Given the following information for a one-year project, answer the following questions.…

  1. User

    Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV 22,000 EV 20,000 AC 25,000 BAC 120,000 5 5 5 5 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? d. Use the SPI to estimate how long it will take to finish this project. e. Sketch the earned value chart for this project,

  2. Assistant

    a. To calculate the project's performance metrics, we'll use the following formulas:

    1. Cost Variance (CV): [ \text{CV} = \text{EV} - \text{AC} ]
    2. Schedule Variance (SV): [ \text{SV} = \text{EV} - \text{PV} ]
    3. Cost Performance Index (CPI): [ \text{CPI} = \frac{\text{EV}}{\text{AC}} ]
    4. Schedule Performance Index (SPI): [ \text{SPI} = \frac{\text{EV}}{\text{PV}} ]

    Given:

    • PV = $22,000
    • EV = $20,000
    • AC = $25,000

    Calculations:

    1. Cost Variance (CV): [ \text{CV} = $20,000 - $25,000 = -$5,000 ]

    2. Schedule Variance (SV): [ \text{SV} = $20,000 - $22,000 = -$2,000 ]

    3. Cost Performance Index (CPI): [ \text{CPI} = \frac{$20,000}{$25,000} = 0.8 ]

    4. Schedule Performance Index (SPI): [ \text{SPI} = \frac{$20,000}{$22,000} \approx 0.9091 ]

    Answer:

    • Cost Variance (CV): - $5,000
    • Schedule Variance (SV): - $2,000
    • Cost Performance Index (CPI): 0.8
    • Schedule Performance Index (SPI): Approximately 0.91

    b. The project status can be interpreted using the calculated variances and indices:

    • Schedule Variance (SV):
      • Negative SV (-$2,000) indicates the project is behind schedule.
    • Schedule Performance Index (SPI):
      • SPI less than 1 (0.91) confirms the project is behind schedule.
    • Cost Variance (CV):
      • Negative CV (-$5,000) indicates the project is over budget.
    • Cost Performance Index (CPI):
      • CPI less than 1 (0.8) confirms the project is over budget.

    Answer:

    • The project is behind schedule and over budget.

    c. To estimate the total cost at project completion using the CPI:

    Estimate at Completion (EAC): [ \text{EAC} = \frac{\text{BAC}}{\text{CPI}} ]

    Given:

    • BAC = $120,000
    • CPI = 0.8

    Calculations: [ \text{EAC} = \frac{$120,000}{0.8} = $150,000 ]

    Since the EAC ($150,000) is higher than the original BAC ($120,000), the project is expected to cost more than planned.

    Answer:

    • Estimate at Completion (EAC): $150,000
    • The project is performing worse than planned, as it's projected to exceed the budget.

    d. To estimate the total project duration using the SPI:

    Estimated Project Duration: [ \text{Estimated Duration} = \frac{\text{Planned Duration}}{\text{SPI}} ]

    Given:

    • Planned Duration = 1 year
    • SPI = 0.91

    Calculations: [ \text{Estimated Duration} = \frac{1 \text{ year}}{0.91} \approx 1.10 \text{ years} ]

    So, the project is estimated to take approximately 1.10 years (or about 13.2 months) to complete.

    Answer:

    • The estimated time to finish the project is approximately 1.10 years.

    e. Earned Value Chart Sketch:

    [Visual representation cannot be provided in text form, but here's how to sketch the chart.]

    To create the earned value chart:

    1. Plot the Time Axis (X-Axis):

      • Mark the timeline of the project (e.g., months).
    2. Plot the Cost Axis (Y-Axis):

      • Mark the cost values (in dollars).
    3. Draw the Planned Value (PV) Curve:

      • Plot the cumulative planned expenditures over time.
      • At the current time, PV is $22,000.
    4. Draw the Actual Cost (AC) Curve:

      • Plot the cumulative actual costs incurred over time.
      • At the current time, AC is $25,000.
    5. Draw the Earned Value (EV) Curve:

      • Plot the cumulative value of work actually completed over time.
      • At the current time, EV is $20,000.
    6. Interpretation:

      • AC Curve above EV Curve: Project is over budget.
      • EV Curve below PV Curve: Project is behind schedule.

    Answer:

    • Sketch an earned value chart plotting PV at $22,000, EV at $20,000, and AC at $25,000 at the current time point. The AC curve will be above the EV curve, which is below the PV curve.