LETS DO PERT in full deatil making activity and event tables and Determine the…
- User
LETS DO PERT in full deatil making activity and event tables and Determine the probabilities that the different nodes of the project are realized
Project (a)Activity (a, m, b) Activity (a, m, b) 1-2 (5, 6, 8) 3-6 (3, 4, 5) 1-4 (1, 3, 4) 4-6 (4, 8, 10) 1-5 (2, 4, 5) 4-7 (5, 6, 8)) 2-3 (4, 5, 6) 5-6 (9, 10, 15) 2-5 (7, 8, 10) 5-7 (4, 6, 8) 2-6 (8, 9, 13) 6-7 (3, 4, 5) 3-4 (5, 9, 19)
graph: Node 1 has edges going to:
Node 2 with weight 10 Node 5 with weight 5Node 2 has edges going to:
Node 3 with weight 9 Node 5 with weight 8 Node 6 with weight 10Node 3 has edges going to:
Node 4 with weight 3 Node 6 with weight 4Node 4 has edges going to:
Node 6 with weight 5Node 5 has edges going to:
Node 6 with weight 7 Node 7 with weight 3Node 6 has edges going to:
Node 7 with weight 8 - Assistant
Certainly! Let's perform a comprehensive PERT (Program Evaluation and Review Technique) analysis for Project (a). This will include creating detailed Activity Tables, Event Tables, identifying the Critical Path, and determining the probabilities of the project’s nodes being realized by specific times.
1. Understanding PERT
PERT is a project management tool used to schedule, organize, and coordinate tasks within a project. It accounts for uncertainty in activity durations by using three time estimates:
- Optimistic time (a)
- Most likely time (m)
- Pessimistic time (b)
From these, we calculate:
- Expected Time (TE)
- Variance (V)
2. Activity Table
The Activity Table lists all project activities, their dependencies, time estimates, expected time, and variance.
2.1. Activity Details
Activity Description Optimistic (a) Most Likely (m) Pessimistic (b) 1-2 Start to Node 2 5 6 8 1-4 Start to Node 4 1 3 4 1-5 Start to Node 5 2 4 5 2-3 Node 2 to Node 3 4 5 6 2-5 Node 2 to Node 5 7 8 10 2-6 Node 2 to Node 6 8 9 13 3-4 Node 3 to Node 4 5 9 19 3-6 Node 3 to Node 6 3 4 5 4-6 Node 4 to Node 6 4 8 10 4-7 Node 4 to End 5 6 8 5-6 Node 5 to Node 6 9 10 15 5-7 Node 5 to End 4 6 8 6-7 Node 6 to End 3 4 5 2.2. Calculating Expected Time (TE) and Variance (V)
Using PERT formulas:
- Expected Time (TE) = (a + 4m + b) / 6
- Variance (V) = [(b - a) / 6]^2
Activity TE Variance (V) 1-2 6.167 0.25 1-4 2.833 0.25 1-5 3.833 0.25 2-3 5.000 0.111 2-5 8.167 0.250 2-6 9.500 0.694 3-4 10.000 5.444 3-6 4.000 0.111 4-6 7.667 1.000 4-7 6.167 0.250 5-6 10.667 1.000 5-7 6.000 0.444 6-7 4.000 0.111
3. Network Diagram Construction
Before proceeding, it’s essential to visualize the network based on the activities and dependencies:
- Start Node (1) leads to Nodes 2, 4, and 5.
- Node 2 leads to Nodes 3, 5, and 6.
- Node 3 leads to Nodes 4 and 6.
- Node 4 leads to Nodes 6 and 7 (End).
- Node 5 leads to Nodes 6 and 7 (End).
- Node 6 leads to Node 7 (End).
4. Forward Pass (Earliest Times)
Calculates the Earliest Start (ES) and Earliest Finish (EF) times for each node.
4.1. Calculations
-
Node 1 (Start):
- ES = 0
- EF = 0
-
Node 2:
- ES = EF of Node 1 + Activity 1-2 TE = 0 + 6.167 = 6.167
- EF = 6.167
-
Node 4:
- ES = EF of Node 1 + Activity 1-4 TE = 0 + 2.833 = 2.833
- EF = 2.833
-
Node 5:
- ES = EF of Node 1 + Activity 1-5 TE = 0 + 3.833 = 3.833
- EF = 3.833
-
Node 3:
- ES = EF of Node 2 + Activity 2-3 TE = 6.167 + 5 = 11.167
- EF = 11.167
-
Node 6:
- Multiple incoming activities:
- From Node 2 via 2-6: 6.167 + 9.500 = 15.667
- From Node 2 via 2-5 and 5-6: 6.167 + 8.167 + 10.667 = 24.001
- From Node 3 via 3-6: 11.167 + 4 = 15.167
- From Node 4 via 4-6: 2.833 + 7.667 = 10.500
- From Node 5 via 5-6: 3.833 + 10.667 = 14.500
- ES (Node 6) = Maximum of all incoming EF = 24.001
- Multiple incoming activities:
-
Node 7 (End):
- Incoming from:
- Node 6 via 6-7: 24.001 + 4 = 28.001
- Node 5 via 5-7: 3.833 + 6 = 9.833
- Node 4 via 4-7: 2.833 + 6.167 = 9.000
- Node 2 via 2-5 and 5-7: 6.167 + 8.167 + 6 = 20.334
- EF (Node 7) = Maximum of all incoming EF = 28.001
- Incoming from:
4.2. Summary of Earliest Times
Node Earliest Start (ES) Earliest Finish (EF) 1 0 0 2 6.167 6.167 4 2.833 2.833 5 3.833 3.833 3 11.167 11.167 6 24.001 24.001 7 28.001 28.001
5. Backward Pass (Latest Times)
Calculates the Latest Start (LS) and Latest Finish (LF) times for each node.
5.1. Calculations
-
Node 7 (End):
- LF = EF = 28.001
- LS = LF - Duration of incoming activity
-
Node 6:
- LF = LF of Node 7 - Activity 6-7 TE = 28.001 - 4 = 24.001
- LS = 24.001 - 0 = 24.001
-
Node 5:
- Incoming activities to Node 5:
- To Node 6 via 5-6: LF (Node 6) - 10.667 = 24.001 - 10.667 = 13.334
- To Node 7 via 5-7: LF (Node 7) - 6 = 28.001 - 6 = 22.001
- LF (Node 5) = Minimum of the above = 13.334
- LS = 13.334 - 3.833 = 9.501
- Incoming activities to Node 5:
-
Node 4:
- Incoming activities to Node 4:
- To Node 6 via 4-6: LF (Node 6) - 7.667 = 24.001 - 7.667 = 16.334
- To Node 7 via 4-7: LF (Node 7) - 6.167 = 28.001 - 6.167 = 21.834
- LF (Node 4) = Minimum of the above = 16.334
- LS = 16.334 - 2.833 = 13.501
- Incoming activities to Node 4:
-
Node 3:
- Incoming activities to Node 3:
- To Node 4 via 3-4: LF (Node 4) - 10 = 16.334 - 10 = 6.334
- To Node 6 via 3-6: LF (Node 6) - 4 = 24.001 - 4 = 20.001
- LF (Node 3) = Minimum of the above = 6.334
- LS = 6.334 - 11.167 = -4.833 (Negative slack indicates criticality)
- Incoming activities to Node 3:
-
Node 2:
- Incoming activities to Node 2:
- To Node 3 via 2-3: LF (Node 3) - 5 = 6.334 - 5 = 1.334
- To Node 5 via 2-5: LF (Node 5) - 8.167 = 13.334 - 8.167 = 5.167
- To Node 6 via 2-6: LF (Node 6) - 9.500 = 24.001 - 9.500 = 14.501
- LF (Node 2) = Minimum of the above = 1.334
- LS = 1.334 - 6.167 = -4.833 (Negative slack indicates criticality)
- Incoming activities to Node 2:
-
Node 1 (Start):
- Incoming activities to Node 1:
- From Node 1 to Node 2: LF (Node 2) - 6.167 = 1.334 - 6.167 = -4.833
- From Node 1 to Node 4: LF (Node 4) - 2.833 = 16.334 - 2.833 = 13.501
- From Node 1 to Node 5: LF (Node 5) - 3.833 = 13.334 - 3.833 = 9.501
- LF (Node 1) = Minimum of the above = -4.833
- LS = LF - 0 = -4.833
- Incoming activities to Node 1:
5.2. Summary of Latest Times
Node Latest Start (LS) Latest Finish (LF) Slack 1 -4.833 0 0 (Critical) 2 -4.833 6.167 0 (Critical) 4 13.501 16.334 13.501 - 2.833 = 10.668 5 9.501 13.334 9.501 - 3.833 = 5.668 3 6.334 6.334 6.334 - 11.167 = -4.833 (Critical) 6 24.001 24.001 0 (Critical) 7 28.001 28.001 0 (Critical) Note: Negative slack indicates that the activity is on the Critical Path.
6. Identifying the Critical Path
The Critical Path is the longest path through the project network, determining the shortest possible project duration. Activities on this path have zero slack.
Critical Path:
- 1 → 2 (Activity 1-2)
- 2 → 3 (Activity 2-3)
- 3 → 4 (Activity 3-4)
- 4 → 6 (Activity 4-6)
- 6 → 7 (Activity 6-7)
Total Expected Duration (TE) = 6.167 + 5 + 10 + 7.667 + 4 = 32.834 units
7. Project Variance and Standard Deviation
Critical Path Activities and Their Variances:
Activity Variance (V) 1-2 0.25 2-3 0.111 3-4 5.444 4-6 1.000 6-7 0.111 Total Variance (σ²) = 0.25 + 0.111 + 5.444 + 1 + 0.111 = 6.916
Standard Deviation (σ) = √6.916 ≈ 2.63 units
8. Probability Analysis for Node Realizations
PERT assumes that activity durations are normally distributed. The probability of completing the project by a certain time can be calculated using the Z-score:
[ Z = \frac{(T - TE)}{\sigma} ]
where:
- ( T ) = Target time
- ( TE ) = Expected project time
- ( \sigma ) = Standard deviation
8.1. Probability of Completing by TE
- At TE = 32.834 units:
- ( Z = \frac{(32.834 - 32.834)}{2.63} = 0 )
- Probability = 50%
8.2. Probability Examples for Specific Times
-
Probability of Completing in ≤ 30 units:
[ Z = \frac{(30 - 32.834)}{2.63} = \frac{-2.834}{2.63} ≈ -1.079 ]
- Lookup Z=-1.079 in standard normal tables:
- Probability ≈ 14%
- Lookup Z=-1.079 in standard normal tables:
-
Probability of Completing in ≤ 35 units:
[ Z = \frac{(35 - 32.834)}{2.63} = \frac{2.166}{2.63} ≈ 0.825 ]
- Lookup Z=0.825 in standard normal tables:
- Probability ≈ 79%
- Lookup Z=0.825 in standard normal tables:
8.3. Probabilities for Specific Nodes
To determine the probability that specific nodes are realized by their Earliest Finish (EF), we consider their position in the network and associated uncertainties.
Example: Probability that Node 2 is completed by its EF (6.167 units):
- Node 2's LF = 6.167, ES = 6.167
- Since Node 2 is on the Critical Path, its EF aligns with TE.
- Probability = 50%
Example: Probability that Node 5 is completed by its EF (3.833 units):
-
Node 5’s TE = 3.833, Variance = 0.25
-
Standard Deviation for Node 5 (σ5) = √0.25 = 0.5
[ Z = \frac{(3.833 - 3.833)}{0.5} = 0 ]
-
Probability = 50%
Note: Nodes on the Critical Path (e.g., Node 2, Node 3, Node 6) have directly tied probabilities related to the project's TE, whereas others (e.g., Node 5) may have their own variances contributing to different probabilities.
9. Summary and Recommendations
- Project Duration: Expected to complete in 32.834 units with a standard deviation of 2.63 units.
- Critical Path: 1-2-3-4-6-7. Any delay in these activities will directly delay the project.
- Probabilities:
- There's a 50% chance the project will be completed in 32.834 units.
- 14% chance of finishing within 30 units.
- 79% chance of finishing within 35 units.
Recommendations:
- Focus on the Critical Path: Ensure that activities on the critical path are closely monitored and managed to prevent delays.
- Manage Variances: Activities with higher variances (e.g., 3-4 with V=5.444) should be scrutinized for potential risks and mitigation strategies.
- Probability Planning: Use the probability data to set realistic deadlines and buffer times as necessary.
By following this detailed PERT analysis, you can effectively manage and monitor Project (a), ensuring timely completion and optimal resource allocation.