please correct: A. Starboard Main Engine Alignment • Stbd Main engine foot plates (4…
- User
please correct: A. Starboard Main Engine Alignment • Stbd Main engine foot plates (4 pcs) machining at FAG expected to be completed today. • Reinstallation of foot plates is scheduled today afternoon once foot plates are delivered after machining. Once inserted, deflection reading will be checked and if found not critical bolt tightening and torquing will proceed. • Seal pressure is currently on hold to 9PSI to be increased up to 15PSI. • Divers are requested for underwater checking during the shaft adjustment
- Assistant
Here's a corrected and polished version of your text:
A. Starboard Main Engine Alignment
- Machining of the four starboard main engine foot plates at FAG is expected to be completed today.
- Reinstallation of the foot plates is scheduled for this afternoon, once they are delivered after machining. After installation, deflection readings will be checked. If the readings are within acceptable limits, bolt tightening and torquing will proceed.
- Seal pressure is currently on hold at 9 PSI, with plans to increase it to 15 PSI.
- Divers are requested for underwater inspection during the shaft adjustment.
Let me know if you need any further modifications!
- User
Please correct: A. Site services unmooring crew • Tug will be request to assist the vessel to the seatrial location given the current rought sea condition. • Felix and Jomve will be the assigned the point person during the operation. B. Design attendance during seatrial • Nap to provide a team to check the vibration during seatrial operation C. Seatrial Test • Gally to lead the seatrial and record all data, Ating to assist.
- Assistant
Here’s a corrected and polished version of your text:
A. Site Services Unmooring Crew
- A tug will be requested to assist the vessel in reaching the sea trial location, given the current rough sea conditions.
- Felix and Jomve will be assigned as the point persons during the operation.
B. Design Attendance During Sea Trial
- Nap will provide a team to monitor vibration during the sea trial operation.
C. Sea Trial Test
- Gally will lead the sea trial and record all data, with Ating assisting.
Feel free to reach out if you need any more adjustments!
- User
please correct: A. Folded Mast • Awaiting for the counterbalance and solenoid valves for the operational testing of folded mast. • Robert has provide the specs for the counterbalance and solenoid valves. PR to be raised by Neil for SCM to expedite the ordering and delivery within today. B. Stagedown of scaffolds – end user to provide update of their work completion • Stbd Aft ramp scaffolding – proceed to be removed today • Engine room scaffolding – to be removed on Sunday. Gally/Philibert to update Felix once all works are done to with proceed the scaffold removal. • Mast scaffolding - to be removed on Sunday after completion of folded mast operational testing.
- Assistant
Here’s a corrected and polished version of your text:
A. Folded Mast
- We are awaiting the counterbalance and solenoid valves for the operational testing of the folded mast.
- Robert has provided the specifications for the counterbalance and solenoid valves. Neil will raise a purchase requisition (PR) for SCM to expedite the ordering and delivery by the end of today.
B. Stagedown of Scaffolds – End User to Provide Update on Work Completion
- Starboard aft ramp scaffolding will be removed today.
- Engine room scaffolding is scheduled to be removed on Sunday. Gally and Philibert will update Felix once all work is completed to proceed with the scaffold removal.
- Mast scaffolding will be removed on Sunday after the completion of the folded mast operational testing.
Let me know if you need any further modifications!