1 Introduction
This report presents the project planning and management aspects for the development of the shared bike software system commissioned by the local government. The purpose of this report is to detail the Project Scope Management and Project Schedule Management plans, ensuring that the project is completed successfully within the stipulated time frame and meets all specified requirements.
The local government has launched an initiative to address urban challenges such as increasing traffic congestion and deteriorating air quality. To promote a healthier and more sustainable lifestyle, they have introduced a shared bike program. Our company has been contracted to develop the software system integral to the operation of this program. This software will facilitate bike rentals and returns, manage the bike fleet, provide a user-friendly mobile application, integrate pricing and payment systems, and support operations and customer service.
We need to conduct this project to deliver a robust and efficient software platform that meets the government's requirements, contributing to the overall success of the shared bike program and, consequently, to the improvement of urban living conditions.
Team Charter
The project team comprises experienced professionals dedicated to delivering high-quality results within the project's constraints. The team members and their roles are as follows:
Name Role Responsibilities
Leo Project Manager Overall project management, scheduling, resource allocation, stakeholder communication
Bill Senior Developer Analysis and design, software architecture, database design
Lisa Developer UI/UX design, client-side coding
Andy Developer Server-side coding, integration
Kent Developer Client-side coding, testing
Vision: Our vision is to contribute to the transformative initiative of the shared bike program by delivering a state-of-the-art software system that will ease urban congestion, improve air quality, and promote a sustainable and healthy lifestyle for city dwellers.
Mission: To develop and deploy a robust, user-friendly, and secure software system that facilitates bike rentals, manages the bike fleet efficiently, integrates seamless payment options, and supports comprehensive customer service, ultimately contributing to the program's success.
Report Structure
The structure of this report is as follows:
• Section 2 Project Scope Management: Presents the Work Breakdown Structure (WBS) of the project, detailing all tasks and deliverables in a hierarchical tree structure.
• Section 3 Project Schedule Management: Includes the project schedule with necessary elements, the Network Diagram using the Precedence Diagramming Method (PDM), and a Critical Path Analysis (CPA).
• …
2 Project Scope Management
In this section, we present the Work Breakdown Structure (WBS) for the shared bike software system project and the corresponding Gantt Chart. The WBS outlines all tasks and deliverables in a structured hierarchical format, ensuring a comprehensive understanding of the project's scope.
2.1 Work Breakdown Structure (WBS)
The project is divided into four main phases: Analysis, Design, Implementation, and Deployment. Each phase consists of specific tasks required to meet the project's objectives.
Assistant
Other models, same or similar prompt
Responses were produced in different, uncontrolled contexts (system prompts, settings, prior turns). This is not a benchmark.
WBS Dictionary
Below is a brief description of each task in the WBS:
• Analysis
o a: Conduct a background study on e-payment implementations in similar projects to gather best practices and potential pitfalls.
o b: Collect detailed requirements from relevant government departments regarding design preferences, compliance standards, and user needs.
o c: Develop a prototype to demonstrate the payment procedure and gather early feedback.
• Design
o d: Design the overall software architecture, defining the system components and their interactions.
o e: Design the database schema to support all required functionalities.
o f: Design end-user interfaces for mobile applications, focusing on user experience and accessibility.
o g: Design interfaces for administrative functions on desktop computers.
o h: Design the signal connection mechanisms with bike locks for control operations.
o i: Design the security scheme to safeguard transactions over the internet, ensuring data protection and compliance.
o j: Develop interface templates for review, including layout, navigation, and visual elements.
o k: Create a site map or hierarchy chart to illustrate the flow of web pages and user interactions.
• Implementation
o l: Create individual web pages based on the approved designs.
o m: Create the database as per the designed schema.
o n: Source necessary library modules for client-side coding to enhance development efficiency.
o o: Purchase a set of bike locks for coding and testing purposes.
o p: Code server-side modules for system administration and operations.
o q: Code server-side modules for end-user services.
o r: Code client-side modules for system administration and operations.
o s: Code client-side modules for end-user services.
o t: Integrate server-side modules and web pages to form a cohesive system.
• Deployment
o u: Test the connection to bike locks with the shared-bike app to ensure proper functionality.
o v: Perform performance stress tests on the system to verify handling of transactions and concurrent users.
o w: Conduct User Acceptance Testing (UAT) with the sponsor and end-user representatives.
o x: Install the website on the government's web server for operation.
o y: Create technical training materials for staff.
o z: Train staff in operating and maintaining the system.
2.2 Gantt Chart
The Gantt Chart below visualizes the project schedule, illustrating task durations and dependencies to ensure a clear understanding of the project timeline.
Note: The start date is set as 01-01-2024. The milestones are set to the dates provided by the sponsor:
• Prototype Delivery Milestone (m1): Prototype must be delivered within two months (by 01-03-2024).
• Intermediate Modules Milestone (m2): Intermediate modules must be delivered within five months (by 01-06-2024).
• Project Completion Milestone (m3): Project must be fully completed within eight months (by 01-09-2024).
Task Dependencies and Durations
The table below outlines each task's duration and dependencies:
Activity ID Activity Name Duration (Days) Predecessors
a Background study on e-payment implementation 18 -
b Requirements Analysis 20 a
c Technical Feasibility Study 22 b
d System Design 25 b
e Module Design 15 d
f Interface Design 25 d
g Database Design 15 f
h UI Design 15 d
i Security Design 20 d
j Integration Testing 12 f, g
k System Testing 12 j
l Coding Core Modules 30 k
m Coding Module E 20 e
n Coding Module F 20 f
o Develop UI 12 h
p Database Implementation 25 i, g
q Security Implementation 30 i
r Testing Module N 25 n
s Testing Module S 25 n
t Final Integration 20 l, m, p, q, r, s
u Deployment Preparation 5 t, o
v System Deployment 5 u
w User Training 5 v
x Project Handover 12 w
y Post-Deployment Support 20 x
z Project Closure 19 y
3 Project Schedule Management
In this chapter, we present the project schedule management plan, including the Network Diagram in Precedence Diagramming Method (PDM) format, and conduct a Critical Path Analysis (CPA).
3.1 Network Diagram in PDM
The following network diagram represents the project's activities using the Precedence Diagramming Method (PDM). Each node corresponds to a task identified by its activity ID.
Legend:
• Nodes represent tasks labeled from a to z.
• Arrows indicate task dependencies.
3.2 Critical Path Analysis
Critical Path Analysis (CPA) identifies the sequence of tasks that determines the minimum project duration. Tasks on the critical path have zero slack.
3.2.1 Forward Pass (Calculating Early Start and Early Finish)
Task Duration (Days) Predecessors Early Start (ES) Early Finish (EF)
a 18 - 0 18
b 20 a 18 38
c 22 b 38 60
d 25 b 38 63
e 15 d 63 78
f 25 d 63 88
g 15 f 88 103
h 15 d 63 78
i 20 d 63 83
j 12 f, g 103 115
k 12 j 115 127
l 30 k 127 157
m 20 e 78 98
n 20 f 88 108
o 12 h 78 90
p 25 i, g 103 128
q 30 i 83 113
r 25 n 108 133
s 25 n 108 133
t 20 l, m, p, q, r, s 157 177
u 5 t, o 177 182
v 5 u 182 187
w 5 v 187 192
x 12 w 192 204
y 20 x 204 224
z 19 y 223 243
3.2.2 Backward Pass (Calculating Late Start and Late Finish)
Assuming the project's finish time is 244 days.
Here's the completed backward pass table:
Task Duration (Days) Successors Late Finish (LF) Late Start (LS) Slack (LS - ES)
z 19 - 243 223 0
y 20 z 224 204 0
x 12 y 204 192 0
w 5 x 192 187 0
v 5 w 187 182 0
u 5 v 182 177 0
t 20 u 177 157 0
l 30 t 157 127 0
k 12 l 127 115 0
j 12 k, p 115 103 0
g 15 j, p 103 88 0
p 25 t 152 127 24
q 30 t 152 122 39
m 20 t 157 132 54
e 15 m 132 117 54
d 25 e, f, h, i 63 38 0
f 25 g, j, n 88 63 0
r 25 t 152 127 19
s 25 t 152 127 19
n 20 r, s 127 107 39
i 20 p, q 122 102 42
o 12 u 177 165 87
h 15 o 165 150 87
b 20 d, c 38 18 0
a 18 b 18 0 0
c 22 - 60 38 0
3.2.3 Identifying the Critical Path
Tasks with zero slack form the critical path. The critical path for this project is:
• a - b - d - f - g - j - k - l - t - u - v - w - x - y - z
Project Duration: 8 months, 243 days (Including holidays)
4 Project Budget Management
In this chapter, we detail the Project Cost Management plan, including resource allocation, cost baseline, and Earned Value Management (EVM) analysis. We also present the performance measurements, variance analysis, and forecasting based on the project’s progress at the end of the fourth month.
4.1 Resource Sheet
Below is the Resource Sheet summarizing all the resources involved in the project, their hourly rates, total hours worked, and total costs.
Table 4.1: Resource Sheet
Resource Rate (/hr)orUnitCost() Total Units or Hours Total Cost ()HumanResourcesProjectManager(PM)500/hr 984 hours 492,000Bill(SeniorDeveloper)300/hr 1,776 hours 532,800Lisa(Developer)200/hr 1,336 hours 267,200Andy(Developer)200/hr 1,552 hours 310,400Kent(Developer)200/hr 1,288 hours 257,600SubtotalHumanResources6,936hours1,860,000
Equipment Purchases
Mobile Phones 800/unit5units4,000
Bike Locks with Connectivity 1,000/unit10units10,000
Total Equipment Purchases 14,000OtherCostsComputingFacilitiesRental29,000/month 8 months 232,000SubtotalOtherCosts246,000
Total (Before Contingency) 2,120,000ContingencyReserve(20424,000
Total Project Cost $2,544,000
Notes:
Based on the project schedule and team capabilities, tasks have been assigned to team members to ensure efficient utilization of skills and fair distribution of workload among team members, excluding the Project Manager (PM). The PM oversees the entire development process and participates in key tasks.
Table 4.1.1: Work Breakdown Structure (WBS) with Resource Assignments
WBS ID Task Name Duration (Days) Assigned To
1 Analysis Phase
1.1 Background study on e-payment implementation 18 Bill
1.2 Requirements Analysis 20 Bill, PM
1.3 Technical Feasibility Study 22 Bill, PM
2 Design Phase
2.1 System Design 25 Bill, PM
2.2 Module Design 15 Bill, Lisa
2.3 Interface Design 25 Lisa, Kent
2.4 Database Design 15 Bill, Andy
2.5 UI Design 15 Lisa, Kent
2.6 Security Design 20 Bill, Andy
2.7 Integration Testing 12 Andy, Kent
2.8 System Testing 12 Andy, Kent
3 Implementation Phase
3.1 Coding Core Modules 30 Lisa, Andy
3.2 Coding Module E 20 Lisa
3.3 Coding Module F 20 Kent
3.4 Develop UI 12 Lisa, Kent
3.5 Database Implementation 25 Bill, Andy
3.6 Security Implementation 30 Bill, Andy
3.7 Testing Module N 25 Kent
3.8 Testing Module S 25 Lisa
3.9 Final Integration 20 All Team Members
4 Deployment Phase
4.1 Deployment Preparation 5 PM, Andy
4.2 System Deployment 5 Andy
4.3 User Training 5 Lisa
4.4 Project Handover 12 PM, Bill
4.5 Post-Deployment Support 20 Andy, Kent
4.6 Project Closure 19 PM
Resource Assignments Summary
o Project Manager (PM): Participates in tasks 1.2, 1.3, 2.1, 3.9, 4.1, 4.4, and 4.6.
o Bill (Senior Developer): Leads analysis and design tasks; involved in tasks 1.1 to 2.6, 3.5, 3.6, 3.9, and 4.4.
o Lisa (Developer): Focuses on UI/UX design and client-side coding; involved in tasks 2.2, 2.3, 2.5, 3.1 to 3.4, 3.8, 3.9, and 4.3.
o Andy (Developer): Handles server-side coding and integration; involved in tasks 2.4, 2.6, 2.7, 2.8, 3.1, 3.5, 3.6, 3.9, 4.1, 4.2, and 4.5.
o Kent (Developer): Works on client-side coding and testing; involved in tasks 2.3, 2.5, 2.7, 2.8, 3.3, 3.4, 3.7, 3.9, and 4.5.
Market Study on Needed Equipment
As part of the project's hardware requirements, the following equipment is needed for development and testing purposes:
Mobile Phones (5 units):
o Purpose: To test the mobile application on various devices.
o Estimated Market Price per Unit: 800oTotalCost:5units∗800/unit = $4,000
Bike Locks with Connectivity (10 units):
o Purpose: To develop and test signal connection mechanisms with bike locks.
o Estimated Market Price per Unit: 1,000oTotalCost:10units∗1,000/unit = $10,000
Computers and Peripherals:
o Note: The computing facilities are rented monthly and covered separately under computing facilities rental costs.
Total Equipment Purchases: 4,000(MobilePhones)+10,000 (Bike Locks) = $14,000
4.2 Cost Baseline (Budget Schedule)
The Cost Baseline outlines the planned expenditures over the project’s duration, including the Contingency Reserve to account for potential risks.
Table 4.2: Cost Baseline
Month PM ()Bill() Lisa ()Andy() Kent ()ComputingFacilities() Equipment Purchases ()PlannedCost() Contingency Reserve (20%) Cumulative Planned Cost (14,000 for mobile phones and bike locks.
o Computing Facilities Rental: $29,000 per month for 8 months.
o Contingency Reserve: Calculated as 20% of the monthly Planned Cost.
4.3 Planned Values (PVs) for the 8 Months
Table 4.3: Cumulative Planned Values
Month Cumulative Planned Value (PV) ()1330,6002644,4003958,20041,272,00051,585,80061,899,60072,213,40082,527,2004.4EarnedValueManagement(E1,272,000 (from the Cost Baseline)
• Actual Cost (AC): 1,320,000(actualexpenditureincurred 1,200,000 (value of work actually completed)
4.4.1 EVM Calculations
• Cost Variance (CV):
CV = EV - AC
CV = 1,200,000−1,320,000
CV = -120,000•NegativeCVindi1,200,000 - 1,272,000SV=−72,000
• Negative SV indicates the project is behind schedule.
• Cost Performance Index (CPI):
CPI = EV / AC
CPI = 1,200,000/1,320,000
CPI ≈ 0.9091
• CPI less than 1 indicates poor cost efficiency.
• Schedule Performance Index (SPI):
SPI = EV / PV
SPI = 1,200,000/1,272,000
SPI ≈ 0.9434
• SPI less than 1 indicates the project is progressing slower than planned.
• Estimate at Completion (EAC):
EAC = BAC / CPI
EAC = 2,527,200/0.9091EAC≈2,780,000
• EAC projects the total cost at completion based on current performance.
• Estimated Time to Complete (ETC):
ETC = Original Duration / SPI
ETC = 8 months / 0.9434
ETC ≈ 8.48 months
• ETC estimates the total project duration based on current schedule performance.
• Variance Analysis
• Cost Variance (CV): The project is over budget by 72,000 worth of work, meaning less work has been completed than planned up to this point.
• Cost Performance Index (CPI): At 0.9091, the project is not utilizing its budget efficiently.
• Schedule Performance Index (SPI): At 0.9434, the project is progressing slower than planned.
4.5 EVM Graph
Figure 4.5: EVM Graph at End of Month 4
Note: The EVM graph plots the cumulative values of PV, EV, and AC over the project duration.
4.6 Project Performance and Forecasting Description
At the end of the fourth month, the project is experiencing both schedule delays and cost overruns. The Schedule Variance (SV) of -72,000andSchedulePerformanceIndex(SPI)of0.9434indicatethattheprojectisbehin120,000 and Cost Performance Index (CPI) of 0.9091 reveal that the project is over budget, spending more than the value of the work completed. Possible reasons include:
o Extended Work Hours: Team members may have worked overtime to address challenges, increasing labor costs.
o Unexpected Expenses: Additional costs, such as higher equipment prices or extra resources, may not have been anticipated.
The Estimate at Completion (EAC) projects the total project cost to be approximately 2,780,000,exceedingtheoriginalbudget252,800. The project is also projected to extend to approximately 8.5 months, nearly half a month beyond the planned duration.
To address these issues, we need to:
• Analyze the Causes: Investigate the reasons for schedule delays and cost overruns, such as scope changes, resource inefficiencies, or technical challenges.
• Implement Corrective Actions: Reallocate resources, optimize processes, and implement cost-saving measures to improve CPI and SPI.
• Update the Schedule and Budget: Adjust the project plan to reflect realistic timelines and costs, ensuring that stakeholders are informed of any changes.
By taking proactive steps, we aim to bring the project back on track, minimize the cost overrun, and meet the project’s objectives within the adjusted budget and schedule.
5 Project Resource Management
In this chapter, we delve into the project's resource management aspects, focusing on the team dynamics, responsibility assignments, and workload distribution. Effective resource management ensures that the project progresses smoothly, with clear roles, efficient collaboration, and balanced workloads among team members.
5.1 Team Charter
Project Purpose
The Shared Bike App Platform project aims to develop a comprehensive software system to support the local government's shared bike program. This initiative addresses urban challenges by promoting sustainable transportation, reducing traffic congestion, and improving air quality.
Team Mission
Our mission is to collaboratively develop and deploy a high-quality software system that fulfills all specified requirements, meets user needs, and is delivered on time and within budget constraints. We strive to maintain a positive team environment that encourages innovation, professional growth, and a shared commitment to excellence.
Team Vision
Our vision is to be a cohesive and high-performing team that delivers a state-of-the-art software platform for the shared bike program. We aim to contribute significantly to sustainable urban living and set a benchmark for future projects in public transportation and environmental initiatives.
Team Goals
o Deliver on Schedule and Budget: Complete the project within the stipulated time frame and budget.
o Meet Quality Standards: Ensure the software meets all government specifications, compliance standards, and user requirements.
o Effective Communication: Foster open and efficient communication channels within the team and with stakeholders.
o Continuous Improvement: Encourage learning and professional development among team members.
o Customer Satisfaction: Achieve high satisfaction levels from the sponsor and end-users through reliable and user-friendly solutions.
Team Members and Roles
o Leo (Project Manager)
o Responsibilities: Overall project management, scheduling, resource allocation, stakeholder communication, conflict resolution, risk management, and ensuring project objectives are met.
o Bill (Senior Developer)
o Responsibilities: Leading analysis and design phases, software architecture, database design, mentoring developers, overseeing technical quality, and ensuring adherence to best practices.
o Lisa (Developer)
o Responsibilities: UI/UX design, client-side coding, interface development, user experience optimization, and creating technical training materials.
o Andy (Developer)
o Responsibilities: Server-side coding, system integration, implementation of security features, performance optimization, and deployment preparation.
o Kent (Developer)
o Responsibilities: Client-side coding, testing, quality assurance, assisting with UI/UX development, and post-deployment support.
Core Values
o Collaboration: We value teamwork and believe that collaborative efforts lead to superior outcomes.
o Integrity: We commit to honesty and transparency in all interactions.
o Excellence: We strive for the highest quality in our work and continuously seek ways to improve.
o Respect: We treat each other with respect and value diverse perspectives and contributions.
o Accountability: We take responsibility for our actions and their impact on the project and team.
Communication Guidelines
o Meetings:
o Team Meetings: Held twice a week on Mondays and Thursdays at 10 AM to discuss progress, issues, and plans.
o Stakeholder Meetings: Scheduled as needed to provide updates and gather feedback.
o Communication Channels:
o Email: For formal communications and documentation.
o Instant Messaging (Slack): For quick questions and discussions.
o Video Conferencing (Zoom/Teams): For virtual meetings and presentations.
o Reporting:
o Team members submit weekly progress reports every Friday by 5 PM.
o The Project Manager compiles and distributes a weekly project status report to stakeholders.
Decision-Making Guidelines
o Consensus-Based Approach: Decisions are made collaboratively, seeking input from all relevant team members.
o Escalation: If consensus cannot be reached, the Project Manager will make the final decision after considering all perspectives.
o Documentation: All significant decisions are documented and shared with the team.
Conflict Resolution Guidelines
o Direct Communication: Team members address conflicts directly and respectfully with the involved parties.
o Mediation: The Project Manager acts as a mediator if conflicts cannot be resolved between individuals.
o Focus on Issues: Discussions focus on resolving the issue at hand, not personal attributes.
Meeting Guidelines
o Preparation: Agendas are distributed before meetings, and team members are expected to come prepared.
o Punctuality: Meetings start and end on time.
o Participation: All team members are encouraged to actively participate and share their insights.
o Action Items: Responsibilities and deadlines are clearly assigned during meetings.
Team Agreements
o Availability: Team members inform the Project Manager of any planned absences at least two weeks in advance.
o Responsiveness: Team members respond to communications within 24 hours.
o Quality Commitment: Adherence to coding standards, documentation requirements, and testing protocols is mandatory.
o Support and Collaboration: Team members support each other and share knowledge to overcome challenges.
Team Performance Assessment
o Regular Reviews: The Project Manager conducts monthly performance reviews with each team member.
o Feedback Mechanism: Constructive feedback is provided promptly to acknowledge achievements and address any issues.
o Recognition: Exceptional contributions are recognized during team meetings and in project communications.
5.2 RACI Chart
The RACI chart outlines the roles and responsibilities of team members for each project task, ensuring clarity and accountability. It aligns tasks with team members' skills and expertise, facilitating effective collaboration.
Legend:
o R (Responsible): The person(s) who perform the task.
o A (Accountable): The person who is ultimately accountable and has authority.
o C (Consulted): The person(s) who need to be consulted before a decision or action.
o I (Informed): The person(s) who need to be informed after a decision or action.
RACI Chart for Project Tasks (a to z)
Task ID Task Name Leo (PM) Bill (SD) Lisa (D1) Andy (D2) Kent (D3)
a Background study on e-payment implementation C R/A I I I
b Requirements Analysis R/A R I I I
c Develop prototype for payment procedure I A R C C
d Design overall software architecture I R/A C C I
e Design database schema I R/A I C I
f Design end-user interfaces for mobile applications I C R/A I C
g Design admin interfaces for desktop computers I C A I R
h Design signal connection mechanisms with bike locks I C I R/A I
i Design security scheme I C I R/A I
j Develop interface templates for review I I R/A C C
k Create site map/hierarchy chart I C R/A I C
l Create individual web pages I C R I R
m Create the database I A I R I
n Source client-side coding libraries I I C I R/A
o Purchase bike locks R/A C I C I
p Code server-side modules for admin and operations I C I R/A I
q Code server-side modules for end-user services I C I R/A I
r Code client-side modules for admin and operations I C C I R
s Code client-side modules for end-user services I C R I C
t Integrate server-side modules and web pages I C C R/A C
u Test connection to bike locks with app I C C R/A C
v Perform performance stress tests I C I C R/A
w Conduct User Acceptance Testing (UAT) R/A C C I I
x Install website on government's web server I C I R/A I
y Create technical training materials for staff A C R I I
z Train staff in operating and maintaining the system A C R C I
5.3 Resource Histogram
The Resource Histogram illustrates the distribution of work among team members over the project's duration. It helps identify periods of high or low workload, enabling the Project Manager to balance resources effectively.
Methodology
Project Timeline Division: The 8-month project duration is divided into 16 two-week periods.
Task Scheduling: Tasks are mapped to these periods based on their start and finish dates.
Workload Calculation:
o For each task assigned to a team member, we calculate the number of hours they work during each period.
o A standard work schedule of 8 hours per day and 5 workdays per week (40 hours per week).
o If a task spans multiple periods, the workload is distributed accordingly.
Resource Histogram Data
Total Work Hours per Team Member:
o Leo (PM): 984 hours
o Bill (SD): 1,776 hours
o Lisa (D1): 1,336 hours
o Andy (D2): 1,552 hours
o Kent (D3): 1,288 hours
Work Hours Distribution:
Below is the distribution of work hours for each team member across the 16 periods.
Period Definitions:
o Period 1: Days 0-13 (Jan 1 - Jan 14)
o Period 2: Days 14-27 (Jan 15 - Jan 28)
o Period 3: Days 28-41 (Jan 29 - Feb 11)
o Period 4: Days 42-55 (Feb 12 - Feb 25)
o Period 5: Days 56-69 (Feb 26 - Mar 10)
o Period 6: Days 70-83 (Mar 11 - Mar 24)
o Period 7: Days 84-97 (Mar 25 - Apr 7)
o Period 8: Days 98-111 (Apr 8 - Apr 21)
o Period 9: Days 112-125 (Apr 22 - May 5)
o Period 10: Days 126-139 (May 6 - May 19)
o Period 11: Days 140-153 (May 20 - Jun 2)
o Period 12: Days 154-167 (Jun 3 - Jun 16)
o Period 13: Days 168-181 (Jun 17 - Jun 30)
o Period 14: Days 182-195 (Jul 1 - Jul 14)
o Period 15: Days 196-209 (Jul 15 - Jul 28)
o Period 16: Days 210-223 (Jul 29 - Aug 11)
Work Hours per Team Member per Period:
(Note: The following is an estimated distribution based on task assignments and durations.)
Period Leo (PM) Hours Bill (SD) Hours Lisa (D1) Hours Andy (D2) Hours Kent (D3) Hours
1 24 80 0 0 0
2 40 80 0 0 0
3 40 80 0 0 0
4 40 64 48 0 0
5 24 64 80 16 16
6 0 64 80 80 64
7 0 64 64 80 80
8 0 64 64 80 80
9 0 64 64 80 80
10 0 40 40 80 80
11 0 0 0 64 64
12 0 0 0 64 40
13 16 16 16 16 16
14 40 0 0 0 0
15 40 0 80 0 0
16 40 16 0 0 0
Total 304 696 536 560 520
Explanation:
o Periods 1-3: Leo and Bill focus on analysis and design tasks. Leo (PM) spends time on requirements analysis and feasibility studies.
o Periods 4-5: Lisa and Kent begin UI/UX design tasks, while Andy starts initial development tasks.
o Periods 6-10: Core development phase where all developers are heavily involved in coding and integration.
o Periods 11-12: Andy and Kent focus on testing and deployment preparation.
o Periods 13-16: Leo resumes significant involvement for UAT, training, and project closure. Lisa assists with training materials.
Resource Histogram Visualization
A bar chart (histogram) can be created to visualize the above data, with periods on the x-axis and work hours on the y-axis. Each team member's workload can be represented by a colored bar for each period.
Sample Histogram:
Due to the constraints of this document format, please refer to the attached chart or spreadsheet for the visual representation of the Resource Histogram.
Analysis and Workload Balancing
o Peak Periods: Periods 6-10 show the highest workload for developers, aligning with the intensive coding and integration phase.
o Leo's Involvement: The Project Manager's workload is heavier during early analysis and late-stage activities like UAT and project closure.
Project Risk Management
You are required to conduct a risk analysis for your project. Identify two incidences that could
potentially inflict risk on your project in the future, necessitating changes to keep the project on
track for success. You need to conduct evaluation on the incidences in terms of their
probabilities and impacts toward the project, and propose risk responses and
secondary/residual risks on them and identify the type of risk responses. The risk responses
include adjustments to address the incidence(s) while making an effort to adhere to the original
budget. If the change will result in a budget increase, you must provide a justification for this
increase. Additionally, consider the organizational structure and the procedure for submitting
change requests. Tailor your responses specifically to the context of your project (In other
words, avoid using vague language that could apply to any situation). If possible, include some
intriguing insights. For each incidence, please document your findings in at least 400 words but
no more than 600 words, organized into four paragraphs as follows.
⚫ Incidence (e.g. the sponsor requests the project manager to expedite the project and to
complete it 2 months earlier; a disaster happens; the chief engineer gets sick and is no
longer capable to carry on his/her duties; the delay of delivery of the equipment etc.)
⚫ Anticipated probability and impact on the project (in the 4 project objectives) (e.g. the
project would be impacted by the delay by one month and probably by the increase of
cost due to... etc.)
⚫ Risk response (i.e. propose actions addressing the risks brought by the incidences)
⚫ Potential secondary/residual risks (the potential secondary and residual risks that may
arise for the project if the proposed changes are implemented)
(Make an effort to incorporate as many project management concepts and terminologies as
possible, including considerations of scope, time, cost, quality, and risk. Utilize terms such as
fast-tracking, crashing, contingent plans, secondary risks, contingent reserves, change requests,
critical path analysis, and stakeholder expectations, as well as various risk response
strategies.).
Risk Analysis for Shared Bike Software System Project
Incidence
One critical incidence that could potentially disrupt our project's timeline is a significant delay in the delivery of essential equipment, specifically the bike locks with connectivity, which are required for developing and testing our signal connection mechanisms. These bike locks are vital for enabling user interactions with the physical bike fleet in the shared bike program. If the supplier experiences production issues or logistical problems, this could result in delays that impact the entire development schedule. Given the interdependencies in our project, delays in obtaining the bike locks could cascade through our project timeline, affecting subsequent development tasks and potentially pushing back key milestones such as Prototype Delivery (Milestone m1) and Project Completion (Milestone m3). Such a delay would not only impact time but could also escalate costs due to the need for expedited shipping or alternative procurement methods.
Anticipated Probability and Impact on the Project
The probability of experiencing equipment delivery delays is assessed as moderate to high, given the current global supply chain challenges that various industries are facing. If such a delay occurs, we anticipate a negative impact on the project objectives, particularly time and cost. Specifically, the project could be delayed by one to three months, depending on the severity of the supply chain disruption. This delay could lead to increased labor costs due to extended project durations, especially if the team is obligated to work overtime to meet deadlines once the equipment arrives. Additionally, the quality of the software product may be compromised if we are forced to launch the project with incomplete testing due to equipment unavailability, ultimately affecting user satisfaction and stakeholder expectations. The project timeline relies heavily on critical path activities, making any delays particularly detrimental.
Risk Response
To address the risk posed by potential delays in equipment delivery, we propose implementing a proactive risk response strategy that could include both contingency planning and fast-tracking. Firstly, we will develop a contingency plan that outlines alternative suppliers for bike locks, ensuring that if our primary supplier fails to deliver on time, we can quickly engage a backup vendor to procure the necessary equipment. This secondary supplier could be identified and vetted during the project planning phase. Moreover, we will allocate a contingency reserve of approximately 10% of the total budget specifically earmarked for expedited shipping or other unforeseen costs related to securing the locks. Additionally, we will incorporate fast-tracking techniques in our project schedule where feasible, allowing us to overlap certain development tasks that are not dependent on equipment arrival, thereby mitigating some of the delays caused by waiting for the locks.
Potential Secondary/Residual Risks
While our risk response strategies aim to safeguard the project against equipment delivery delays, they may inadvertently introduce secondary risks. The search for alternative suppliers could lead to negotiations that prolong the procurement process, as vetting new vendors might consume time and resources meant for other project activities. This could contribute to further schedule delays if not carefully managed. Additionally, if we opt for expedited shipping, we potentially face increased costs that could cause us to exceed our original budget unless offset by budget reallocation or cost savings in other areas. The reliance on secondary suppliers also poses a risk regarding quality assurance—there's a possibility that the quality of equipment from alternative vendors may not meet our standards, which could ultimately impact the software testing phase. Therefore, careful management of procurement, along with constant communication with stakeholders regarding potential budget increases due to expedited shipping or alternative sourcing methods, will be essential to navigate these challenges effectively. Change requests will be submitted to seek approval for any additional budget requirements and adjustments in the project schedule, ensuring that all project stakeholders are informed and aligned moving forward.