napisz minutki ze spotkania po angielsku, podziekowanie za uczestnictwa, jednomyslnie…
- User
napisz minutki ze spotkania po angielsku,
podziekowanie za uczestnictwa,
jednomyslnie reklamacja 70/2024 uznana za zasadna Reklamacja - RN 90/2024 - wałki zostaną zabrane spowrotem do TNB jednak TNB nie uznaje reklamacji.
TNB przygotuje mapę produkci z informacjami na temat rodzaju kotronli produktu TNB zrobi analize ryzyka - przesledzenie potenjalnych wad powsatłych w procesie kucia TNB aktualizacja raportów 8D
Natepny update w przyszłym tygodniu
- Assistant
Meeting Minutes
Date: [Insert Date]
Time: [Insert Time]
Attendees: [List of Attendees]
1. Opening
- The meeting commenced with a warm welcome and appreciation for everyone’s participation. Thank you all for being here today.
2. Complaints Review
-
Complaint 70/2024:
The committee unanimously accepted complaint 70/2024 as valid. -
Complaint RN 90/2024:
The rollers will be returned to TNB; however, TNB does not acknowledge this complaint as valid.
3. Action Items from TNB
-
TNB will prepare a production map containing information about the types of product controls.
-
TNB will conduct a risk analysis to investigate potential defects arising from the forging process.
-
TNB will provide an update on the 8D reports.
4. Next Update
- User
uzyj prostrzych słów
- Assistant
Meeting Minutes
Date: [Insert Date]
Time: [Insert Time]
Attendees: [List of Attendees]
1. Opening
- The meeting began with a thank you to everyone for coming.
2. Complaints Review
-
Complaint 70/2024:
The group agreed that complaint 70/2024 is valid. -
Complaint RN 90/2024:
The rollers will be sent back to TNB, but TNB does not accept this complaint.
3. Action Items from TNB
-
TNB will create a production map that shows what type of product controls are in place.
-
TNB will do a risk analysis to check for possible issues that might occur during the forging process.
-
TNB will update the 8D reports.
4. Next Update
- We will meet again next week for updates on these topics.
Adjournment:
The meeting ended with another thank you to everyone for their help.
- User
prezentacja bedzie udostepnion pózniej
- Assistant
Meeting Minutes
Date: [Insert Date]
Time: [Insert Time]
Attendees: [List of Attendees]
1. Opening
- The meeting began with a thank you to everyone for attending.
2. Complaints Review
-
Complaint 70/2024:
The group agreed that complaint 70/2024 is valid. -
Complaint RN 90/2024:
The rollers will be sent back to TNB, but TNB does not accept this complaint.
3. Action Items from TNB
-
TNB will create a production map that shows what type of product controls are in place.
-
TNB will do a risk analysis to check for possible issues that might occur during the forging process.
-
TNB will update the 8D reports.
4. Presentation Sharing
- The presentation will be shared later.
5. Next Update
- We will meet again next week for updates on these topics.