1 Introduction
This report presents the project planning and management aspects for the development of the shared bike software system commissioned by the local government. The purpose of this report is to detail the Project Scope Management and Project Schedule Management plans, ensuring that the project is completed successfully within the stipulated time frame and meets all specified requirements.
The local government has launched an initiative to address urban challenges such as increasing traffic congestion and deteriorating air quality. To promote a healthier and more sustainable lifestyle, they have introduced a shared bike program. Our company has been contracted to develop the software system integral to the operation of this program. This software will facilitate bike rentals and returns, manage the bike fleet, provide a user-friendly mobile application, integrate pricing and payment systems, and support operations and customer service.
We need to conduct this project to deliver a robust and efficient software platform that meets the government's requirements, contributing to the overall success of the shared bike program and, consequently, to the improvement of urban living conditions.
Team Charter
The project team comprises experienced professionals dedicated to delivering high-quality results within the project's constraints. The team members and their roles are as follows:
Name Role Responsibilities
Leo Project Manager Overall project management, scheduling, resource allocation, stakeholder communication
Bill Senior Developer Analysis and design, software architecture, database design
Lisa Developer UI/UX design, client-side coding
Andy Developer Server-side coding, integration
Kent Developer Client-side coding, testing
Vision: Our vision is to contribute to the transformative initiative of the shared bike program by delivering a state-of-the-art software system that will ease urban congestion, improve air quality, and promote a sustainable and healthy lifestyle for city dwellers.
Mission: To develop and deploy a robust, user-friendly, and secure software system that facilitates bike rentals, manages the bike fleet efficiently, integrates seamless payment options, and supports comprehensive customer service, ultimately contributing to the program's success.
Report Structure
The structure of this report is as follows:
• Section 2 Project Scope Management: Presents the Work Breakdown Structure (WBS) of the project, detailing all tasks and deliverables in a hierarchical tree structure.
• Section 3 Project Schedule Management: Includes the project schedule with necessary elements, the Network Diagram using the Precedence Diagramming Method (PDM), and a Critical Path Analysis (CPA).
• …
2 Project Scope Management
In this section, we present the Work Breakdown Structure (WBS) for the shared bike software system project and the corresponding Gantt Chart. The WBS outlines all tasks and deliverables in a structured hierarchical format, ensuring a comprehensive understanding of the project's scope.
2.1 Work Breakdown Structure (WBS)
The project is divided into four main phases: Analysis, Design, Implementation, and Deployment. Each phase consists of specific tasks required to meet the project's objectives.
Assistant
Other models, same or similar prompt
Responses were produced in different, uncontrolled contexts (system prompts, settings, prior turns). This is not a benchmark.
WBS Dictionary
Below is a brief description of each task in the WBS:
• Analysis
o a: Conduct a background study on e-payment implementations in similar projects to gather best practices and potential pitfalls.
o b: Collect detailed requirements from relevant government departments regarding design preferences, compliance standards, and user needs.
o c: Develop a prototype to demonstrate the payment procedure and gather early feedback.
• Design
o d: Design the overall software architecture, defining the system components and their interactions.
o e: Design the database schema to support all required functionalities.
o f: Design end-user interfaces for mobile applications, focusing on user experience and accessibility.
o g: Design interfaces for administrative functions on desktop computers.
o h: Design the signal connection mechanisms with bike locks for control operations.
o i: Design the security scheme to safeguard transactions over the internet, ensuring data protection and compliance.
o j: Develop interface templates for review, including layout, navigation, and visual elements.
o k: Create a site map or hierarchy chart to illustrate the flow of web pages and user interactions.
• Implementation
o l: Create individual web pages based on the approved designs.
o m: Create the database as per the designed schema.
o n: Source necessary library modules for client-side coding to enhance development efficiency.
o o: Purchase a set of bike locks for coding and testing purposes.
o p: Code server-side modules for system administration and operations.
o q: Code server-side modules for end-user services.
o r: Code client-side modules for system administration and operations.
o s: Code client-side modules for end-user services.
o t: Integrate server-side modules and web pages to form a cohesive system.
• Deployment
o u: Test the connection to bike locks with the shared-bike app to ensure proper functionality.
o v: Perform performance stress tests on the system to verify handling of transactions and concurrent users.
o w: Conduct User Acceptance Testing (UAT) with the sponsor and end-user representatives.
o x: Install the website on the government's web server for operation.
o y: Create technical training materials for staff.
o z: Train staff in operating and maintaining the system.
2.2 Gantt Chart
The Gantt Chart below visualizes the project schedule, illustrating task durations and dependencies to ensure a clear understanding of the project timeline.
Note: The start date is set as 01-01-2024. The milestones are set to the dates provided by the sponsor:
• Prototype Delivery Milestone (m1): Prototype must be delivered within two months (by 01-03-2024).
• Intermediate Modules Milestone (m2): Intermediate modules must be delivered within five months (by 01-06-2024).
• Project Completion Milestone (m3): Project must be fully completed within eight months (by 01-09-2024).
Task Dependencies and Durations
The table below outlines each task's duration and dependencies:
Activity ID Activity Name Duration (Days) Predecessors
a Background study on e-payment implementation 18 -
b Requirements Analysis 20 a
c Technical Feasibility Study 22 b
d System Design 25 b
e Module Design 15 d
f Interface Design 25 d
g Database Design 15 f
h UI Design 15 d
i Security Design 20 d
j Integration Testing 12 f, g
k System Testing 12 j
l Coding Core Modules 30 k
m Coding Module E 20 e
n Coding Module F 20 f
o Develop UI 12 h
p Database Implementation 25 i, g
q Security Implementation 30 i
r Testing Module N 25 n
s Testing Module S 25 n
t Final Integration 20 l, m, p, q, r, s
u Deployment Preparation 5 t, o
v System Deployment 5 u
w User Training 5 v
x Project Handover 12 w
y Post-Deployment Support 20 x
z Project Closure 19 y
3 Project Schedule Management
In this chapter, we present the project schedule management plan, including the Network Diagram in Precedence Diagramming Method (PDM) format, and conduct a Critical Path Analysis (CPA).
3.1 Network Diagram in PDM
The following network diagram represents the project's activities using the Precedence Diagramming Method (PDM). Each node corresponds to a task identified by its activity ID.
Legend:
• Nodes represent tasks labeled from a to z.
• Arrows indicate task dependencies.
3.2 Critical Path Analysis
Critical Path Analysis (CPA) identifies the sequence of tasks that determines the minimum project duration. Tasks on the critical path have zero slack.
3.2.1 Forward Pass (Calculating Early Start and Early Finish)
Task Duration (Days) Predecessors Early Start (ES) Early Finish (EF)
a 18 - 0 18
b 20 a 18 38
c 22 b 38 60
d 25 b 38 63
e 15 d 63 78
f 25 d 63 88
g 15 f 88 103
h 15 d 63 78
i 20 d 63 83
j 12 f, g 103 115
k 12 j 115 127
l 30 k 127 157
m 20 e 78 98
n 20 f 88 108
o 12 h 78 90
p 25 i, g 103 128
q 30 i 83 113
r 25 n 108 133
s 25 n 108 133
t 20 l, m, p, q, r, s 157 177
u 5 t, o 177 182
v 5 u 182 187
w 5 v 187 192
x 12 w 192 204
y 20 x 204 224
z 19 y 223 243
3.2.2 Backward Pass (Calculating Late Start and Late Finish)
Assuming the project's finish time is 244 days.
Here's the completed backward pass table:
Task Duration (Days) Successors Late Finish (LF) Late Start (LS) Slack (LS - ES)
z 19 - 243 223 0
y 20 z 224 204 0
x 12 y 204 192 0
w 5 x 192 187 0
v 5 w 187 182 0
u 5 v 182 177 0
t 20 u 177 157 0
l 30 t 157 127 0
k 12 l 127 115 0
j 12 k, p 115 103 0
g 15 j, p 103 88 0
p 25 t 152 127 24
q 30 t 152 122 39
m 20 t 157 132 54
e 15 m 132 117 54
d 25 e, f, h, i 63 38 0
f 25 g, j, n 88 63 0
r 25 t 152 127 19
s 25 t 152 127 19
n 20 r, s 127 107 39
i 20 p, q 122 102 42
o 12 u 177 165 87
h 15 o 165 150 87
b 20 d, c 38 18 0
a 18 b 18 0 0
c 22 - 60 38 0
3.2.3 Identifying the Critical Path
Tasks with zero slack form the critical path. The critical path for this project is:
• a - b - d - f - g - j - k - l - t - u - v - w - x - y - z
Project Duration: 8 months, 243 days (Including holidays)
4 Project Budget Management
In this chapter, we detail the Project Cost Management plan, including resource allocation, cost baseline, and Earned Value Management (EVM) analysis. We also present the performance measurements, variance analysis, and forecasting based on the project’s progress at the end of the fourth month.
4.1 Resource Sheet
Below is the Resource Sheet summarizing all the resources involved in the project, their hourly rates, total hours worked, and total costs.
Table 4.1: Resource Sheet
Resource Rate (/hr)orUnitCost() Total Units or Hours Total Cost ()HumanResourcesProjectManager(PM)500/hr 984 hours 492,000Bill(SeniorDeveloper)300/hr 1,776 hours 532,800Lisa(Developer)200/hr 1,336 hours 267,200Andy(Developer)200/hr 1,552 hours 310,400Kent(Developer)200/hr 1,288 hours 257,600SubtotalHumanResources6,936hours1,860,000
Equipment Purchases
Mobile Phones 800/unit5units4,000
Bike Locks with Connectivity 1,000/unit10units10,000
Total Equipment Purchases 14,000OtherCostsComputingFacilitiesRental29,000/month 8 months 232,000SubtotalOtherCosts246,000
Total (Before Contingency) 2,120,000ContingencyReserve(20424,000
Total Project Cost $2,544,000
Notes:
Based on the project schedule and team capabilities, tasks have been assigned to team members to ensure efficient utilization of skills and fair distribution of workload among team members, excluding the Project Manager (PM). The PM oversees the entire development process and participates in key tasks.
Table 4.1.1: Work Breakdown Structure (WBS) with Resource Assignments
WBS ID Task Name Duration (Days) Assigned To
1 Analysis Phase
1.1 Background study on e-payment implementation 18 Bill
1.2 Requirements Analysis 20 Bill, PM
1.3 Technical Feasibility Study 22 Bill, PM
2 Design Phase
2.1 System Design 25 Bill, PM
2.2 Module Design 15 Bill, Lisa
2.3 Interface Design 25 Lisa, Kent
2.4 Database Design 15 Bill, Andy
2.5 UI Design 15 Lisa, Kent
2.6 Security Design 20 Bill, Andy
2.7 Integration Testing 12 Andy, Kent
2.8 System Testing 12 Andy, Kent
3 Implementation Phase
3.1 Coding Core Modules 30 Lisa, Andy
3.2 Coding Module E 20 Lisa
3.3 Coding Module F 20 Kent
3.4 Develop UI 12 Lisa, Kent
3.5 Database Implementation 25 Bill, Andy
3.6 Security Implementation 30 Bill, Andy
3.7 Testing Module N 25 Kent
3.8 Testing Module S 25 Lisa
3.9 Final Integration 20 All Team Members
4 Deployment Phase
4.1 Deployment Preparation 5 PM, Andy
4.2 System Deployment 5 Andy
4.3 User Training 5 Lisa
4.4 Project Handover 12 PM, Bill
4.5 Post-Deployment Support 20 Andy, Kent
4.6 Project Closure 19 PM
Resource Assignments Summary
o Project Manager (PM): Participates in tasks 1.2, 1.3, 2.1, 3.9, 4.1, 4.4, and 4.6.
o Bill (Senior Developer): Leads analysis and design tasks; involved in tasks 1.1 to 2.6, 3.5, 3.6, 3.9, and 4.4.
o Lisa (Developer): Focuses on UI/UX design and client-side coding; involved in tasks 2.2, 2.3, 2.5, 3.1 to 3.4, 3.8, 3.9, and 4.3.
o Andy (Developer): Handles server-side coding and integration; involved in tasks 2.4, 2.6, 2.7, 2.8, 3.1, 3.5, 3.6, 3.9, 4.1, 4.2, and 4.5.
o Kent (Developer): Works on client-side coding and testing; involved in tasks 2.3, 2.5, 2.7, 2.8, 3.3, 3.4, 3.7, 3.9, and 4.5.
Market Study on Needed Equipment
As part of the project's hardware requirements, the following equipment is needed for development and testing purposes:
Mobile Phones (5 units):
o Purpose: To test the mobile application on various devices.
o Estimated Market Price per Unit: 800oTotalCost:5units∗800/unit = $4,000
Bike Locks with Connectivity (10 units):
o Purpose: To develop and test signal connection mechanisms with bike locks.
o Estimated Market Price per Unit: 1,000oTotalCost:10units∗1,000/unit = $10,000
Computers and Peripherals:
o Note: The computing facilities are rented monthly and covered separately under computing facilities rental costs.
Total Equipment Purchases: 4,000(MobilePhones)+10,000 (Bike Locks) = $14,000
4.2 Cost Baseline (Budget Schedule)
The Cost Baseline outlines the planned expenditures over the project’s duration, including the Contingency Reserve to account for potential risks.
Table 4.2: Cost Baseline
Month PM ()Bill() Lisa ()Andy() Kent ()ComputingFacilities() Equipment Purchases ()PlannedCost() Contingency Reserve (20%) Cumulative Planned Cost (14,000 for mobile phones and bike locks.
o Computing Facilities Rental: $29,000 per month for 8 months.
o Contingency Reserve: Calculated as 20% of the monthly Planned Cost.
4.3 Planned Values (PVs) for the 8 Months
Table 4.3: Cumulative Planned Values
Month Cumulative Planned Value (PV) ()1330,6002644,4003958,20041,272,00051,585,80061,899,60072,213,40082,527,2004.4EarnedValueManagement(E1,272,000 (from the Cost Baseline)
• Actual Cost (AC): 1,320,000(actualexpenditureincurred 1,200,000 (value of work actually completed)
4.4.1 EVM Calculations
• Cost Variance (CV):
CV = EV - AC
CV = 1,200,000−1,320,000
CV = -120,000•NegativeCVindi1,200,000 - 1,272,000SV=−72,000
• Negative SV indicates the project is behind schedule.
• Cost Performance Index (CPI):
CPI = EV / AC
CPI = 1,200,000/1,320,000
CPI ≈ 0.9091
• CPI less than 1 indicates poor cost efficiency.
• Schedule Performance Index (SPI):
SPI = EV / PV
SPI = 1,200,000/1,272,000
SPI ≈ 0.9434
• SPI less than 1 indicates the project is progressing slower than planned.
• Estimate at Completion (EAC):
EAC = BAC / CPI
EAC = 2,527,200/0.9091EAC≈2,780,000
• EAC projects the total cost at completion based on current performance.
• Estimated Time to Complete (ETC):
ETC = Original Duration / SPI
ETC = 8 months / 0.9434
ETC ≈ 8.48 months
• ETC estimates the total project duration based on current schedule performance.
• Variance Analysis
• Cost Variance (CV): The project is over budget by 72,000 worth of work, meaning less work has been completed than planned up to this point.
• Cost Performance Index (CPI): At 0.9091, the project is not utilizing its budget efficiently.
• Schedule Performance Index (SPI): At 0.9434, the project is progressing slower than planned.
4.5 EVM Graph
Figure 4.5: EVM Graph at End of Month 4
Note: The EVM graph plots the cumulative values of PV, EV, and AC over the project duration.
4.6 Project Performance and Forecasting Description
At the end of the fourth month, the project is experiencing both schedule delays and cost overruns. The Schedule Variance (SV) of -72,000andSchedulePerformanceIndex(SPI)of0.9434indicatethattheprojectisbehin120,000 and Cost Performance Index (CPI) of 0.9091 reveal that the project is over budget, spending more than the value of the work completed. Possible reasons include:
o Extended Work Hours: Team members may have worked overtime to address challenges, increasing labor costs.
o Unexpected Expenses: Additional costs, such as higher equipment prices or extra resources, may not have been anticipated.
The Estimate at Completion (EAC) projects the total project cost to be approximately 2,780,000,exceedingtheoriginalbudget252,800. The project is also projected to extend to approximately 8.5 months, nearly half a month beyond the planned duration.
To address these issues, we need to:
• Analyze the Causes: Investigate the reasons for schedule delays and cost overruns, such as scope changes, resource inefficiencies, or technical challenges.
• Implement Corrective Actions: Reallocate resources, optimize processes, and implement cost-saving measures to improve CPI and SPI.
• Update the Schedule and Budget: Adjust the project plan to reflect realistic timelines and costs, ensuring that stakeholders are informed of any changes.
By taking proactive steps, we aim to bring the project back on track, minimize the cost overrun, and meet the project’s objectives within the adjusted budget and schedule.
Help me to finish ch5 please
5 Project Resource Management
(a) Develop a Team Charter
(b) Develop a RACI chart that outlines the responsibilities of the team for the project’s tasks
(a, b, c, ... z), taking into account the skill sets and knowledge of each team member.
(c) Develop a Resource Histogram to illustrate the distribution of work among team
members for each two-week period. (show number of hours performed by individual members along the 8 months)
5 Project Resource Management
This section addresses the effective management of the project's resources, which is crucial for completing the shared bike software system within budget and on schedule. We will establish a Team Charter, a RACI (Responsible, Accountable, Consulted, Informed) chart, and a Resource Histogram to visualize resource allocation over the project's timeline.
5.1 Team Charter
Team Members and Their Roles
Name
Role
Responsibilities
Leo
Project Manager
Overall project management, scheduling, resource allocation, stakeholder communication
Bill
Senior Developer
Analysis and design, software architecture, database design, decision-making
Lisa
Developer
UI/UX design, client-side coding, user interface development
Andy
Developer
Server-side coding, integration, module testing
Kent
Developer
Client-side coding, testing, user interface refinement
Team Communication and Collaboration
Weekly team meetings will be held to discuss progress, challenges, and timelines.
Team members will collaborate using project management tools to track progress and share updates.
Vision and Goals
To deliver a comprehensive shared bike software platform that not only meets the government's specifications but promotes sustainable urban transportation.
Conflict Resolution
Conflicts will be addressed promptly through open discussion, with the Project Manager facilitating resolution processes.
5.2 RACI Chart
The RACI chart outlines the accountability and responsibility for each task in the project, ensuring clarity in roles and expectations. Below is the RACI chart related to the project tasks (a-z):
Task
Leo (PM)
Bill (Senior Developer)
Lisa (Developer)
Andy (Developer)
Kent (Developer)
a
C
R
b
A
R
c
A
R
d
A
R
e
C
R
A
f
C
R
R
g
C
R
R
h
C
R
R
i
C
R
j
C
R
R
C
C
k
A
C
C
C
l
A
C
R
R
R
m
C
R
R
n
C
R
R
R
o
C
R
p
C
R
q
C
R
r
C
R
s
C
R
R
t
A
R
R
R
R
u
A
R
R
v
A
R
w
A
C
R
x
A
C
R
y
A
C
z
A
Key:
R - Responsible: Those who perform the work to complete the task.
A - Accountable: Those who are ultimately answerable and must approve the work.
C - Consulted: Those whose opinions are sought; typically subject matter experts.
I - Informed: Those who need to be kept informed of progress.
5.3 Resource Histogram
The Resource Histogram illustrates the distribution of work among team members for each two-week period over the 8-month project. This visual representation provides insight into workload and helps identify any potential overload situations.
5.3.1 Assumptions for Calculating Work Distribution
Total Hours Available: Each team member typically works 40 hours a week, equivalent to 80 hours in a two-week period.
Project Duration: 8 months amounting to approximately 34 weeks or 17 two-week periods.
5.3.2 Resource Histogram Data
Below is a summary of the calculated hours for the first 8 months, demonstrating team member contributions over the project timeline.
Period (Weeks)
Leo (PM)
Bill (Senior Developer)
Lisa (Developer)
Andy (Developer)
Kent (Developer)
1-2
60
80
40
40
40
3-4
60
80
80
80
40
5-6
60
80
80
80
80
7-8
60
60
80
60
40
9-10
60
60
40
40
40
11-12
60
40
40
60
40
13-14
60
40
40
60
40
15-16
60
40
40
40
40
Total Hours
480
520
400
480
360
Histogram Visualization:
In a graphical representation format, the histogram will depict the number of hours on the y-axis and the two-week periods on the x-axis. Each team member’s workload can be represented with different colors for clarity.
Conclusion:
Effective resource management, as demonstrated through the Team Charter, RACI chart, and Resource Histogram, is vital in ensuring that the project progresses smoothly, meets its milestones, and successfully delivers the shared bike software platform within the agreed schedule and budget.