30 / 45 Which of the following team-level events does SAFe recommend running on a cadence during the PI for SAFe Team Kanban Teams? System Demo PO Sync Coach Sync Retrospective
- Assistant
For SAFe Team Kanban teams during the Program Increment (PI), the recommended team-level event to run on a cadence is the Retrospective.
Here's why:
- System Demo: This is typically an ART-level event (or higher), demonstrating the integrated work of multiple teams.
- PO Sync: This is a program-level event involving Product Owners, not a team-level event.
- Coach Sync: This is a sync meeting among Agile coaches, not a team-level event for Kanban teams.
- Retrospective: This is a team-level event recommended for all Agile teams (Scrum or Kanban) to reflect on their process and adapt.
Answer: Retrospective