i have a task and here is the description of the task: you are required to develop a communication application that camn only be used by students at your college. The college have budgeted R80000 towards the project .To undertake the projecct, you must assemble your own team that include a project manager ,system analyst,designer and three programmers .Your SDLC stages are planning and research,designer,development,testing and implementation. It is estimated that ,the project will take 40 days to complete. Sub-task 2 create and modify work breakdown structure based on a wbs.add descriptions and content that are relevant to the sections in the sections in the document pertaining to the : introduction.outline view and hierarchal structure.Tabular view.Modify this view to include the following based on the 3rd level tasks. (You should adapt the tasks to correspond to the given stages as part of the description.) Responsible person allocated to the sub-task.For this you need to consider that the development would be done by a team with different team members and each will have different responsibilities. Estimated duration of the task. Costs involved per task
- Assistant
Certainly! Below is a sample Work Breakdown Structure (WBS) for a communication application to be used by students at your college. For ease of understanding, I will break down the tasks according to the SDLC stages mentioned: Planning and Research, Design, Development, Testing, and Implementation. Each task will also indicate the responsible person, estimated duration, and costs involved.
Introduction
The project involves the development of a communication application exclusively for students at the college. The college has allocated a budget of R80000 and the project is expected to be completed in 40 days. The project team consists of a Project Manager, a System Analyst, a Designer, and three Programmers. The project will follow the Software Development Life Cycle (SDLC) stages: Planning and Research, Design, Development, Testing, and Implementation.
Outline View and Hierarchal Structure
-
Planning and Research (10 days)
- Identify requirements (3 days)
- Conduct market research (4 days)
- Feasibility study (3 days)
-
Design (10 days)
- System architecture design (5 days)
- User Interface (UI) design (5 days)
-
Development (10 days)
- Backend development (5 days)
- Frontend development (5 days)
-
Testing (7 days)
- Unit testing (3 days)
- System testing (2 days)
- User Acceptance Testing (UAT) (2 days)
-
Implementation (3 days)
- Deployment (2 days)
- User training (1 day)
Tabular View
| |--- |Sub-task|Responsible Person|Estimated Duration (Days)|Cost (R) | | |### Planning and Research | | |Identify requirements|Project Manager|3|6000 | | |Conduct market research|System Analyst|4|8000 | | |Feasibility study|System Analyst|3|6000 | | |### Design | | |System architecture design|Designer/System Analyst|5|10000 | | |User Interface (UI) design|Designer|5|10000 | | |### Development | | |Backend development|Programmer 1|5|10000 | | |Frontend development|Programmer 2|5|10000 | | |### Testing | | |Unit testing|Programmer 3|3|6000 | | |System testing|Programmer 1 and Programmer 2|2|4000 | | |User Acceptance Testing (UAT)|Project Manager|2|4000 | | |### Implementation | | |Deployment|Programmer 1 and Programmer 3|2|4000 | | |User training|Project Manager|1|2000 | |
Summary of Cost Allocation
- Planning and Research: R20000
- Design: R20000
- Development: R20000
- Testing: R14000
- Implementation: R6000
Total Cost: R80000
Hierarchal Structure
. └── Project: Student Communication Application ├── Planning and Research (10 days) │ ├── Identify requirements (3 days) │ ├── Conduct market research (4 days) │ └── Feasibility study (3 days) ├── Design (10 days) │ ├── System architecture design (5 days) │ └── User Interface (UI) design (5 days) ├── Development (10 days) │ ├── Backend development (5 days) │ └── Frontend development (5 days) ├── Testing (7 days) │ ├── Unit testing (3 days) │ ├── System testing (2 days) │ └── User Acceptance Testing (UAT) (2 days) └── Implementation (3 days) ├── Deployment (2 days) └── User training (1 day)Comments
-
Planning and Research:
- Identify requirements: Responsible for gathering all the user and system requirements.
- Conduct market research: Analyze potential competitors and gather data on user needs.
- Feasibility study: Assess the financial, technical, and operational feasibility.
-
Design:
- System architecture design: Develop the overall architecture of the application.
- UI design: Create the user interface design according to user requirements.
-
Development:
- Backend development: Develop server-side components.
- Frontend development: Develop client-side components.
-
Testing:
- Unit testing: Ensure individual components work as intended.
- System testing: Ensure all components work together.
- User Acceptance Testing (UAT): Ensure the application meets user requirements.
-
Implementation:
- Deployment: Deploy the application to a live environment.
- User training: Train users on how to use the application.
This structure ensures that each phase of your project is clearly defined and each team member is aware of their responsibilities, durations, and cost constraints.
-