1 Introduction
This report presents the project planning and management aspects for the development of the shared bike software system commissioned by the local government. The purpose of this report is to detail the Project Scope Management and Project Schedule Management plans, ensuring that the project is completed successfully within the stipulated time frame and meets all specified requirements.
The local government has launched an initiative to address urban challenges such as increasing traffic congestion and deteriorating air quality. To promote a healthier and more sustainable lifestyle, they have introduced a shared bike program. Our company has been contracted to develop the software system integral to the operation of this program. This software will facilitate bike rentals and returns, manage the bike fleet, provide a user-friendly mobile application, integrate pricing and payment systems, and support operations and customer service.
We need to conduct this project to deliver a robust and efficient software platform that meets the government's requirements, contributing to the overall success of the shared bike program and, consequently, to the improvement of urban living conditions.
Team Charter
The project team comprises experienced professionals dedicated to delivering high-quality results within the project's constraints. The team members and their roles are as follows:
Name Role Responsibilities
Leo Project Manager Overall project management, scheduling, resource allocation, stakeholder communication
Bill Senior Developer Analysis and design, software architecture, database design
Lisa Developer UI/UX design, client-side coding
Andy Developer Server-side coding, integration
Kent Developer Client-side coding, testing
Vision: Our vision is to contribute to the transformative initiative of the shared bike program by delivering a state-of-the-art software system that will ease urban congestion, improve air quality, and promote a sustainable and healthy lifestyle for city dwellers.
Mission: To develop and deploy a robust, user-friendly, and secure software system that facilitates bike rentals, manages the bike fleet efficiently, integrates seamless payment options, and supports comprehensive customer service, ultimately contributing to the program's success.
Report Structure
The structure of this report is as follows:
• Section 2 Project Scope Management: Presents the Work Breakdown Structure (WBS) of the project, detailing all tasks and deliverables in a hierarchical tree structure.
• Section 3 Project Schedule Management: Includes the project schedule with necessary elements, the Network Diagram using the Precedence Diagramming Method (PDM), and a Critical Path Analysis (CPA).
• …
2 Project Scope Management
In this section, we present the Work Breakdown Structure (WBS) for the shared bike software system project and the corresponding Gantt Chart. The WBS outlines all tasks and deliverables in a structured hierarchical format, ensuring a comprehensive understanding of the project's scope.
2.1 Work Breakdown Structure (WBS)
The project is divided into four main phases: Analysis, Design, Implementation, and Deployment. Each phase consists of specific tasks required to meet the project's objectives.
Assistant
WBS Dictionary
Below is a brief description of each task in the WBS:
• Analysis
o a: Conduct a background study on e-payment implementations in similar projects to gather best practices and potential pitfalls.
o b: Collect detailed requirements from relevant government departments regarding design preferences, compliance standards, and user needs.
o c: Develop a prototype to demonstrate the payment procedure and gather early feedback.
• Design
o d: Design the overall software architecture, defining the system components and their interactions.
o e: Design the database schema to support all required functionalities.
o f: Design end-user interfaces for mobile applications, focusing on user experience and accessibility.
o g: Design interfaces for administrative functions on desktop computers.
o h: Design the signal connection mechanisms with bike locks for control operations.
o i: Design the security scheme to safeguard transactions over the internet, ensuring data protection and compliance.
o j: Develop interface templates for review, including layout, navigation, and visual elements.
o k: Create a site map or hierarchy chart to illustrate the flow of web pages and user interactions.
• Implementation
o l: Create individual web pages based on the approved designs.
o m: Create the database as per the designed schema.
o n: Source necessary library modules for client-side coding to enhance development efficiency.
o o: Purchase a set of bike locks for coding and testing purposes.
o p: Code server-side modules for system administration and operations.
o q: Code server-side modules for end-user services.
o r: Code client-side modules for system administration and operations.
o s: Code client-side modules for end-user services.
o t: Integrate server-side modules and web pages to form a cohesive system.
• Deployment
o u: Test the connection to bike locks with the shared-bike app to ensure proper functionality.
o v: Perform performance stress tests on the system to verify handling of transactions and concurrent users.
o w: Conduct User Acceptance Testing (UAT) with the sponsor and end-user representatives.
o x: Install the website on the government's web server for operation.
o y: Create technical training materials for staff.
o z: Train staff in operating and maintaining the system.
2.2 Gantt Chart
The Gantt Chart below visualizes the project schedule, illustrating task durations and dependencies to ensure a clear understanding of the project timeline.
Note: The start date is set as 01-01-2024. The milestones are set to the dates provided by the sponsor:
• Prototype Delivery Milestone (m1): Prototype must be delivered within two months (by 01-03-2024).
• Intermediate Modules Milestone (m2): Intermediate modules must be delivered within five months (by 01-06-2024).
• Project Completion Milestone (m3): Project must be fully completed within eight months (by 01-09-2024).
Task Dependencies and Durations
The table below outlines each task's duration and dependencies:
Activity ID Activity Name Duration (Days) Predecessors
a Background study on e-payment implementation 18 -
b Requirements Analysis 20 a
c Technical Feasibility Study 22 b
d System Design 25 b
e Module Design 15 d
f Interface Design 25 d
g Database Design 15 f
h UI Design 15 d
i Security Design 20 d
j Integration Testing 12 f, g
k System Testing 12 j
l Coding Core Modules 30 k
m Coding Module E 20 e
n Coding Module F 20 f
o Develop UI 12 h
p Database Implementation 25 i, g
q Security Implementation 30 i
r Testing Module N 25 n
s Testing Module S 25 n
t Final Integration 20 l, m, p, q, r, s
u Deployment Preparation 5 t, o
v System Deployment 5 u
w User Training 5 v
x Project Handover 12 w
y Post-Deployment Support 20 x
z Project Closure 19 y
3 Project Schedule Management
In this chapter, we present the project schedule management plan, including the Network Diagram in Precedence Diagramming Method (PDM) format, and conduct a Critical Path Analysis (CPA).
3.1 Network Diagram in PDM
The following network diagram represents the project's activities using the Precedence Diagramming Method (PDM). Each node corresponds to a task identified by its activity ID.
Legend:
• Nodes represent tasks labeled from a to z.
• Arrows indicate task dependencies.
3.2 Critical Path Analysis
Critical Path Analysis (CPA) identifies the sequence of tasks that determines the minimum project duration. Tasks on the critical path have zero slack.
3.2.1 Forward Pass (Calculating Early Start and Early Finish)
Task Duration (Days) Predecessors Early Start (ES) Early Finish (EF)
a 18 - 0 18
b 20 a 18 38
c 22 b 38 60
d 25 b 38 63
e 15 d 63 78
f 25 d 63 88
g 15 f 88 103
h 15 d 63 78
i 20 d 63 83
j 12 f, g 103 115
k 12 j 115 127
l 30 k 127 157
m 20 e 78 98
n 20 f 88 108
o 12 h 78 90
p 25 i, g 103 128
q 30 i 83 113
r 25 n 108 133
s 25 n 108 133
t 20 l, m, p, q, r, s 157 177
u 5 t, o 177 182
v 5 u 182 187
w 5 v 187 192
x 12 w 192 204
y 20 x 204 224
z 19 y 223 243
3.2.2 Backward Pass (Calculating Late Start and Late Finish)
Assuming the project's finish time is 244 days.
Here's the completed backward pass table:
Task Duration (Days) Successors Late Finish (LF) Late Start (LS) Slack (LS - ES)
z 19 - 243 223 0
y 20 z 224 204 0
x 12 y 204 192 0
w 5 x 192 187 0
v 5 w 187 182 0
u 5 v 182 177 0
t 20 u 177 157 0
l 30 t 157 127 0
k 12 l 127 115 0
j 12 k, p 115 103 0
g 15 j, p 103 88 0
p 25 t 152 127 24
q 30 t 152 122 39
m 20 t 157 132 54
e 15 m 132 117 54
d 25 e, f, h, i 63 38 0
f 25 g, j, n 88 63 0
r 25 t 152 127 19
s 25 t 152 127 19
n 20 r, s 127 107 39
i 20 p, q 122 102 42
o 12 u 177 165 87
h 15 o 165 150 87
b 20 d, c 38 18 0
a 18 b 18 0 0
c 22 - 60 38 0
3.2.3 Identifying the Critical Path
Tasks with zero slack form the critical path. The critical path for this project is:
• a - b - d - f - g - j - k - l - t - u - v - w - x - y - z
Project Duration: 8 months, 243 days (Including holidays)
4 Project Budget Management
In this chapter, we detail the Project Cost Management plan, including resource allocation, cost baseline, and Earned Value Management (EVM) analysis. We also present the performance measurements, variance analysis, and forecasting based on the project’s progress at the end of the fourth month.
4.1 Resource Sheet
Below is the Resource Sheet summarizing all the resources involved in the project, their hourly rates, total hours worked, and total costs.
Table 4.1: Resource Sheet
WBS (Simplified) Hourly Rate (/hr)TotalHoursTotalCost() % of Total
Human Resources 1,431,40071.3ProjectManager(PM)500 640 320,00015.9Bill(SeniorDeveloper)300 1,210 363,00018.0Lisa(Developer)200 1,294 258,80012.8Andy(Developer)200 1,192 238,40011.8Kent(Developer)200 1,256 251,20012.5OtherCosts248,000 12.4%
Hardware/Equipment Purchases 16,0000.8ComputingFacilitiesRental(8months@29,000/month) 232,00011.6ContingencyReserve(20335,880 16.7%
Total Project Cost $2,015,280 100%
Notes:
o PM (Project Manager): Works an average of 4 hours per day on general project management tasks throughout the project and additional hours during specific tasks such as requirements analysis, project handover, and project closure.
o Bill: Leads analysis and design tasks, contributing significantly during the initial phases of the project.
o Lisa, Andy, Kent: Work on design, implementation, and deployment tasks, with efforts fairly distributed among them.
4.3 Planned Values (PVs) for the 8 Months
Table 4.3: Cumulative Planned Values
Month Cumulative Planned Value (PV) ()1268,7102518,2203767,73041,017,24051,266,75061,516,26071,765,77082,015,2804.4EarnedValueManagement(E1,017,240 (from the Cost Baseline)
• Actual Cost (AC): 1,085,994.5(actualexpenditureincurred1,000,000 (value of work actually completed)
4.4.1 EVM Calculations
• Cost Variance (CV): CV = EV - AC = 1,085,994.5−1,017,240 = -68,754.5oNegativeCVindi1,000,000 - 1,017,240=1,000,000 / 1,1,000,000 / 1,017,2402,015,280 / 0.921 ≈ $2,188,143.322
o EAC projects the total cost at completion based on current performance.
• Estimate Time to Complete (ETC): time estimate / SPI = 8 / 0.983 = 8.138 (month)
o ETC is the expected cost to finish all remaining project work.
4.5 EVM Graph
Figure 4.1: EVM Graph at End of Month 4
Note: The EVM graph plots the cumulative values of PV, EV, and AC over the project duration.
4.6 Project Performance and Forecasting Description
At the end of the fourth month, the project’s performance indicators suggest that we are behind schedule and over budget. The Schedule Variance (SV) of -17,240 and Schedule Performance Index (SPI) of 0.983 indicate that less work has been accomplished than initially planned. This could be due to delays in completing key tasks or underestimation of the time required for certain activities.
The Cost Variance (CV) of -68,754.5andCostPerformanceIndex(CPI)of0.921showthattheprojectisincurringhigh2,188,143.322, which exceeds the original budget (including contingency) by $68,754.5. This indicates a potential cost overrun if corrective actions are not taken. The •Estimate Time to Complete (ETC) is 8.138 month, suggesting that it will take some more time to complete the project.
To address these issues, we need to:
• Analyze the Causes: Investigate the reasons for schedule delays and cost overruns, such as scope changes, resource inefficiencies, or technical challenges.
• Implement Corrective Actions: Reallocate resources, optimize processes, and implement cost-saving measures to improve CPI and SPI.
• Update the Schedule and Budget: Adjust the project plan to reflect realistic timelines and costs, ensuring that stakeholders are informed of any changes.
By taking proactive steps, we aim to bring the project back on track, minimize the cost overrun, and meet the project’s objectives within the adjusted budget and schedule.
code
*Project Cost Management Requirement*
Assume that you have 4 people working on the project, including one experienced team
member (Bill) who is good at analysis and design and charges $300 per hour; and three others
(Lisa, Andy and Kent) who are good at design and implementation and each of them charges
$200 per hour. All of them can deal with other tasks, such as deployment. You are the project
manager who takes part in managing the entire development process and you charge $500 per
hour. Besides, you must take hardware/equipment into your budget consideration as well.
Although the project does not include the purchase of bike locks and other equipment for the
later operation, you still need some for the development purpose. (Do a little market study on
the current prices of the needed equipment, e.g. mobile phones, bike locks, though marks will
not be deducted much for inaccurate estimations of hardware).
(a) Based on the project schedule, assign tasks to team members according to their
capabilities (including yourself) reasonably for the entire project. Except for you, the other
team members should be fairly assigned with workload as much as possible. Calculate the
costs and make up a Resource Sheet (just a table to show all the resources and their costs;
and the number of hours worked of human resource and the total costs in the project).
(b) Use the data from Resource Sheet to make the budget schedule (Cost Baseline) for your
project. Don’t forget to add the Contingency Reserve to the Cost Baseline table to make it
look complete.
(c) The required computing facility (for development), including computers, printers, network
equipment, along with necessary maintenance services, are rented for a certain amount (i.e.
$29,000) per month.
(d) At the end of the 4
th month, you are obligated to provide a progress report to your senior
management. Utilize the Earned Value Management (EVM) method to conduct the
necessary performance measurements, variance analysis and forecasting for your project.
(You need to make up reasonable figures for Earned Values and Actual Costs. Show the
detailed steps of calculations.)
(e) Exhibit the EVM graph to show relevant calculations and results of performance and
forecasting.
(f) Write a paragraph to describe the project progress at the end of 4
th month based on
the graph and figures in (d) and (e).
my colleague gave me Project Cost Management Requirement and let me rewrite to meet this requirement, can you help me do that?
4 Project Budget Management
This chapter outlines the Project Cost Management plan, including resource allocation, the Cost Baseline, and an Earned Value Management (EVM) analysis at the end of the fourth month. The plan ensures that all project expenses are accounted for and that resource utilization aligns with the project's objectives and constraints.
4.1 Resource Allocation and Task Assignment
Based on the project schedule and team capabilities, tasks have been assigned to team members to ensure efficient utilization of skills and fair distribution of workload among team members, excluding the Project Manager (PM). The PM oversees the entire development process and participates in key tasks.
Task Assignments
Analysis Phase:
Task a: Background study on e-payment implementation (18 days)
Assigned to: Bill
Task b: Requirements Analysis (20 days)
Assigned to: Bill, PM
Task c: Technical Feasibility Study (22 days)
Assigned to: Bill, PM
Design Phase:
Task d: System Design (25 days)
Assigned to: Bill, PM
Task e: Module Design (15 days)
Assigned to: Bill, Lisa
Task f: Interface Design (25 days)
Assigned to: Lisa, Kent
Task g: Database Design (15 days)
Assigned to: Bill, Andy
Task h: UI Design (15 days)
Assigned to: Lisa, Kent
Task i: Security Design (20 days)
Assigned to: Bill, Andy
Task j: Integration Testing (12 days)
Assigned to: Andy, Kent
Task k: System Testing (12 days)
Assigned to: Andy, Kent
Implementation Phase:
Task l: Coding Core Modules (30 days)
Assigned to: Lisa, Andy
Task m: Coding Module E (20 days)
Assigned to: Lisa
Task n: Coding Module F (20 days)
Assigned to: Kent
Task o: Develop UI (12 days)
Assigned to: Lisa, Kent
Task p: Database Implementation (25 days)
Assigned to: Bill, Andy
Task q: Security Implementation (30 days)
Assigned to: Bill, Andy
Task r: Testing Module N (25 days)
Assigned to: Kent
Task s: Testing Module S (25 days)
Assigned to: Lisa
Task t: Final Integration (20 days)
Assigned to: All team members (PM, Bill, Lisa, Andy, Kent)
Deployment Phase:
Task u: Deployment Preparation (5 days)
Assigned to: PM, Andy
Task v: System Deployment (5 days)
Assigned to: Andy
Task w: User Training (5 days)
Assigned to: Lisa
Task x: Project Handover (12 days)
Assigned to: PM, Bill
Task y: Post-Deployment Support (20 days)
Assigned to: Andy, Kent
Task z: Project Closure (19 days)
Assigned to: PM
Total Hours Worked
Each team member's total hours are calculated based on task assignments:
PM: 984 hours
Bill: 1,776 hours
Lisa: 1,336 hours
Andy: 1,552 hours
Kent: 1,288 hours
4.2 Resource Sheet
The Resource Sheet summarizes all resources, their hourly rates, total hours worked, and total costs.
Table 4.1: Resource Sheet
Resource
Rate ($/hr)
Total Hours
Total Cost ($)
Project Manager (PM)
$500
984
$492,000
Bill (Senior Developer)
$300
1,776
$532,800
Lisa (Developer)
$200
1,336
$267,200
Andy (Developer)
$200
1,552
$310,400
Kent (Developer)
$200
1,288
$257,600
Subtotal Human Resources
6,936
$1,860,000
Hardware/Equipment Purchases
-
-
$16,000
Computing Facilities Rental
-
-
$232,000
Total (Before Contingency)
$2,108,000
Contingency Reserve (20%)
$421,600
Total Project Cost
$2,529,600
Note: The Contingency Reserve accounts for potential risks and unforeseen expenses.
4.3 Cost Baseline (Budget Schedule)
The Cost Baseline outlines planned expenditures over the project's duration, including the Contingency Reserve.
Table 4.2: Cost Baseline
Month
PM ($)
Bill ($)
Lisa ($)
Andy ($)
Kent ($)
Computing Facilities ($)
Equipment Purchases ($)
Planned Cost ($)
Contingency Reserve (20%)
Cumulative Planned Cost ($)
1
61,500
66,600
33,400
38,800
32,200
29,000
16,000
277,500
55,500
333,000
2
61,500
66,600
33,400
38,800
32,200
29,000
0
261,500
52,300
646,800
3
61,500
66,600
33,400
38,800
32,200
29,000
0
261,500
52,300
960,600
4
61,500
66,600
33,400
38,800
32,200
29,000
0
261,500
52,300
1,274,400
5
61,500
66,600
33,400
38,800
32,200
29,000
0
261,500
52,300
1,588,200
6
61,500
66,600
33,400
38,800
32,200
29,000
0
261,500
52,300
1,902,000
7
61,500
66,600
33,400
38,800
32,200
29,000
0
261,500
52,300
2,215,800
8
61,500
66,600
33,400
38,800
32,200
29,000
0
261,500
52,300
2,529,600
Total
492,000
532,800
267,200
310,400
257,600
232,000
16,000
Notes:
Hardware/Equipment Purchases of $16,000 are incurred in Month 1.
Computing Facilities Rental is $29,000 per month for development infrastructure.
Contingency Reserve is calculated as 20% of the Planned Cost each month.
4.4 Planned Values (PV) for the 8 Months
Table 4.3: Cumulative Planned Values Including Contingency Reserve
Month
Cumulative Planned Value (PV) ($)
1
333,000
2
646,800
3
960,600
4
1,274,400
5
1,588,200
6
1,902,000
7
2,215,800
8
2,529,600
4.5 Earned Value Management (EVM) Analysis at End of Month 4
At the end of the fourth month, an Earned Value Management analysis was conducted to assess the project's performance.
Assumed Values at End of Month 4:
Planned Value (PV): $1,274,400 (from the Cost Baseline)
Actual Cost (AC): $1,350,000 (actual expenditure incurred)
Earned Value (EV): $1,200,000 (value of work actually completed)
4.5.1 EVM Calculations
Cost Variance (CV):
CV = EV - AC
CV = 1,200,000−1,350,000 CV = -$150,000
Negative SV indicates the project is behind schedule.
Cost Performance Index (CPI):
CPI = EV / AC
CPI = 11,350,000
4.5.2 Variance Analysis
The Cost Variance of -$150,000 indicates that the project has spent more than the value of work completed, suggesting cost overruns.
The Schedule Variance of -$74,400 shows that the project work is behind the planned schedule.
The CPI of 0.8889 reveals a cost efficiency below the ideal value of 1, indicating that for every dollar spent, only $0.8889 worth of work has been completed.
The SPI of 0.9416 suggests that the project is progressing at 94.16% of the planned rate.
4.6 EVM Graph
Figure 4.1: EVM Graph at End of Month 4
[image: EVM Graph]
Note: The EVM graph plots the cumulative values of PV, EV, and AC over the project's duration, highlighting the variances at the end of Month 4.
4.7 Project Performance and Forecasting Description
At the end of the fourth month, the project is experiencing both schedule delays and cost overruns. The Schedule Variance (SV) of -$74,400 and Schedule Performance Index (SPI) of 0.9416 indicate that the project is behind schedule, with less work completed than planned. The delay may stem from unforeseen complexities in design tasks or resource allocation inefficiencies.
The Cost Variance (CV) of -$150,000 and Cost Performance Index (CPI) of 0.8889 reveal that the project is over budget, spending more than the value of completed work justifies. Factors contributing to the cost overrun could include higher resource costs, extended working hours, or additional expenses not anticipated during planning.
The Estimate at Completion (EAC) projects the total project cost to be approximately 2,846,400∗∗,exceedingtheori316,800. The project is also projected to extend to , half a month beyond the planned duration.
Actions to Address Performance Issues:
Root Cause Analysis: Investigate specific reasons for cost overruns and schedule delays, such as scope changes, technical challenges, or resource shortages.
Resource Reallocation: Optimize resource utilization by balancing workloads and possibly bringing in additional support to critical tasks.
Cost Control Measures: Implement cost-saving strategies, negotiate better rates with suppliers, and minimize unnecessary expenses.
Schedule Recovery Plan: Accelerate lagging tasks where possible, adjust task dependencies, and consider overtime where justified.
Stakeholder Communication: Keep all stakeholders informed of the project's status, challenges faced, and measures being taken to mitigate issues.
By proactively addressing these challenges, the project team aims to realign with the original objectives, minimize the budget overrun, and deliver the project successfully.