Later When 10 men work together, they can finish a task in four days. Alternatively, 12…
- User
Later
When 10 men work together, they can finish a task in four days. Alternatively, 12 women can complete the same work in 10 days, while 20 children can finish it in 15 days. How many days will 4 men, 8 women, and 10 children take to complete the task if they all work together?
Select an option
75 days
4 days
5 days
8 days
- Assistant
First, let's find the rate at which men, women, and children work.
We are told that 10 men can finish the task in 4 days. So, the work rate for men is: Work (for men) = 1 task/4 days.
Thus, one man's work rate is: 1 man = (1 task/4 days) / 10 men = 1 task / (4 * 10) days = 1/40 tasks per day.
Next, we are told 12 women can finish the task in 10 days. So, the work rate for women is: Work (for women) = 1 task/10 days.
Thus, one woman's work rate is: 1 woman = (1 task/10 days) / 12 women = 1/120 tasks per day.
We also know that 20 children can finish the task in 15 days. So, the work rate for children is: Work (for children) = 1 task/15 days.
Thus, one child's work rate is: 1 child = (1 task/15 days) / 20 children = 1/300 tasks per day.
Now we need to find out the combined work rate for 4 men, 8 women, and 10 children working together.
For 4 men: 4 men = 4 * (1/40) = 1/10 tasks per day.