What is project quality management?
The processes or activities an organization takes to identify quality requirements.
The processes or activities an organization takes to identify quality requirements and how they meet those qualifications or standards fulfilling stakeholder needs.
How an organization meets qualifications or standards in order to fulfill stakeholder needs.
Status: [object Object]
1 point
2.
Question 2
Consider buying when...
The organization has the capability to perform the work.
It's more cost effective to do the work internally
Suppliers have greater expertise
All of the above
Status: [object Object]
1 point
3.
Question 3
How do you identify risks to your project or its quality?
Use tools to help identify potential risks before they happen.
Use tools to help identify potential risks after they happen.
Use tools to help identify potential risks while they are happening.
Status: [object Object]
1 point
4.
Question 4
Which is not a process included in the qualitative analysis used to prioritize risks?
Identify the likelihood the event will occur
Measure the impact of the event
Sort risks in priority ranking based on the severity
Create a project rating
Status: [object Object]
1 point
5.
Question 5
A quality plan that is properly implemented prevents issues and _____ the number of identified problems during final inspection.
Decreases
Increases
Cancels out
Status: [object Object]
1 point
6.
Question 6
The level of risk depends on...
Likelihood and Severity
Likelihood and Cost
Severity and Cost
Status: [object Object]
1 point
7.
Question 7
Which is a part of the Project Procurement Management Process?
Initiating and Planning
Executing
Monitoring and Controlling
All of the above
Status: [object Object]
1 point
8.
Question 8
The objectives of project risk management are to decrease the likelihood of positive events and increase the probability of negative events.
True
False
Status: [object Object]
1 point
9.
Question 9
Transfer strategies move the risk to _____ who is better equipped to handle it.
Your boss
The project manager
A third party
Status: [object Object]
1 point
10.
Question 10
Managing and leading a project means that you must not only manage the execution of the _____, but the management of the _____ as well.
Project, yourself
Team, yourself
Project, team
Status: [object Object]
1 point
11.
Question 11
What is used to complete quality controls in order to ensure that you are meeting your agreed upon goals for quality?
Cost Audit
Quality Audit
Risk Audit
Status: [object Object]
1 point
12.
Question 12
What does the actual management of the team not include?
Expecting perfect performance
Tracking performance
Providing feedback
Resolving issues
Status: [object Object]
1 point
13.
Question 13
Budget, time, contracts, other projects, etc. are constraints that may impact the project and team.
True
False
Status: [object Object]
1 point
14.
Question 14
Which is not an output due to effective management?
Updated documents
Leaving internal processes the same
Change requests
Status: [object Object]
1 point
15.
Question 15
A Risk Management Plan...
Documents how to conduct the risk management activities.
Aligns the project risk approach with the risk profile of the organization.
Communicates the project risk approach to the stakeholders and helps to gain support.
All of the above
Status: [object Object]
1 point
16.
Question 16
A time and material contract can resemble a cost-reimbursable contract by using what?
Fixed fee
Sliding fee
Unit rate prices
Status: [object Object]
1 point
17.
Question 17
What is included in a quality management plan?
Scope baseline
Schedule baseline
Cost baseline
All of the above
Status: [object Object]
1 point
18.
Question 18
Which is a part of a control procurement?
Acceptance of Final Documentation
Lessons Learned Documentation
Procurement Performance Reviews
Status: [object Object]
1 point
19.
Question 19
The seller of the goods, services, or results will typically treat the procurement event as a(n) _____ .
Project
Event
Transaction
Status: [object Object]
1 point
20.
Question 20
Which of these is the correct order of the stages of team development?
Norming, Forming, Storming, Performing, Adjourning
Forming, Storming, Norming, Performing, Adjourning
Forming, Storming, Performing, Norming, Adjourning
Status: [object Object]
1 point
21.
Question 21
What is the most commonly used Fixed Price Contract?
Firm Fixed Price Contracts
Fixed Price with Economic Price Adjustment
Fixed Price Incentive Fee
Status: [object Object]
1 point
22.
Question 22
What is a key input to the Risk Management Plan?
Project Management Plan
Stakeholder Register
Organizational Process Assets
All of the above
Status: [object Object]
1 point
23.
Question 23
What is included in the Procurement Statement of Work?
Quality requirements
Performance data
Work locations
All of the above
Status: [object Object]
1 point
24.
Question 24
What does quality assurance not include?
Inspection of the process and continuous process improvement
Uses tools to identify whether or not the project is meeting agreed upon quality standards
Is often overseen by the project manager
Status: [object Object]
1 point
25.
Question 25
What can you do as the PM to make the team more effective?
Team-building Activities
Interpersonal Communication
Team Training
All of the above