please correct: Hello Team, Sharing the minutes of meeting for the discussion of seatrial. Final schedule of seatrial is on Monday, actual time will depend on the final alignment result and mast operational testing.
Seatrial Schedule: • Basin Trial and operational test: March 2, 2025 • Movement and Preparation: March 3, 2025 at 7:00am-11:00am • Seatrial Operation: March 3, 2025 at 1:00pm-5:00pm
Outstanding Works: • Stbd Main Engine Final alignment – Awaiting for the machined engine foot plates, scheduled to be installed for today once engine foot plates are delivered. After installation, deflection will be checked and if found within acceptable limits bolt tightening and torquing will follows. • Stbd Exhaust and Pipe reinstatement to Main Engine – scheduled tonight once stbd main engine alignment is done. • Folded mast operational testing – awaiting for the counterbalance and solenoid valves. SCM now expediting the delivery which is expected this afternoon around 2-3pm.
• Scaffolds removal – stbd aft ramp accommodation ladder scaffold now can be removed, retained scaffolds at engine room and folded mast are scheduled to be removed on Sunday. - Assistant
Subject: Minutes of Meeting - Seatrial Discussion
Hello Team,
I am sharing the minutes of the meeting regarding the seatrial discussion. The final schedule for the seatrial is set for Monday, with the exact timing dependent on the results of the final alignment and mast operational testing.
Seatrial Schedule:
- Basin Trial and Operational Test: March 2, 2025
- Movement and Preparation: March 3, 2025, from 7:00 AM to 11:00 AM
- Seatrial Operation: March 3, 2025, from 1:00 PM to 5:00 PM
Outstanding Works:
- Starboard Main Engine Final Alignment: We are awaiting the machined engine foot plates, which are scheduled to be installed today upon arrival. After installation, deflection will be checked, and if within acceptable limits, bolt tightening and torquing will follow.
- Starboard Exhaust and Pipe Reinstatement to Main Engine: This is scheduled for tonight after the starboard main engine alignment is completed.
- Folded Mast Operational Testing: We are awaiting the delivery of the counterbalance and solenoid valves. SCM is currently expediting the delivery, which is expected this afternoon around 2-3 PM.
- Scaffold Removal: The scaffolding for the starboard aft ramp accommodation ladder can now be removed. The remaining scaffolds in the engine room and for the folded mast are scheduled to be removed on Sunday.