To successfully complete your task and sub-task 2, you will need to plan meticulously and ensure that you understand the components of the project work breakdown structure (WBS). Let's break this down into manageable sections and provide a detailed explanation.
Introduction
A Work Breakdown Structure (WBS) is a hierarchical decomposition of a project into smaller components. It provides a structured way to organize and define the total scope of the project. The main objective of developing a WBS is to ensure that all necessary tasks are identified, assigned, and managed efficiently.
Outline View
In the outline view of the WBS, we will break down the stages as described in the SDLC: Planning and Research, Design, Development, Testing, and Implementation. Each stage will further break down into tasks and subtasks.
Hierarchical Structure
The hierarchical structure divides the project into manageable levels. The project is on the top level, followed by major phases (SDLC stages). Each phase contains detailed tasks and responsibilities.
Tabular View
The tabular view will include detailed descriptions of each task, responsible persons, estimated durations, and costs involved.
Detailed Work Breakdown Structure with Responsibilities, Duration, and Costs
Level 1: Project Development
-
Project Preparation
- Assemble Team
- Responsible: Project Manager
- Duration: 2 days
- Cost: R2000
-
SDLC Phases
Level 2: Planning and Research (6 days) - Total Cost: R12000
- Requirement Gathering
- Responsible: System Analyst
- Duration: 4 days
- Cost: R8000
- Feasibility Study
- Responsible: Project Manager
- Duration: 2 days
- Cost: R4000
Level 3: Design (8 days) - Total Cost: R16000
- System Architecture
- Responsible: System Analyst
- Duration: 4 days
- Cost: R8000
- Interface Design
- Responsible: Designer
- Duration: 4 days
- Cost: R8000
Level 4: Development (20 days) - Total Cost: R40000
- Frontend Development
- Responsible: Programmer 1
- Duration: 10 days
- Cost: R10000
- Backend Development
- Responsible: Programmer 2
- Duration: 10 days
- Cost: R10000
- Database Development
- Responsible: Programmer 3
- Duration: 10 days
- Cost: R10000
- Integration
- Responsible: All Programmers
- Duration: 10 days (parallel work)
- Cost: R10000
Level 5: Testing (4 days) - Total Cost: R8000
- Unit Testing
- Responsible: Programmer 1 & 2
- Duration: 2 days
- Cost: R4000
- System Testing
- Responsible: Programmer 3 & Designer
- Duration: 2 days
- Cost: R4000
Level 6: Implementation (2 days) - Total Cost: R4000
- Deployment
- Responsible: System Analyst & All Programmers
- Duration: 1 day
- Cost: R2000
- User Training
- Responsible: Project Manager & Designer
- Duration: 1 day
- Cost: R2000
Modified WBS View with 3rd Level Tasks
Level 2: Planning and Research
| Sub-task | Responsible Person | Estimated Duration | Costs (R) |
|---|
| Requirement Gathering | System Analyst | 4 days | 8000 |
| Feasibility Study | Project Manager | 2 days | 4000 |
Level 3: Design
| Sub-task | Responsible Person | Estimated Duration | Costs (R) |
|---|
| System Architecture | System Analyst | 4 days | 8000 |
| Interface Design | Designer | 4 days | 8000 |
Level 4: Development
| Sub-task | Responsible Person | Estimated Duration | Costs (R) |
|---|
| Frontend Development | Programmer 1 | 10 days | 10000 |
| Backend Development | Programmer 2 | 10 days | 10000 |
| Database Development | Programmer 3 | 10 days | 10000 |
| Integration | All Programmers | 10 days (parallel work) | 10000 |
Level 5: Testing
| Sub-task | Responsible Person | Estimated Duration | Costs (R) |
|---|
| Unit Testing | Programmer 1 & 2 | 2 days | 4000 |
| System Testing | Programmer 3 & Designer | 2 days | 4000 |
Level 6: Implementation
| Sub-task | Responsible Person | Estimated Duration | Costs (R) |
|---|
| Deployment | System Analyst & All Programmers | 1 day | 2000 |
| User Training | Project Manager & Designer | 1 day | 2000 |
Summary
The total estimated duration of the project is 40 days with a total cost of R80000. This structured approach ensures that everyone in the team understands their responsibilities, the time frame, and the associated costs. The project must be completed within these constraints to adhere to the provided budget and deadlines.
This detailed WBS should serve as a strong foundation for your project planning and management. Make sure to adapt this structure to fit the specific needs and any changes that may arise during the project lifecycle.