Create a precedence activity network using the following details,…
- User
Create a precedence activity network using the following details, Activity=A,B,C,D,E,F,G,H,I,J,K,L. depends= A=null A,B,A,D,B,B,G,C,G,EF,IH. durations (days) = 5,7,6,5,10,15,8,8,4,4,7,5. calculate the earliest and latest start and end dates and the float associated with each activity.from this identity the critical path