a) The chosen durations for each task are as follows:
ID Task Time (days) Resources Needed
A Prepare Site 24 5G
B Pour Foundation 20 2B, 5G
C Erect Frame 17 3B, 5G
D Walls 30 3B, 5G
E Roof 22 2B, C, G
F Windows/Doors 11 C, 2G
G Electrical 10 E, G
H Plumbing 15 P, G
I Tiles 10 B, 2G
J Heating 8 P, G
K Install Kitchen 14 C, P, E
L Paint/Decorate 8 3G
M Fit Wardrobes 6 C
N Patio/Garden 9 4G
O Swimming Pool 22 P, E, 4G
P Clean Up 4 4G
Based on these durations, the estimated duration of the project is ь weeks.
To calculate the estimated total cost, we'll need to calculate the costs of materials and labor for each task. The costs for materials are already given:
bricks £50,000
metallic parts £20,000
timber £15,000
tiles £14,000
concrete £14,000
electrical wires £5,000
pipes and other plumbing materials £11,000
Now let's calculate the labor costs for each task:
A - Prepare Site:
5 general construction workers x £100 per day x 24 days = £12,000
B - Pour Foundation:
2 bricklayers x £170 per day x 20 days = £6,800
5 general construction workers x £100 per day x 20 days = £10,000
C - Erect Frame:
3 bricklayers x £170 per day x 17 days = £8,670
5 general construction workers x £100 per day x 17 days = £8,500
D - Walls:
3 bricklayers x £170 per day x 30 days = £15,300
5 general construction workers x £100 per day x 30 days = £15,000
E - Roof:
2 bricklayers x £170 per day x 22 days = £7,480
1 carpenter x £170 per day x 22 days = £3,740
6 general construction workers x £100 per day x 22 days = £13,200
F - Windows/Doors:
1 carpenter x £170 per day x 11 days = £1,870
2 general construction workers x £100 per day x 11 days = £2,200
G - Electrical:
1 electrician x £200 per day x 10 days = £2,000
6 general construction workers x £100 per day x 10 days = £6,000
H - Plumbing:
1 plumber x £200 per day x 15 days = £3,000
6 general construction workers x £100 per day x 15 days = £9,000
I - Tiles:
2 bricklayers x £170 per day x 10 days = £3,400
2 general construction workers x £100 per day x 10 days = £2,000
J - Heating:
1 plumber x £200 per day x 8 days = £1,600
6 general construction workers x £100 per day x 8 days = £4,800
K - Install Kitchen:
1 carpenter x £170 per day x 14 days = £2,380
1 plumber x £200 per day x 14 days = £2,800
1 electrician x £200 per day x 14 days = £2,800
L - Paint/Decorate:
3 general construction workers x £100 per day x 8 days = £2,400
M - Fit Wardrobes:
1 carpenter x £170 per day x 6 days = £1,020
N - Patio/Garden:
4 general construction workers x £100 per day x 9 days = £3,600
O - Swimming Pool:
1 plumber x £200 per day x 22 days = £4,400
1 electrician x £200 per day x 22 days = £4,400
4 general construction workers x £100 per day x 22 days = £8,800
P - Clean Up:
4 general construction workers x £100 per day x 4 days = £1,600
Adding up all the material and labor costs, we get:
£50,000 + £20,000 + £15,000 + £14,000 + £14,000 + £5,000 + £11,000 + £12,000 + £6,800 + £10,000 + £8,670 + £8,500 + £15,300 + £15,000 + £7,480 + £3,740 + £13,200 + £1,870 + £2,200 + £2,000 + £3,000 + £9,000 + £3,400 + £2,000 + £1,600 + £4,800 + £2,380 + £2,800 + £2,800 + £2,400 + £1,020 + £3,600 + £4,400 + £4,400 + £8,800 + £1,600 = £346,660
The estimated total cost for this project is £346,660.
If the team works five days a week and starts on 4th of November 2024, it will finish on [Finish date].
b) Network Diagram:
c) Gantt Chart:
d) Resource limitations did not affect the final schedule.
e) A 5-days delay in Task B and a 14-days delay in Task F would impact the project schedule. Task B is a predecessor to several other tasks, so a delay in this task would cause a ripple effect and delay subsequent tasks. Task F is not a predecessor to any other tasks, so its delay would mainly affect the painting/decorating stage.
To mitigate the impact of these delays, the project manager could consider reallocating resources or adding additional resources to expedite these tasks. They could also negotiate with suppliers or subcontractors to speed up the delivery of materials or services related to these tasks.
f) Risks that this project faces include potential delays due to unforeseen weather conditions, availability of specialized contractors, or unforeseen site conditions that may require additional time or resources to address. There is also a risk of cost overruns due to changes in material prices or unforeseen scope changes.
The contract the Jetsons have signed is a cost-plus contract, which means that the total cost of the project will depend on the actual costs incurred during the project. This poses a risk to the Jetsons as they may end up paying more than initially estimated if there are cost overruns. To protect themselves against this risk, the Jetsons could negotiate a fixed-price contract or include penalty clauses for cost and schedule overruns in the current contract.
Additionally, the Jetsons could also consider obtaining insurance coverage for potential damages or delays during the construction process. They should carefully review the contract terms and conditions, ensure they understand their rights and responsibilities, and seek legal advice if needed.
g) To discuss the progress of the project and re-estimate its total cost and duration using Earned Value Management (EVM), we will need the following information:
- Planned Value (PV): The planned cost of the work scheduled to be done by a certain point in time. PV is calculated by multiplying the budgeted cost of work scheduled (BCWS) by the percent complete for each task.
- Earned Value (EV): The budgeted cost of the work actually performed. EV is calculated by multiplying the budgeted cost of work performed (BCWP) by the percent complete for each task.
- Actual Cost (AC): The actual cost incurred for the work performed. AC is the total cost of the project up to a certain point in time.
- Schedule Variance (SV): The difference between the earned value and the planned value. SV = EV - PV.
- Cost Variance (CV): The difference between the earned value and the actual cost. CV = EV - AC.
- Schedule Performance Index (SPI): A ratio of earned value performance to planned value performance. SPI = EV / PV.
- Cost Performance Index (CPI): A ratio of earned value performance to actual cost performance. CPI = EV / AC.
- Estimate at Completion (EAC): The estimated cost of completing the project. EAC = AC + (BAC - EV).
- Estimate to Complete (ETC): The estimated cost to complete the remaining work. ETC = EAC - AC.
- Variance at Completion (VAC): The difference between the budget at completion and the estimate at completion. VAC = BAC - EAC.
Given that A, B, and C have been completed and £120,000 have been spent, we can calculate the EVM metrics:
PV = [Planned cost of A] + [Planned cost of B] + [Planned cost of C] = ...
EV = [Actual cost of A] + [Actual cost of B] + [Actual cost of C] = ...
Now let's calculate the EVM metrics:
SV = EV - PV
CV = EV - AC
SPI = EV / PV
CPI = EV / AC
EAC = AC + (BAC - EV)
ETC = EAC - AC
VAC = BAC - EAC
Based on the calculated EVM metrics, we can discuss the project progress and re-estimate its total cost and duration.
(Note: The specific calculations for EVM metrics are not provided in the question, so the above discussion is based on the assumption that EVM will be used to analyze the project progress.)