CERCLA § 107 provides a right of action in favor of a private party who has expended costs in the remediation and removal of hazardous substances released or generated by the owner/operator of a facility. 42 U.S.C. § 9607(a)(2)(B). American Color, as the party seeking reimbursement or prospective relief must establish four elements:
a. The Lobeco plant site is a "facility", pursuant to 42 U.S.C. § 9601(9);
b. Tenneco is a "covered person" as defined in 42 U.S.C. § 9607(a);
c. A "hazardous substance" as defined in 42 U.S.C. § 9601(14), was "released" at or from the site, as release is defined in 42 U.S.C. § 9601(22), during the time Tenneco acted as the owner/operator or generator; and
d. American Color has incurred necessary "response costs" in the remediation of the site and/or removal of the hazardous substances, which costs are not inconsistent with the National Contingency Plan ("NCP") relating to such action. 40 C.F.R. § 300.700(c)(3)(i).
-
Tenneco has admitted the first three of these four elements that were alleged by American Color in its Amended Complaint, which elements are necessary to prove a CERCLA claim.
-
CERCLA was enacted for the "protection and preservation of public health ..." General Electric v. Litton Business Systems, 715 F.Supp. 949, 961 (W.D.Mo. 1989), aff'd, 920 F.2d 1415 (8th Cir.1990). Such statutes are "to be given an extremely liberal construction for the accomplishment of their beneficial objectives." Id. at 961. The goal of § 107 is "to induce [private parties] voluntarily to pursue appropriate environmental response actions ..." Id. at 962 (emphasis in original). CERCLA was enacted "to encourage ... private cleanup efforts, ... to preserve the limited resources of the government and the Superfund, and to make those responsible bear the burden of the conditions they created." Con-Tech Sales Defined Benefit Trust v. Cockerham, 1991 WL 209791, at *4 (E.D.Pa.1991).
*956 4. Tenneco has admitted that the 1990 NCP governs this remediation. Trial Transcript at Vol. IX, p. 51. The court agrees. The 1990 NCP controls if the remediation was underway as of April 9, 1990, the enactment date of the 1990 NCP. This is clearly true of the PCB remediation involved in this case. 55 Fed.Reg. 8795 (1990); Tri-County Business Campus Joint Venture v. Clow Corp., 792 F.Supp. 984, 990 (E.D.Pa.1992); ConTech, Supra, at *8.
-
The 1990 NCP clarified the 1985 NCP. 55 Fed.Reg. 8666 (1990).
-
The standard for compliance under the 1990 NCP is substantial compliance, not strict compliance. 40 CFR 300.700(c)(3)(i). "Immaterial or insubstantial" deviation from the items set forth in the 1990 NCP will not cause the cleanup to be deemed inconsistent. 40 CFR § 300.700(c)(4).
-
The NCP is a regulatory framework governing the cleanup of hazardous wastes. "The NCP is not intended to provide complex and detailed site-specific decision-making criteria." General Electric, 715 F.Supp. at 962. The NCP addresses the method of site investigation and analysis of remedial alternatives. The regulations suggest the creation of certain documents that fulfill these goals.
-
Tenneco argued that the only NCP deficiency was the failure to hold a public hearing. Trial Transcript, Vol. V, pp. 132-138, 146-151. Tenneco is thus precluded from any argument that the documentary requirements of the NCP were not fulfilled. The Court finds, however, that documents substantially similar to the documents suggested in the 1990 NCP were prepared in this case. The G & E Report constituted the remedial investigation portion of the remedial investigation ("RI")/feasible study ("FS") (RI/FS). Plaintiff's Trial Exhibit 1. The Lane Plan of Study constituted the RI work plan. See, Lane Deposition Testimony p. 46, I. 6-11; p. 47, I. 20 p. 48, I. 3. Plaintiff's Trial Exhibit 2. Section 8 of the RMT September 1988 Report constitutes the FS portion because it considers and discusses the various remedial alternatives. Plaintiff's Trial Exhibit 5. Section 9 of the RMT Report sets forth the Remedial Action Plan. Id. The Remedial Design ("RD")/Remedial Action ("RA") (RD/RA) phase is also substantially represented in the documents submitted by the parties to DHEC. The RMT Project Manual (which took the form of a construction bid document) is the RD. Plaintiff's Trial Exhibit 3. DHEC approved RMT's Sampling and Analysis Plan (SAP) in October 1989. Plaintiff's Trial Exhibit 271. OHM Corporation was selected to perform the Remedial Action (RA). In January 1990, OHM submitted its contractor's RA work plan to DHEC. DHEC's acceptance of Lane's Final Report on the dig and haul portion of the remediation constitutes a Final Report under the NCP. See Plaintiff's Exhibit 303. A Health and Safety Plan was also submitted. Plaintiff's Trial Exhibit 8.
-
The 1990 NCP requires an opportunity for public comment concerning the selection of a response action and calls for meaningful public participation in that process. A public hearing is not expressly required by the 1990 NCP. 40 CFR § 300.700(c)(6).
-
Compliance with state requirements that are substantially equivalent to those found in the 1990 NCP, or that provide substantially equivalent protections as those found in the 1990 NCP, constitutes substantial compliance with the public participation requirement of the 1990 NCP. 40 C.F.R. § 300.700(c)(6); See also General Electric, 715 F.Supp. at 961.
-
The extensive involvement of government agencies charged with protection of the public interest may serve as a substitute for public comment. General Electric, 715 F.Supp. at 961.
-
The court finds that the rationale of the General Electric court controls this action, although this action arises under the 1990 NCP, whereas the General Electric action arose under the 1985 NCP. The 1990 NCP did not radically change the public participation element of the 1985 NCP nor was it intended to increase the difficulty of a plaintiff in recovering necessary response costs. Indeed, the opposite is true. Compare 40 C.F.R. § 300.71(a)(2)(ii) to 40 C.F.R. § 300.700(c)(6). Neither version of the NCP *957 expressly requires a public hearing, but both require an opportunity for meaningful public comment. Id.
-
General Electric recognizes that state agencies charged with duties involving overseeing the remediation of hazardous wastes, fulfill the function of public participation where parties voluntarily undertake to act pursuant to the agency's instructions and with the agency's comprehensive input. 715 F.Supp. at 961-963. This court agrees with that reasoning and recognizes that governmental agencies charged with protection of the public interest may serve as substitutes for participation by individual members of the public, at least where the agency is actively involved in all aspects of the investigation, planning, and remediation of a release of a hazardous substance, as was the case here. The court also notes that the Fourth Circuit has not rejected General Electric and has seemingly implicitly adopted its rationale. Channel Master Satellite Systems, Inc. v. JFD Electronics Corp., 702 F.Supp. 1229 (E.D.N.C.1988) (Court considered arguments as to whether a party's compliance with meager state requirements satisfied the NCP, implicitly indicating that the reasoning of General Electric was to be followed, because the consideration would have been rendered unnecessary by a rejection of General Electric).
-
The response costs incurred by American Color were in substantial compliance with the 1990 NCP.
-
The court agrees with the Advisory Jury's answer to the Special Interrogatory that the public was provided with an opportunity for meaningful public comment concerning the selection of a response action. The fact that the public actually influenced which remedial alternative was chosen, indeed influencing the parties to select the most expensive alternative of those under consideration, has influenced the Court's decision that the public had a meaningful opportunity to participate in the remediation process.
-
The newspaper coverage outlined above, the Meeks' and other Lobeco employees' communications with individual members of the public, and participation of the public's elected officials such as the Beaufort County Council adequately apprised the public in this very small community of the remediation, so that the public could have participated even more in the selection of a remedial alternative if it had wanted to.
-
In addition, under General Electric, the remediation substantially complied with the NCP. In this case, DHEC is statutorily charged with protecting the environment in South Carolina and to "abate, control and prevent pollution." S.C.Code Ann. § 48-1-20; See also SC DHEC v. Armstrong, 293 S.C. 209, 359 S.E.2d 302 (1987). The substantial involvement of DHEC and other government agencies in the investigation and remediation served as a substitute for additional public comment, especially in light of DHEC's duty to protect the public.
-
Public agencies were adequately apprised of and involved in, the remediation, so that they did participate, and could have participated, in the cleanup to the fullest extent.
-
Additionally, the requirements of the DHEC Consent Orders were substantially equivalent to those found in the 1990 NCP. The parties' performance under the DHEC Consent Orders therefore substantially fulfilled the requirements of the 1990 NCP.
-
Although Tenneco contended at trial that a public hearing should have been held regarding the Remedial Action Plan, the Court finds that sufficient information regarding the remediation was disseminated to the public either directly, or through state and federal agencies representing the public interest. The court's conclusion is based in large measure upon Tenneco's failure to proffer any witness who was dissatisfied with the remediation or who would have chosen a different remedial plan, including Tenneco itself. Moreover, Tenneco participated, at least equally, in all phases of the decision-making process regarding the remedy selection in the Remedial Action Plan, and itself suggested and persuaded the other parties to agree to the exclusion of an NCP-consistency clause in the Amended Consent Order. The Court has also considered the fact that DHEC itself did not require a public hearing. The Court is impressed as well with the fact *958 that the remedial plan chosen was the most comprehensive, most expensive and most thorough course of remedial action among the alternatives considered, which achieved a permanent remedy, forever decreasing the volume, toxicity and mobility of the PCB contamination. See e.g., Towe Testimony, Vol. VI, p. 99-100; Plaintiff's Trial Exhibit 5A § 9.
-
Tenneco waived its right to insist on compliance with the NCP when it suggested that NCP-compliance be deleted from the Amended Consent Order. See Lyles v. BMI, Inc., 292 S.C. 153, 355 S.E.2d 282, 285 (1987) (waiver is the intentional relinquishment of a known right). Tenneco purposefully removed the language from the Amended Consent Order and cannot later contend that compliance was required. Additionally, Tenneco is estopped from contending that American Color cannot recover under CERCLA because of the remediation's alleged technical non-compliance with the NCP, as Tenneco participated on at least an equal basis in the decision-making process regarding the selection of the remedial alternative for the cleanup of the PCB contamination, which contamination it alone created at the Lobeco plant site. See Standard Fire Ins. v. Marine Contracting and Towing Co., 301 S.C. 418, 392 S.E.2d 460, 462 (1990).
-
Tenneco is liable for all past and future American Color response costs associated with the Lobeco plant site remediation. But for the presence of PCBs, the Court finds that DHEC would not have ordered the remediation encompassed in the three Consent Orders. These costs include those incurred by American Color under the Second Consent Order, and any future costs associated with the incidental remediation of slight non-PCB contamination occurring as the result of the DHEC-ordered PCB remediation and investigation.
-
Tenneco is legally obligated to reimburse American Color for its response costs. This court previously determined that Tenneco is estopped under Fed.R.Civ.P. 8(c) from raising the defense that it was not the proper defendant.[2]
-
Tenneco's admission of the CERCLA elements as set forth above constitute sufficient positive evidence of its liability for American Color's claims. Tenneco cannot now avoid or disclaim such admissions.
-
Tenneco contends that the indemnification provisions in the 1973 Agreement bar American Color's CERCLA claim, on the purported ground that American Color agreed to indemnify Tenneco for all contingent liabilities. Amended Answer and Counterclaim ¶ 85; 101-120.
*959 26. As discussed above, however, American Color's indemnification liability is limited to at most $500,000 for things known to Tenneco at the time the 1973 Agreement was executed. Plaintiff's Trial Exhibit 25 at ¶ 12.
-
Because Tenneco knew of the PCB contamination as of the execution of the 1973 Agreement, American Color's liability under the 1973 Agreement is limited to at most $500,000. The 1973 Agreement does not preclude recovery by American Color of its CERCLA response costs.
-
The jury returned a verdict in favor of Tenneco for $500,000 on its contractually-based Counterclaim. While this verdict operates as a set-off to the judgment herein granted to American Color, it in no way operates to preclude recovery by American Color of its past and future response costs.
-
The other affirmative defenses or claims for set-off that Tenneco asserted in response to the CERCLA claim, including laches, and American Color's alleged failure to exercise due care are without merit.
-
Tenneco also contends that American Color's CERCLA claim should be reduced or set-off in proportion to American Color's own liability under 42 U.S.C. § 9613(f). Amended Answer and Counterclaim at ¶ 93. In confronting Tenneco's claim, the Court's mandate is to render an equitable result, based upon factors the Court deems appropriate. 42 U.S.C. § 9613(f)(1); See also Environmental Transportation Systems, Inc. v. ENSCO, Inc., 969 F.2d 503, 507 (7th Cir.1992); U.S. v. S.C. Recycling and Disposal, Inc., 653 F.Supp. 984 (D.S.C.1986), aff'd in part and vacated in part, U.S. v. Monsanto Co., 858 F.2d 160 (4th Cir.1988). A party seeking to allocate costs has the burden of proving that allocation is appropriate in a particular case. 969 F.2d at 508. Tenneco has not met its burden of proving that the costs of remediation should be apportioned in a manner that reduces American Color's entitlement to relief.
-
Allocation of response costs is determined on a case by case basis. 969 F.2d at 509. A "court may consider any factors appropriate to balance the equities in the totality of the circumstance." Id. In making the determination the court "may consider several factors, a few factors, or only one determining factor", such as the relative fault of the parties in contributing to the release. Id.
-
Among the factors which have been applied are those suggested in an unsuccessful amendment to CERCLA.[3]Bell Petroleum Services, Inc. v. Sequa Corp., 3 F.3d 889 (5th Cir.1993); In re Hemingway Transport, Inc., 993 F.2d 915 (1st Cir.1993).
-
Tenneco did not introduce evidence that specifically addressed any equitable factor. The evidence which is in the record compels the conclusion that American Color is entitled to full recovery of its response costs. Tenneco is exclusively responsible for the release of PCBs at the site. See Central Maine Power Co. v. O'Connor Co., 838 F.Supp. 641, 645-47 (D.Me.1993) (holding that no future costs for the remediation of lead should be allocated to the party which did not send lead to the contaminated site). PCBs were the contaminant of concern at Lobeco and drove the remedy; American Color did not contribute to the release of the hazardous substance in question; was not involved in the generation, transportation, storage or disposal thereof; was not responsible for exercising due care in connection therewith; and fully cooperated (and continues *960 fully to cooperate) with state and local officials in the investigation and remediation thereof. To the extent the Gore factors are applicable, the Court concludes that Tenneco is not entitled to contribution from American Color or other apportionment of American Color's costs and is not entitled to a finding that some portion of American Color's response costs should be allocated to American Color.
-
The Court finds that Tenneco is fully liable under CERCLA for all past and future response costs incurred by American Color in connection with the investigation and remediation of the release of hazardous substances at the Lobeco site.
-
Tenneco also contends that imposition of liability under CERCLA is unconstitutional. Amended Answer and Counterclaim at ¶ 94. This Court finds that imposition of CERCLA liability is not unconstitutional. Retroactive application of CERCLA does not violate the due process clause because such an application is supported by a "legitimate legislative purpose furthered by rational means ..." U.S. v. Northeastern Pharmaceutical & Chem. Co., 810 F.2d 726, 733 (8th Cir.1986), cert. denied, 484 U.S. 848, 108 S.Ct. 146, 98 L.Ed.2d 102 (1987); U.S. v. Kramer, 757 F.Supp. 397, 429 (D.N.J.1991).
-
American Color is entitled to judgment on its CERCLA claim. Judgment is hereby entered in favor of American Color and against Tenneco in the amount of $6,000,000, together with prejudgment interest as set forth below.
-
CERCLA specifically provides for the recovery of prejudgment interest at 42 U.S.C. § 9607(a)(4). Prejudgment interest in this case shall run from November 14, 1990, the date the American Color filed its Complaint. The filing of a complaint constitutes a written demand for payment which is required under CERCLA. In the Matter of Bell Petroleum Services, Inc., 3 F.3d 889, 907 (5th Cir.1993). CERCLA refers to the interest "specified for interest on investments of the Hazardous Substance Superfund established under subchapter A of Chapter 98 of title 26." 42 U.S.C. § 9607(a)(4). Pursuant to the referenced statute, the prejudgment interest rate shall be "equal to the current average market yield on outstanding marketable obligations of the United States." 26 U.S.C. § 9507(d)(3)(c). Excess Superfund money investments "may be made only in interest-bearing obligation(s) of the United States." 26 U.S.C. § 9602(b)(1). Based on this directive, the interest rates have been computed by averaging the auction average annual rate of six (6) month treasury bills and the average annual rate of composite long term government securities for that year. These rates are published by the Federal Reserve Board. Interest rates used are as follows:
1990 ......................... 7.07%
1991 ......................... 7.07%
1992 ......................... 5.64%
1993 ......................... 4.84%
1994 ......................... 4.93%
1995 ......................... 5.50%