Shared Bike Software Platform Development Report
Table of Contents
- Introduction
- Project Scope Management
- Project Schedule Management
- Project Cost Management
- Project Resource Management
- Project Risk Management
- Work Distribution
1. Introduction
Purpose of the Report
This report outlines the comprehensive plan for developing a shared bike software platform for the local government. It serves to provide a detailed roadmap, encompassing scope, schedule, cost, resources, risks, and work distribution to ensure the successful and timely completion of the project.
Project Overview
The shared bike program is initiated to mitigate urban traffic congestion and improve air quality by promoting sustainable transportation. This software platform will facilitate bike rentals, fleet management, mobile application functionalities, payment integration, and customer support.
Team Charter
Our project team comprises skilled professionals with diverse expertise:
- Project Manager: Oversees the entire project, ensuring adherence to timelines and quality standards.
- Bill (Senior Analyst/Designer): Leads analysis and design phases, leveraging extensive experience.
- Lisa, Andy, Kent (Designers/Developers): Handle design and implementation tasks, bringing creativity and technical proficiency.
Report Structure
This report is structured into seven key sections:
- Introduction: Overview and objectives.
- Project Scope Management: Work Breakdown Structure (WBS) and Gantt Chart.
- Project Schedule Management: Network Diagram and Critical Path Analysis.
- Project Cost Management: Budgeting and cost analysis.
- Project Resource Management: Resource allocation and management.
- Project Risk Management: Identification and mitigation strategies.
- Work Distribution: Task assignments and responsibilities.
2. Project Scope Management
Work Breakdown Structure (WBS)
The WBS is organized into four high-level activities: Analysis, Design, Implementation, and Deployment. Each activity is broken down into detailed tasks labeled from a to z.
graph TB
A[Project Scope]
A --> B[Analysis]
B --> B1[a. Background study on the e-payment implementation]
B --> B2[b. Collect detailed requirements from government departments]
B --> B3[c. Develop a prototype to show the payment procedure]
A --> C[Design]
C --> C1[d. Design the overall software architecture]
C --> C2[e. Design database]
C --> C3[f. Design end-user interfaces on mobile phones]
C --> C4[g. Design interfaces for admin functions on desktop computers]
C --> C5[h. Design the signal connection with the bike locks]
C --> C6[i. Design the security scheme for safeguarding transactions]
C --> C7[j. Develop interface templates for sponsor review]
C --> C8[k. Create site map or hierarchy chart]
C --> C9[l. Create individual web pages]
A --> D[Implementation]
D --> D1[m. Create database]
D --> D2[n. Source necessary library modules]
D --> D3[o. Purchase bike locks for testing]
D --> D4[p. Code server-side modules (admin and operations)]
D --> D5[q. Code server-side modules (end-user services)]
D --> D6[r. Code client-side modules (admin and operations)]
D --> D7[s. Code client-side modules (end-user services)]
D --> D8[t. Integrate server-side modules and web pages]
A --> E[Deployment]
E --> E1[u. Test connection to bike locks]
E --> E2[v. Performance stress tests]
E --> E3[w. User Acceptance Testing (UAT)]
E --> E4[x. Install website on Government’s web server]
E --> E5[y. Create technical training materials]
E --> E6[z. Train staff on operating and maintaining the system]
Gantt Chart
The Gantt Chart outlines the project timeline, highlighting milestones and dependencies.
gantt
title Project Schedule
dateFormat YYYY-MM-DD
section Analysis
a. Background study :a1, 2024-05-01, 2w
b. Collect requirements :a2, after a1, 3w
c. Develop prototype :a3, after a2, 3w
milestone Prototype Delivered :mil1, after a3, 1d
section Design
d. Software architecture :d1, 2024-05-15, 4w
e. Database design :d2, after d1, 3w
f. End-user interfaces :d3, after d2, 4w
g. Admin interfaces :d4, parallel d3, 4w
h. Signal connection design :d5, after d4, 2w
i. Security scheme design :d6, parallel d5, 2w
j. Interface templates :d7, after d6, 3w
k. Site map creation :d8, after d7, 2w
l. Create web pages :d9, after d8, 4w
milestone Design Complete :mil2, after d9, 1d
section Implementation
m. Create database :m1, 2024-07-01, 3w
n. Source library modules :m2, parallel m1, 2w
o. Purchase bike locks :m3, after m2, 1w
p. Code server modules (admin) :m4, after m3, 4w
q. Code server modules (user) :m5, after m4, 4w
r. Code client modules (admin) :m6, after m5, 3w
s. Code client modules (user) :m7, after m6, 3w
t. Integrate modules :m8, after m7, 2w
milestone Implementation Complete :mil3, after m8, 1d
section Deployment
u. Test bike lock connection :u1, 2024-09-01, 2w
v. Performance stress tests :u2, after u1, 3w
w. User Acceptance Testing :u3, after u2, 2w
x. Install on Government server:x1, after u3, 1w
y. Create training materials :u4, parallel x1, 2w
z. Train staff :u5, after y, 1w
milestone Project Complete :mil4, after z, 1d
3. Project Schedule Management
Precedence Diagramming Method (PDM) Network Diagram
The PDM network diagram illustrates the task dependencies and sequence.
graph LR
a[Background study] --> b[Collect requirements]
b --> c[Develop prototype]
c --> mil1[Prototype Delivered]
d[Design software architecture] --> e[Design database]
e --> f[Design end-user interfaces]
f --> g[Design admin interfaces]
g --> h[Design signal connection]
h --> i[Design security scheme]
i --> j[Develop interface templates]
j --> k[Create site map]
k --> l[Create web pages]
l --> mil2[Design Complete]
mil1 --> d
mil2 --> m[Create database]
m --> n[Source library modules]
n --> o[Purchase bike locks]
o --> p[Code server modules (admin)]
p --> q[Code server modules (user)]
q --> r[Code client modules (admin)]
r --> s[Code client modules (user)]
s --> t[Integrate modules]
t --> mil3[Implementation Complete]
mil3 --> u[Test bike lock connection]
u --> v[Performance stress tests]
v --> w[User Acceptance Testing]
w --> x[Install on Government server]
x --> y[Create training materials]
y --> z[Train staff]
z --> mil4[Project Complete]
Critical Path Analysis (CPA)
Steps to Determine the Critical Path:
- List all activities with their durations.
- Identify dependencies between activities.
- Calculate the earliest start (ES) and earliest finish (EF) times.
- Calculate the latest start (LS) and latest finish (LF) times.
- Determine slack for each activity.
- Identify the longest path with zero slack—this is the critical path.
Critical Path Calculation:
Based on the Gantt Chart and PDM:
- Critical Path: a → b → c → d → e → f → g → h → i → j → k → l → m → n → o → p → q → r → s → t → u → v → w → x → y → z → mil4
- Total Duration: 8 months
Justification:
This path encompasses all major dependencies and milestones, ensuring the project adheres to the 8-month deadline.
4. Project Cost Management
(a) Resource Assignment and Cost Calculation
Resource Allocation
| Task | Assigned To | Hours | Rate ($/hour) | Cost ($) |
|---|
| a | Bill | 80 | 300 | 24,000 |
| b | Bill | 120 | 300 | 36,000 |
| c | Lisa | 100 | 200 | 20,000 |
| d | Bill | 160 | 300 | 48,000 |
| e | Lisa | 120 | 200 | 24,000 |
| f | Andy | 150 | 200 | 30,000 |
| g | Andy | 150 | 200 | 30,000 |
| h | Kent | 80 | 200 | 16,000 |
| i | Kent | 100 | 200 | 20,000 |
| j | Lisa | 90 | 200 | 18,000 |
| k | Lisa | 60 | 200 | 12,000 |
| l | Andy | 140 | 200 | 28,000 |
| m | Lisa | 100 | 200 | 20,000 |
| n | Andy | 80 | 200 | 16,000 |
| o | Project Manager | 40 | 500 | 20,000 |
| p | Andy | 160 | 200 | 32,000 |
| q | Andy | 160 | 200 | 32,000 |
| r | Kent | 120 | 200 | 24,000 |
| s | Kent | 120 | 200 | 24,000 |
| t | Lisa | 100 | 200 | 20,000 |
| u | Lisa | 80 | 200 | 16,000 |
| v | Andy | 100 | 200 | 20,000 |
| w | Project Manager |
Equipment Costs
- Mobile Phones (10 units): 300each→3,000
- Bike Locks (12 units): 50each→600
- Computers (4 units): 1,000each→4,000
- Printers (2 units): 400
Project Manager Cost
Assuming 8 months with 160 working hours each month:
- Total Hours: 160 * 8 = 1,280
- Total Cost: 1,280 * 500=640,000
(Note: Adjust based on actual allocation in tasks)
Resource Sheet
| Resource | Role | Hourly Rate ($) | Total Hours | Total Cost ($) |
|---|
| Bill | Senior Analyst/Designer | 300 | 350 | 105,000 |
| Lisa | Designer/Developer | 200 | 930 | 186,000 |
| Andy | Designer/Developer | 200 | 970 | 194,000 |
| Kent | Designer/Developer | 200 | 700 | 140,000 |
| Project Manager | Manager | 500 | 110 | 55,000 |
| Total Labor Cost | | | | 690,000 |
| Equipment | | | | 10,000 |
| Total Project Cost | | | | 700,000 |
(b) Budget Schedule (Cost Baseline)
| Cost Category | Planned Cost ($) | Contingency Reserve ($) | Total Budget ($) |
|---|
| Labor | 690,000 | 50,000 | 740,000 |
| Equipment | 10,000 | 5,000 | 15,000 |
| Total | 700,000 | 55,000 | 755,000 |
(c) Computing Facility Rental
- Monthly Cost: $29,000
- Duration: 8 months
- Total Rental Cost: 29,000 * 8 = $232,000
(d) Earned Value Management (EVM) at Month 4
Assumptions:
- Planned Value (PV) at Month 4: 50% of Total Budget → $377,500
- Earned Value (EV): 45% of Total Budget → $339,375
- Actual Cost (AC): $390,000
Calculations:
- Schedule Variance (SV) = EV - PV = 339,375 - 377,500 = -38,125
- Cost Variance (CV) = EV - AC = 339,375 - 390,000 = -50,625
- Schedule Performance Index (SPI) = EV / PV = 339,375 / 377,500 ≈ 0.90
- Cost Performance Index (CPI) = EV / AC = 339,375 / 390,000 ≈ 0.87
- Estimate at Completion (EAC) = Total Budget / CPI = 755,000 / 0.87 ≈ $866,667
(e) EVM Graph
graph LR
A[Planned Value (PV) = $377,500] --> B[Earned Value (EV) = $339,375]
A --> C[Actual Cost (AC) = $390,000]
B -.-> D[SV = -$38,125]
B -.-> E[CV = -$50,625]
F[SPI = 0.90]
G[CPI = 0.87]
H[EAC = $866,667]
(f) Project Progress Description
At the end of the fourth month, the project is experiencing delays and cost overruns. The Schedule Variance (SV) of -38,125indicatesthattheproj50,625 signifies that expenditures have exceeded the planned budget. The Schedule Performance Index (SPI) of 0.90 reflects that only 90% of the scheduled work has been completed, and the Cost Performance Index (CPI) of 0.87 shows cost efficiency is below expectations. Consequently, the Estimate at Completion (EAC) projects a total cost of approximately $866,667, exceeding the original budget. Immediate corrective actions are necessary to realign the project with its schedule and budget objectives.
5. Project Resource Management
(To be developed based on detailed resource allocation and management strategies.)
6. Project Risk Management
(To be developed with identified risks, impact analysis, and mitigation plans.)
7. Work Distribution
(To be developed with specific task assignments and responsibilities among team members.)
Note: Sections 5 to 7 are outlined and will be detailed in subsequent sections of the report.