4.2.4 User Experience
In addition to the functional and software aspects, the user experience (UX) is of great importance for the quality of the end product (Ridder, n.d.). A positive user experience results in user satisfaction and therefore encourages more frequent use of the app. Additionally, an intuitive user interface and smooth workflows enable users to complete their tasks faster and work more efficiently. The ultimate goal of the application is to accelerate and improve the inventory management process through automation, so efficiency plays an important role.
To ensure that the quality of the user experience is guaranteed, there are a few essential steps that must be taken. It starts with analyzing the user needs and the flow of the application. After this analysis phase, it is important to create a user-friendly design that meets the needs of the users and at the same time the application flow.
In addition, there is a planned UX workshop/course on the program, organized by the company where the internship is taking place. While there is already existing knowledge and skills in the field of user experience, this workshop provides the opportunity to not only gain new insights, but also to connect with various UX experts. This network can be valuable for obtaining additional help and feedback to ensure the product meets the quality standards set by the experts.
During the development of the product, we work in an environment with other developers, often in a group consisting of fellow interns. These colleagues play an active role in extensively testing the product on various devices and platforms. Their feedback is the first “human check” that goes through a functionality, for example. In addition, several feedback sessions will also be planned in collaboration with various stakeholders. Stakeholders are given the opportunity to fully test the application, which provides valuable insights for optimizing the user experience.
It is also a personal goal to add the Wow Factor to the design of the application. While the main goal remains a simplistic yet efficient design, it is not unimportant to give the product a unique and memorable look.
The goal is to create an iterative process where there is continuous development, testing and improvement. With the aim of continuing to work consistently and achieving the desired results.
4.3 Risk analysis
4.3.1 Intro
To determine the risk factors of this project and to establish the relevant measures, a qualitative risk analysis is carried out. This analysis is limited to meeting deadlines, improving the process and limiting expenses during the development process of the AIventory product. In this analysis, the likelihood of risks is estimated and the extent of the consequences is examined. Finally, measures and actions are determined so that a conclusion and recommendations can be drawn.
4.3.2 Risk policy
The main goal of the project, the development of the AIventory product, is to automate the inventory management process with optimal results. Employee satisfaction is central and it goes without saying that the set deadline must be met. It is important to ensure the highest quality within the set timelines without compromising the efficiency of the automation, otherwise the project will miss its target.
risk attitude of the company (and perhaps risk goals)
company takes aggressive attitude towards risks. Takes risks on purpose, for example to make as much profit as possible.
risk strategy, questions for Daan. What does the company do to manage the risks;
- how are unacceptable risks reduced or avoided in the current situation?
- How are responsibilities for managing risks divided?
- Who has ultimate responsibility for the risk management process?
4.3.3 Internal and external risk factors
Various risk factors have been drawn up, both internal and external risks. These are divided into different categories: Project staff & leaders, Planning, Processes & Systems, Finance & resources, Location, Competition and Final project. The list of these risk factors can be found in Appendix 4A.
4.3.4 Measures
Now that it is clear which risks have priority based on the consequences and likelihood of the risk, the measures can be determined. These measures can be divided into 6 categories: Prevention, Detect, Reduce, Correct, Accept, or Transfer. Depending on the category, the consequence or probability of the risk will decrease. This can be read from the table in Appendix 4B.
4.3.5 Conclusion
As you can deduce from the aforementioned appendices, there are a number of high-priority risks. From this we can conclude that, if we look at the two risks with the highest priority, communication between client and development team is extremely important. The risks both concern the area of communication between the two parties. These risk factors indicate that if this communication is not adequately maintained, the end result will suffer with major consequences. Therefore, as a preventive measure, a measure is taken to schedule feedback sessions in advance and it is advised to maintain close contact between the client and the development team.
We can also see from Appendix 4A that the chance and consequences of the risk of an important individual failing (temporarily) is high. It is therefore proposed to keep a replacement internship supervisor in mind, if necessary. It is also recommended to keep several people with expertise informed about the status of the project.
Finally, we can say that a lot of attention must be paid to the user experience of the product. The estimate shows that there is a high chance, with significant consequences, that the product will ultimately prove to be functional, but that the user experience will fall short of expectations.
The recommendation is to follow the advice just mentioned in order to minimize the risks and increase the chance of success.
4.4 Methodology
4.4.1 Intro
Methodical action provides useful guidelines and a solid basis that can be used when confronted with complex issues. How do you respond to situations for which you simply do not have the knowledge? How do you obtain the requirements? How do you act when you have a knowledge question? How are the project phases maintained? This subchapter describes the action plan for the situations just discussed. The realizations of these plans will be elaborated in a later chapter and linked back to this chapter.
4.4.2 Requirements
About 50% of all IT projects fail (Soest, 2021). That's quite an extreme ratio. While the cause is often quite easy to recognize; requirements of a project or system that do not actually solve the problem. These requirements are the basis of your system and without a solid foundation, you will not achieve the desired end result. In short, properly recording these points is extremely important and that is why a lot of attention is paid to this part of the development in this project.
It is important to have a clear idea of where the requirements are derived from. The stakeholders are central to this process. The problem analysis determined which stakeholders there are and how much influence and importance they have. Furthermore, it is important to draw up a communication plan that accurately indicates when communication will take place with the various stakeholders, including how often and the method of communication. This document can be found in Chapter 4.X.X.X.
When these matters are clear, the requirements and wishes can be recorded according to the methods tailored to the relevant stakeholders as described in the aforementioned communication plan. These requirements and wishes are then formulated in the form of a user story. These stories must be autonomous: complete, independent and clear at a glance, explains (Soest, 2021). The user stories must also include acceptance criteria. Ultimately, the intention is for stakeholders to review and approve these user stories before they are considered documented requirements and wishes.
It is important to note that the user stories drawn up do not contain all requirements. They mainly include the Functional Requirements. In addition to these functional aspects, there are also the Non-Functional Requirements, such as the speed of the system response, the security levels or the user-friendliness (ScaledAgileFramework, 2023). In addition, this also includes Design Constraints, such as the choice of programming languages, technologies or hardware components. Both the Functional and Non-Functional requirements together form the scope of the project. However, certain items may not be explicitly stated, making it unclear whether they fall within the scope of the project. These items should be discussed and documented separately to provide complete clarity to both stakeholders and developers about what is and is not within the scope of the project.
4.4.3 Research plan
Various knowledge questions constantly arise during the development of the product. Many technologies or methods are often unknown to the developer and therefore require further research in advance. Moreover, the project starts with the research phase, but how exactly is research conducted and are the results useful and valid? In short, how is data collected and how do we analyze this data to ensure its usability and reliability.
Literature searches and prototyping comprised the majority of the research methods in the research phase, but a Multi-Criteria Analysis (hereinafter referred to as MCA) was also discussed. At the beginning of the research phase, the problem and goal are broadly determined. The next step was to investigate the best-suited technologies and resources for this problem. It always starts with a literature search; looking up possible solutions to the problem or analyzing existing projects with similar topics. It is always best practice to divide a large complex problem into smaller sub-problems. This way it is easier to find a suitable solution for the main problem.