1 Introduction
This report presents the project planning and management aspects for the development of the shared bike software system commissioned by the local government. The purpose of this report is to detail the Project Scope Management and Project Schedule Management plans, ensuring that the project is completed successfully within the stipulated time frame and meets all specified requirements.
The local government has launched an initiative to address urban challenges such as increasing traffic congestion and deteriorating air quality. To promote a healthier and more sustainable lifestyle, they have introduced a shared bike program. Our company has been contracted to develop the software system integral to the operation of this program. This software will facilitate bike rentals and returns, manage the bike fleet, provide a user-friendly mobile application, integrate pricing and payment systems, and support operations and customer service.
We need to conduct this project to deliver a robust and efficient software platform that meets the government's requirements, contributing to the overall success of the shared bike program and, consequently, to the improvement of urban living conditions.
Team Charter
The project team comprises experienced professionals dedicated to delivering high-quality results within the project's constraints. The team members and their roles are as follows:
Name Role Responsibilities
Leo Project Manager Overall project management, scheduling, resource allocation, stakeholder communication
Bill Senior Developer Analysis and design, software architecture, database design
Lisa Developer UI/UX design, client-side coding
Andy Developer Server-side coding, integration
Kent Developer Client-side coding, testing
Vision: Our vision is to contribute to the transformative initiative of the shared bike program by delivering a state-of-the-art software system that will ease urban congestion, improve air quality, and promote a sustainable and healthy lifestyle for city dwellers.
Mission: To develop and deploy a robust, user-friendly, and secure software system that facilitates bike rentals, manages the bike fleet efficiently, integrates seamless payment options, and supports comprehensive customer service, ultimately contributing to the program's success.
Report Structure
The structure of this report is as follows:
• Section 2 Project Scope Management: Presents the Work Breakdown Structure (WBS) of the project, detailing all tasks and deliverables in a hierarchical tree structure.
• Section 3 Project Schedule Management: Includes the project schedule with necessary elements, the Network Diagram using the Precedence Diagramming Method (PDM), and a Critical Path Analysis (CPA).
• …
2 Project Scope Management
In this section, we present the Work Breakdown Structure (WBS) for the shared bike software system project and the corresponding Gantt Chart. The WBS outlines all tasks and deliverables in a structured hierarchical format, ensuring a comprehensive understanding of the project's scope.
2.1 Work Breakdown Structure (WBS)
The project is divided into four main phases: Analysis, Design, Implementation, and Deployment. Each phase consists of specific tasks required to meet the project's objectives.
Assistant
WBS Dictionary
Below is a brief description of each task in the WBS:
• Analysis
o a: Conduct a background study on e-payment implementations in similar projects to gather best practices and potential pitfalls.
o b: Collect detailed requirements from relevant government departments regarding design preferences, compliance standards, and user needs.
o c: Develop a prototype to demonstrate the payment procedure and gather early feedback.
• Design
o d: Design the overall software architecture, defining the system components and their interactions.
o e: Design the database schema to support all required functionalities.
o f: Design end-user interfaces for mobile applications, focusing on user experience and accessibility.
o g: Design interfaces for administrative functions on desktop computers.
o h: Design the signal connection mechanisms with bike locks for control operations.
o i: Design the security scheme to safeguard transactions over the internet, ensuring data protection and compliance.
o j: Develop interface templates for review, including layout, navigation, and visual elements.
o k: Create a site map or hierarchy chart to illustrate the flow of web pages and user interactions.
• Implementation
o l: Create individual web pages based on the approved designs.
o m: Create the database as per the designed schema.
o n: Source necessary library modules for client-side coding to enhance development efficiency.
o o: Purchase a set of bike locks for coding and testing purposes.
o p: Code server-side modules for system administration and operations.
o q: Code server-side modules for end-user services.
o r: Code client-side modules for system administration and operations.
o s: Code client-side modules for end-user services.
o t: Integrate server-side modules and web pages to form a cohesive system.
• Deployment
o u: Test the connection to bike locks with the shared-bike app to ensure proper functionality.
o v: Perform performance stress tests on the system to verify handling of transactions and concurrent users.
o w: Conduct User Acceptance Testing (UAT) with the sponsor and end-user representatives.
o x: Install the website on the government's web server for operation.
o y: Create technical training materials for staff.
o z: Train staff in operating and maintaining the system.
2.2 Gantt Chart
The Gantt Chart below visualizes the project schedule, illustrating task durations and dependencies to ensure a clear understanding of the project timeline.
Note: The start date is set as 01-01-2024. The milestones are set to the dates provided by the sponsor:
• Prototype Delivery Milestone (m1): Prototype must be delivered within two months (by 01-03-2024).
• Intermediate Modules Milestone (m2): Intermediate modules must be delivered within five months (by 01-06-2024).
• Project Completion Milestone (m3): Project must be fully completed within eight months (by 01-09-2024).
Task Dependencies and Durations
The table below outlines each task's duration and dependencies:
Activity ID Activity Name Duration (Days) Predecessors
a Background study on e-payment implementation 18 -
b Requirements Analysis 20 a
c Technical Feasibility Study 22 b
d System Design 25 b
e Module Design 15 d
f Interface Design 25 d
g Database Design 15 f
h UI Design 15 d
i Security Design 20 d
j Integration Testing 12 f, g
k System Testing 12 j
l Coding Core Modules 30 k
m Coding Module E 20 e
n Coding Module F 20 f
o Develop UI 12 h
p Database Implementation 25 i, g
q Security Implementation 30 i
r Testing Module N 25 n
s Testing Module S 25 n
t Final Integration 20 l, m, p, q, r, s
u Deployment Preparation 5 t, o
v System Deployment 5 u
w User Training 5 v
x Project Handover 12 w
y Post-Deployment Support 20 x
z Project Closure 19 y
3 Project Schedule Management
In this chapter, we present the project schedule management plan, including the Network Diagram in Precedence Diagramming Method (PDM) format, and conduct a Critical Path Analysis (CPA).
3.1 Network Diagram in PDM
The following network diagram represents the project's activities using the Precedence Diagramming Method (PDM). Each node corresponds to a task identified by its activity ID.
Legend:
• Nodes represent tasks labeled from a to z.
• Arrows indicate task dependencies.
3.2 Critical Path Analysis
Critical Path Analysis (CPA) identifies the sequence of tasks that determines the minimum project duration. Tasks on the critical path have zero slack.
3.2.1 Forward Pass (Calculating Early Start and Early Finish)
Task Duration (Days) Predecessors Early Start (ES) Early Finish (EF)
a 18 - 0 18
b 20 a 18 38
c 22 b 38 60
d 25 b 38 63
e 15 d 63 78
f 25 d 63 88
g 15 f 88 103
h 15 d 63 78
i 20 d 63 83
j 12 f, g 103 115
k 12 j 115 127
l 30 k 127 157
m 20 e 78 98
n 20 f 88 108
o 12 h 78 90
p 25 i, g 103 128
q 30 i 83 113
r 25 n 108 133
s 25 n 108 133
t 20 l, m, p, q, r, s 157 177
u 5 t, o 177 182
v 5 u 182 187
w 5 v 187 192
x 12 w 192 204
y 20 x 204 224
z 19 y 223 243
3.2.2 Backward Pass (Calculating Late Start and Late Finish)
Assuming the project's finish time is 244 days.
Here's the completed backward pass table:
Task Duration (Days) Successors Late Finish (LF) Late Start (LS) Slack (LS - ES)
z 19 - 243 223 0
y 20 z 224 204 0
x 12 y 204 192 0
w 5 x 192 187 0
v 5 w 187 182 0
u 5 v 182 177 0
t 20 u 177 157 0
l 30 t 157 127 0
k 12 l 127 115 0
j 12 k, p 115 103 0
g 15 j, p 103 88 0
p 25 t 152 127 24
q 30 t 152 122 39
m 20 t 157 132 54
e 15 m 132 117 54
d 25 e, f, h, i 63 38 0
f 25 g, j, n 88 63 0
r 25 t 152 127 19
s 25 t 152 127 19
n 20 r, s 127 107 39
i 20 p, q 122 102 42
o 12 u 177 165 87
h 15 o 165 150 87
b 20 d, c 38 18 0
a 18 b 18 0 0
c 22 - 60 38 0
3.2.3 Identifying the Critical Path
Tasks with zero slack form the critical path. The critical path for this project is:
• a - b - d - f - g - j - k - l - t - u - v - w - x - y - z
Project Duration: 8 months, 243 days (Including holidays)
4 Project Budget Management
In this chapter, we detail the Project Cost Management plan, including resource allocation, cost baseline, and Earned Value Management (EVM) analysis. We also present the performance measurements, variance analysis, and forecasting based on the project’s progress at the end of the fourth month.
4.1 Resource Sheet
Below is the Resource Sheet summarizing all the resources involved in the project, their hourly rates, total hours worked, and total costs.
Table 4.1: Resource Sheet
Resource Rate (/hr)orUnitCost() Total Units or Hours Total Cost ()HumanResourcesProjectManager(PM)500/hr 984 hours 492,000Bill(SeniorDeveloper)300/hr 1,776 hours 532,800Lisa(Developer)200/hr 1,336 hours 267,200Andy(Developer)200/hr 1,552 hours 310,400Kent(Developer)200/hr 1,288 hours 257,600SubtotalHumanResources6,936hours1,860,000
Equipment Purchases
Mobile Phones 800/unit5units4,000
Bike Locks with Connectivity 1,000/unit10units10,000
Total Equipment Purchases 14,000OtherCostsComputingFacilitiesRental29,000/month 8 months 232,000SubtotalOtherCosts246,000
Total (Before Contingency) 2,120,000ContingencyReserve(20424,000
Total Project Cost $2,544,000
Notes:
Based on the project schedule and team capabilities, tasks have been assigned to team members to ensure efficient utilization of skills and fair distribution of workload among team members, excluding the Project Manager (PM). The PM oversees the entire development process and participates in key tasks.
Table 4.1.1: Work Breakdown Structure (WBS) with Resource Assignments
WBS ID Task Name Duration (Days) Assigned To
1 Analysis Phase
1.1 Background study on e-payment implementation 18 Bill
1.2 Requirements Analysis 20 Bill, PM
1.3 Technical Feasibility Study 22 Bill, PM
2 Design Phase
2.1 System Design 25 Bill, PM
2.2 Module Design 15 Bill, Lisa
2.3 Interface Design 25 Lisa, Kent
2.4 Database Design 15 Bill, Andy
2.5 UI Design 15 Lisa, Kent
2.6 Security Design 20 Bill, Andy
2.7 Integration Testing 12 Andy, Kent
2.8 System Testing 12 Andy, Kent
3 Implementation Phase
3.1 Coding Core Modules 30 Lisa, Andy
3.2 Coding Module E 20 Lisa
3.3 Coding Module F 20 Kent
3.4 Develop UI 12 Lisa, Kent
3.5 Database Implementation 25 Bill, Andy
3.6 Security Implementation 30 Bill, Andy
3.7 Testing Module N 25 Kent
3.8 Testing Module S 25 Lisa
3.9 Final Integration 20 All Team Members
4 Deployment Phase
4.1 Deployment Preparation 5 PM, Andy
4.2 System Deployment 5 Andy
4.3 User Training 5 Lisa
4.4 Project Handover 12 PM, Bill
4.5 Post-Deployment Support 20 Andy, Kent
4.6 Project Closure 19 PM
Resource Assignments Summary
o Project Manager (PM): Participates in tasks 1.2, 1.3, 2.1, 3.9, 4.1, 4.4, and 4.6.
o Bill (Senior Developer): Leads analysis and design tasks; involved in tasks 1.1 to 2.6, 3.5, 3.6, 3.9, and 4.4.
o Lisa (Developer): Focuses on UI/UX design and client-side coding; involved in tasks 2.2, 2.3, 2.5, 3.1 to 3.4, 3.8, 3.9, and 4.3.
o Andy (Developer): Handles server-side coding and integration; involved in tasks 2.4, 2.6, 2.7, 2.8, 3.1, 3.5, 3.6, 3.9, 4.1, 4.2, and 4.5.
o Kent (Developer): Works on client-side coding and testing; involved in tasks 2.3, 2.5, 2.7, 2.8, 3.3, 3.4, 3.7, 3.9, and 4.5.
Market Study on Needed Equipment
As part of the project's hardware requirements, the following equipment is needed for development and testing purposes:
Mobile Phones (5 units):
o Purpose: To test the mobile application on various devices.
o Estimated Market Price per Unit: 800oTotalCost:5units∗800/unit = $4,000
Bike Locks with Connectivity (10 units):
o Purpose: To develop and test signal connection mechanisms with bike locks.
o Estimated Market Price per Unit: 1,000oTotalCost:10units∗1,000/unit = $10,000
Computers and Peripherals:
o Note: The computing facilities are rented monthly and covered separately under computing facilities rental costs.
Total Equipment Purchases: 4,000(MobilePhones)+10,000 (Bike Locks) = $14,000
4.2 Cost Baseline (Budget Schedule)
The Cost Baseline outlines the planned expenditures over the project’s duration, including the Contingency Reserve to account for potential risks.
Table 4.2: Cost Baseline
Month PM ()Bill() Lisa ()Andy() Kent ()ComputingFacilities() Equipment Purchases ()PlannedCost() Contingency Reserve (20%) Cumulative Planned Cost (14,000 for mobile phones and bike locks.
o Computing Facilities Rental: $29,000 per month for 8 months.
o Contingency Reserve: Calculated as 20% of the monthly Planned Cost.
4.3 Planned Values (PVs) for the 8 Months
Table 4.3: Cumulative Planned Values
Month Cumulative Planned Value (PV) ()1330,6002644,4003958,20041,272,00051,585,80061,899,60072,213,40082,527,2004.4EarnedValueManagement(E1,272,000 (from the Cost Baseline)
• Actual Cost (AC): 1,320,000(actualexpenditureincurred 1,200,000 (value of work actually completed)
4.4.1 EVM Calculations
• Cost Variance (CV):
CV = EV - AC
CV = 1,200,000−1,320,000
CV = -120,000•NegativeCVindi1,200,000 - 1,272,000SV=−72,000
• Negative SV indicates the project is behind schedule.
• Cost Performance Index (CPI):
CPI = EV / AC
CPI = 1,200,000/1,320,000
CPI ≈ 0.9091
• CPI less than 1 indicates poor cost efficiency.
• Schedule Performance Index (SPI):
SPI = EV / PV
SPI = 1,200,000/1,272,000
SPI ≈ 0.9434
• SPI less than 1 indicates the project is progressing slower than planned.
• Estimate at Completion (EAC):
EAC = BAC / CPI
EAC = 2,527,200/0.9091EAC≈2,780,000
• EAC projects the total cost at completion based on current performance.
• Estimated Time to Complete (ETC):
ETC = Original Duration / SPI
ETC = 8 months / 0.9434
ETC ≈ 8.48 months
• ETC estimates the total project duration based on current schedule performance.
• Variance Analysis
• Cost Variance (CV): The project is over budget by 72,000 worth of work, meaning less work has been completed than planned up to this point.
• Cost Performance Index (CPI): At 0.9091, the project is not utilizing its budget efficiently.
• Schedule Performance Index (SPI): At 0.9434, the project is progressing slower than planned.
4.5 EVM Graph
Figure 4.5: EVM Graph at End of Month 4
Note: The EVM graph plots the cumulative values of PV, EV, and AC over the project duration.
4.6 Project Performance and Forecasting Description
At the end of the fourth month, the project is experiencing both schedule delays and cost overruns. The Schedule Variance (SV) of -72,000andSchedulePerformanceIndex(SPI)of0.9434indicatethattheprojectisbehin120,000 and Cost Performance Index (CPI) of 0.9091 reveal that the project is over budget, spending more than the value of the work completed. Possible reasons include:
o Extended Work Hours: Team members may have worked overtime to address challenges, increasing labor costs.
o Unexpected Expenses: Additional costs, such as higher equipment prices or extra resources, may not have been anticipated.
The Estimate at Completion (EAC) projects the total project cost to be approximately 2,780,000,exceedingtheoriginalbudget252,800. The project is also projected to extend to approximately 8.5 months, nearly half a month beyond the planned duration.
To address these issues, we need to:
• Analyze the Causes: Investigate the reasons for schedule delays and cost overruns, such as scope changes, resource inefficiencies, or technical challenges.
• Implement Corrective Actions: Reallocate resources, optimize processes, and implement cost-saving measures to improve CPI and SPI.
• Update the Schedule and Budget: Adjust the project plan to reflect realistic timelines and costs, ensuring that stakeholders are informed of any changes.
By taking proactive steps, we aim to bring the project back on track, minimize the cost overrun, and meet the project’s objectives within the adjusted budget and schedule.
Help me to finish ch5
5 Project Resource Management
This chapter should include the following items:
(a) Develop a Team Charter
(b) Develop a RACI chart that outlines the responsibilities of the team for the project’s tasks
(a, b, c, ... z), taking into account the skill sets and knowledge of each team member.
(c) Develop a Resource Histogram to illustrate the distribution of work among team members for each two-week period (to show number of hours performed by individual members along the 8 months).
5 Project Resource Management
In this chapter, we outline the resource management plan for the shared bike software system project. Effective resource management ensures that the right resources are allocated to the right tasks at the right time. We will develop a Team Charter to establish clear expectations among team members, a RACI chart to clarify responsibilities, and a Resource Histogram to visualize the distribution of work.
5.1 Develop a Team Charter
A Team Charter is a document that defines the team's purpose, roles and responsibilities, ground rules, communication protocols, decision-making processes, and conflict resolution mechanisms. It serves as a roadmap for how the team will work together to achieve the project objectives.
Team Purpose and Goals
Purpose: To develop and deploy a robust, user-friendly, and secure shared bike software system that meets all the requirements specified by the local government, contributing to the success of the shared bike program.
Goals:
Deliver a prototype within two months.
Complete intermediate modules within five months.
Fully complete the project within eight months.
Ensure the software system meets quality standards and satisfies all functional and non-functional requirements.
Responsibilities: Designing user interfaces, client-side coding, user experience optimization.
Andy (Developer)
Role: Server-side development and integration.
Responsibilities: Server-side coding, integration of modules, backend development.
Kent (Developer)
Role: Client-side coding and testing.
Responsibilities: Client-side development, testing of modules, ensuring software reliability.
Team Values and Norms
Collaboration: Team members will work together cooperatively, sharing knowledge and supporting each other.
Communication: Open and honest communication is encouraged. Team members will keep each other informed of progress and issues.
Quality: Commitment to delivering high-quality work that meets or exceeds expectations.
Respect: Team members will treat each other with respect, valuing diverse perspectives.
Ground Rules
Meetings: Regular team meetings will be held twice weekly (Monday and Thursday) to discuss progress, challenges, and upcoming tasks.
Communication Channels: Primary communication will be through email and a team messaging platform (e.g., Slack). Critical issues should be raised immediately via phone or direct messaging.
Attendance and Punctuality: Team members are expected to attend scheduled meetings on time. If unable to attend, they should notify the PM in advance.
Task Updates: Team members will update the project management tool (e.g., Jira) with the status of their tasks daily.
Decision-Making Process
Consensus: Decisions will be made by consensus whenever possible.
Voting: If consensus cannot be reached, decisions will be made by majority vote among team members.
Escalation: For critical decisions or conflicts that cannot be resolved within the team, the PM will make the final decision, potentially involving stakeholders as needed.
Conflict Resolution
Direct Communication: Team members should address conflicts directly and constructively with the involved parties.
Mediation: If conflicts persist, the PM will mediate to facilitate a resolution.
Documentation: Significant conflicts and their resolutions will be documented to prevent recurrence.
Performance Expectations
Quality of Work: Deliverables should meet the defined quality standards and be completed on time.
Accountability: Team members are accountable for their assigned tasks and responsibilities.
Continuous Improvement: Team members are encouraged to seek feedback and opportunities for skill development.
Communication Plan
Status Reports: Weekly status reports will be prepared by each team member, summarizing accomplishments, upcoming tasks, and any issues.
Stakeholder Updates: The PM will provide bi-weekly updates to stakeholders, including progress towards milestones.
5.2 Develop a RACI Chart
The RACI chart outlines the participation by various roles in completing tasks or deliverables for a project. RACI stands for Responsible (R), Accountable (A), Consulted (C), and Informed (I). This chart clarifies roles and responsibilities, ensuring that tasks are assigned appropriately and that team members understand their roles.
RACI Chart for Project Tasks (a - z)
Key Definitions:
Responsible (R): The person(s) who do the work to complete the task.
Accountable (A): The person who is ultimately answerable for the correct completion of the task and delegates the work; there must be only one A per task.
Consulted (C): The person(s) who need to be consulted prior to a decision or action.
Informed (I): The person(s) who need to be informed after a decision or action is taken.
Table 5.2: RACI Chart
Task
PM
Bill
Lisa
Andy
Kent
a - Conduct background study on e-payment implementations
C, I
R, A
I
I
I
b - Collect detailed requirements from government departments
R, A
R
I
I
I
c - Develop a prototype to demonstrate payment procedure
C
R, A
R
I
I
d - Design the overall software architecture
C
R, A
C
C
I
e - Design the database schema
C, I
R, A
I
R
I
f - Design end-user interfaces for mobile applications
C
I
R, A
I
R
g - Design interfaces for administrative functions
I
C
R, A
I
R
h - Design signal connection mechanisms with bike locks
I
C
I
R, A
I
i - Design the security scheme
C
R, A
I
R
I
j - Develop interface templates for review
I
I
R, A
I
C
k - Create site map or hierarchy chart
C
I
R, A
I
I
l - Create individual web pages
I
I
R, A
I
C
m - Create the database
I
C
I
R, A
I
n - Source necessary library modules for client-side coding
Notes:
Each task has one person accountable (A) for its completion.
Responsibilities are assigned based on team members' roles and expertise.
Consulted (C) individuals provide input and feedback on tasks.
Informed (I) individuals are kept up to date on task progress and outcomes.
5.3 Develop a Resource Histogram
A Resource Histogram is a graphical representation depicting the number of hours each team member is scheduled to work over specific time periods. This visualization helps in understanding the distribution of work, identifying periods of over-allocation or underutilization, and facilitating resource leveling.
Methodology for Developing the Resource Histogram
To create the Resource Histogram for our project:
Define Time Periods: The project spans eight months, equivalent to 32 weeks. We divide this into 16 two-week periods.
Map Tasks to Time Periods: Using the project schedule (Gantt Chart and Network Diagram), we map each task to its corresponding time periods based on the start and end dates.
Allocate Hours per Task: For each task, we calculate the total work hours by multiplying the duration in days by the standard work hours per day (assumed to be 8 hours).
Assign Hours to Team Members: Based on the resource assignments, we distribute the task hours among the assigned team members.
Sum Hours per Time Period: We aggregate the hours each team member is scheduled to work in each two-week period.
Assumptions
Standard Workday: 8 hours per day.
Working Days per Two-Week Period: Approximately 10 working days.
Team Members' Availability: Team members are available full-time unless otherwise specified.
Sample Resource Histogram Data (First Four Periods)
Table 5.3: Resource Allocation Over First Four Periods
Period
Dates
PM (Hours)
Bill (Hours)
Lisa (Hours)
Andy (Hours)
Kent (Hours)
1
Jan 1 - Jan 14
20
112
0
0
0
2
Jan 15 - Jan 28
40
128
16
0
0
3
Jan 29 - Feb 11
40
96
48
16
0
4
Feb 12 - Feb 25
20
88
64
64
32
Explanation:
Period 1:
PM: Participates in initial planning (20 hours).
Bill: Works full-time on Task a (112 hours).
Others: Not yet engaged in tasks.
Period 2:
PM: Engaged in requirements analysis (40 hours).
Bill: Continues requirements analysis and begins design (128 hours).
Lisa: Starts involvement in prototype development (16 hours).
Period 3:
PM: Continues oversight and planning (40 hours).
Bill: Focuses on design tasks (96 hours).
Lisa: Increases involvement in design tasks (48 hours).
Andy: Begins involvement in database and security design (16 hours).
Period 4:
PM: Less intensive involvement (20 hours).
Bill: Continues design tasks (88 hours).
Lisa: Heavily involved in interface and UI design (64 hours).
Andy: Increased involvement in backend design (64 hours).
Kent: Begins participation in UI design (32 hours).
Visualization
Due to the text-based format, we cannot present the graphical histogram here. However, the Resource Histogram would be a bar chart for each team member, with the x-axis representing the 16 two-week periods and the y-axis representing the number of work hours. Each team member's workload would be depicted with bars showing hours scheduled per period, allowing us to visualize peaks and troughs in resource utilization.
Observations and Adjustments
Resource Leveling: If any team member is over-allocated (e.g., assigned more than 80 hours in a two-week period), we may need to redistribute tasks or adjust schedules.
Underutilization: Periods where team members have significantly fewer hours may indicate underutilization, prompting a review of task assignments.
Project Phases: Workload distributions reflect project phases, with analysis and design heavily involving Bill and the PM, and implementation increasing workloads for developers.
Conclusion
The Resource Histogram helps ensure that team members are effectively utilized throughout the project, preventing burnout and ensuring timely completion of tasks.