadow payroll run by second trained Admin member during parallel run. • Emergency delegation matrix posted on Teams; printed copy in safe. |
| 7 | DSGVO / Data Breach during cut-over | Low | Critical | • VPN-only access to new provider during migration (IT). • Data-processing audit report from provider dated < 6 months; reviewed by DPO. • Incident-response playbook rehearsed with provider (1 h tabletop drill). |
| 8 | Cash-Flow Disruption due to Incorrect Net-Pay Totals | Medium | High | • Pre-approved overdraft increase with house bank for 2 payroll cycles (Finance). • Same-day correction SEPA batch template pre-loaded in banking software. |
| 9 | Vendor SLA Breach (missed response time on go-live day) | Medium | Medium | • Penalty clause activated if P1 ticket not solved within 2 h (contract). • Named escalation contacts exchanged 1 week before go-live; mobile numbers verified. |
| 10 | Integration Failure with Time-Clock / ERP | Medium | Medium | • End-to-end interface test with last month’s raw data (IT + provider). • Manual import template kept ready as fallback; tested once during UAT. |