Project Report
Table of Contents
- Introduction
- Project Scope Management
- Project Schedule Management
1 Introduction
This report outlines the project plan for developing the shared bike software platform for the local government. The primary objective is to create a robust, user-friendly system that addresses traffic congestion and air quality issues by promoting a sustainable and healthier lifestyle through a shared bike program.
Purpose of the Report
The purpose of this report is to detail the project scope, schedule, and cost management strategies to ensure the successful completion of the software development within the stipulated 8-month timeframe. This includes defining the Work Breakdown Structure (WBS), project scheduling, resource allocation, budgeting, and performance monitoring.
Project Justification
The shared bike program aims to alleviate traffic congestion and improve air quality in the city. By providing an efficient bike-sharing system, the project promotes sustainable transportation, enhances public health, and contributes to the overall environmental goals of the community.
Team Charter
Project Team Introduction:
- Project Manager: Oversees the entire project, ensuring all tasks are completed on time and within budget.
- Bill: Expert in analysis and design, responsible for requirement gathering and system architecture.
- Lisa, Andy, Kent: Skilled in design and implementation, responsible for UI/UX design, coding, and system integration.
Team Roles and Responsibilities:
| Team Member | Role | Responsibilities | Hourly Rate |
|---|
| PM | Project Manager | Managing project, coordinating team, ensuring milestones are met | $500/hr |
| Bill | Lead Analyst/Designer | Requirement analysis, software architecture, database design | $300/hr |
| Lisa | Designer/Developer | Mobile application UI/UX, client-side coding | $200/hr |
| Andy | Developer | Server-side coding, system integration | $200/hr |
| Kent | Developer | Database implementation, backend services | $200/hr |
Report Structure
The report is structured into three main sections:
- Introduction: Provides an overview of the project, its purpose, justification, and team structure.
- Project Scope Management: Details the Work Breakdown Structure (WBS) and Gantt Chart to outline project tasks and milestones.
- Project Schedule Management: Presents the network diagram using the Precedence Diagramming Method (PDM), critical path analysis, and scheduling strategies to ensure timely project completion.
2 Project Scope Management
Work Breakdown Structure (WBS)
The Work Breakdown Structure (WBS) decomposes the project into manageable sections organized under four high-level activities: Analysis, Design, Implementation, and Deployment. Each task is identified by a unique code (a-z).
graph TD
A[Project: Shared Bike Software Platform]
A --> B[Analysis]
A --> C[Design]
A --> D[Implementation]
A --> E[Deployment]
B --> B1[a: Background study on e-payment]
B --> B2[b: Collect detailed requirements]
B --> B3[c: Develop prototype for payment procedure]
C --> C1[d: Design overall software architecture]
C --> C2[e: Design database]
C --> C3[f: Design end-user interfaces on mobile]
C --> C4[g: Design admin interfaces on desktop]
C --> C5[h: Design signal connection with bike locks]
C --> C6[i: Design security scheme]
C --> C7[j: Develop interface templates]
C --> C8[k: Create site map]
C --> C9[l: Create web pages]
D --> D1[m: Create database]
D --> D2[n: Source library modules for client-side]
D --> D3[o: Purchase bike locks for testing]
D --> D4[p: Code server-side modules (admin)]
D --> D5[q: Code server-side modules (end-user)]
D --> D6[r: Code client-side modules (admin)]
D --> D7[s: Code client-side modules (end-user)]
D --> D8[t: Integrate server-side modules and web pages]
D --> D9[u: Test connection to bike locks]
D --> D10[v: Performance stress tests]
E --> E1[w: Conduct UAT]
E --> E2[x: Install website on server]
E --> E3[y: Create technical training materials]
E --> E4[z: Train staff]
Gantt Chart
The Gantt Chart outlines the project schedule, highlighting task durations, dependencies, and milestones. Due to the text-based medium, a simplified Gantt Chart representation using Mermaid is provided.
gantt
title Shared Bike Software Platform Project Schedule
dateFormat YYYY-MM-DD
section Analysis
a [Background study on e-payment] :a, 2024-01-01, 20d
b [Collect detailed requirements] :b, after a, 30d
c [Develop prototype for payment] :c, after b, 40d
milestone Prototype Delivered :milestone1, after c, 0d
section Design
d [Design software architecture] :d, after c, 25d
e [Design database] :e, after d, 20d
f [Design mobile interfaces] :f, parallel with e, 25d
g [Design admin interfaces] :g, parallel with e, 25d
h [Design signal connection] :h, after d, 20d
i [Design security scheme] :i, after d, 15d
j [Develop interface templates] :j, after f, 15d
k [Create site map] :k, after j, 10d
l [Create web pages] :l, after k, 20d
milestone Design Completed :milestone2, after l, 0d
section Implementation
m [Create database] :m, after e, 15d
n [Source library modules] :n, parallel with m, 10d
o [Purchase bike locks] :o, after n, 5d
p [Code server-side modules (admin)] :p, after m, 30d
q [Code server-side modules (end-user)]:q, after p, 30d
r [Code client-side modules (admin)] :r, after p, 25d
s [Code client-side modules (end-user)]:s, after q, 25d
t [Integrate server-side and web pages]:t, after s, 20d
u [Test connection to bike locks] :u, after t, 15d
v [Performance stress tests] :v, after u, 15d
milestone Implementation Completed :milestone3, after v, 0d
section Deployment
w [Conduct UAT] :w, after v, 15d
x [Install website on server] :x, after w, 10d
y [Create technical training materials]:y, after x, 10d
z [Train staff] :z, after y, 10d
milestone Project Completion :milestone4, after z, 0d
3 Project Schedule Management
Network Diagram (Precedence Diagramming Method - PDM)
The Network Diagram visualizes the dependencies between tasks using the Precedence Diagramming Method (PDM). Each task is represented by its code (a-z), with arrows indicating the sequence and dependencies. Parentheses are encoded as per guidelines.
graph LR
a --> b
b --> c
c --> d
d --> e
d --> f
d --> g
d --> h
d --> i
f --> j
g --> j
j --> k
k --> l
l --> m
m --> p
m --> q
p --> q
p --> r
q --> s
r --> t
s --> t
t --> u
u --> v
v --> w
w --> x
x --> y
y --> z
Activity Details
| Code | Activity Description | Duration (Days) | Predecessors |
|---|
| a | Background study on e-payment | 20 | - |
| b | Collect detailed requirements | 30 | a |
| c | Develop prototype for payment procedure | 40 | b |
| d | Design overall software architecture | 25 | c |
| e | Design database | 20 | d |
| f | Design end-user interfaces on mobile phones | 25 | d |
| g | Design admin interfaces on desktop computers | 25 | d |
| h | Design signal connection with bike locks | 20 | d |
| i | Design security scheme | 15 | d |
| j | Develop interface templates | 15 | f, g |
| k | Create site map | 10 | j |
| l | Create web pages | 20 | k |
| m | Create database | 15 | l |
| n | Source library modules for client-side coding | 10 | m |
| o | Purchase bike locks for testing | 5 | n |
| p | Code server-side modules (system admin and operations) | 30 | m |
| q | Code server-side modules (end-user services) | 30 | p |
| r | Code client-site modules (system admin and operations) | 25 | p |
| s | Code client-site modules (end-user services) | 25 | q |
| t | Integrate server-side modules and web pages | 20 | r, s |
| u | Test connection to bike locks | 15 | t |
| v | Performance stress tests | 15 | u |
| w |
Critical Path Analysis (CPA)
The Critical Path is the longest sequence of tasks that determines the minimum project duration. Identifying the critical path helps in understanding which tasks cannot be delayed without affecting the project's completion date.
Steps to Determine Critical Path:
- List All Activities: As detailed in the Activity Details table above.
- Identify Dependencies: Using the Network Diagram.
- Estimate Durations: Based on the provided durations.
- Calculate Earliest Start (ES) and Earliest Finish (EF) Times:
- Calculate Latest Start (LS) and Latest Finish (LF) Times:
- Determine Slack Time: LF - EF or LS - ES.
- Identify Critical Path: The path with zero slack.
Critical Path Calculation:
-
Path 1: a (20) → b (30) → c (40) → d (25) → e (20) → m (15) → p (30) → q (30) → s (25) → t (20) → u (15) → v (15) → w (15) → x (10) → y (10) → z (10)
Total Duration: 20 + 30 + 40 + 25 + 20 + 15 + 30 + 30 + 25 + 20 + 15 + 15 + 15 + 10 + 10 + 10 = 290 days
-
Path 2: a (20) → b (30) → c (40) → d (25) → f (25) → j (15) → k (10) → l (20) → m (15) → p (30) → q (30) → s (25) → t (20) → u (15) → v (15) → w (15) → x (10) → y (10) → z (10)
Total Duration: 20 + 30 + 40 + 25 + 25 + 15 + 10 + 20 + 15 + 30 + 30 + 25 + 20 + 15 + 15 + 15 + 10 + 10 + 10 = 290 days
-
Path 3: a (20) → b (30) → c (40) → d (25) → g (25) → j (15) → k (10) → l (20) → m (15) → p (30) → q (30) → s (25) → t (20) → u (15) → v (15) → w (15) → x (10) → y (10) → z (10)
Total Duration: Same as above, 290 days
Identified Critical Path:
All three paths share the same total duration of 290 days, indicating multiple critical paths within the project. This means that delays in any tasks along these paths will directly impact the project's completion date.