rewrite audit report The infrastructure planning was based on 2 working shifts with 9…
- User
rewrite audit report The infrastructure planning was based on 2 working shifts with 9 hour/shift and 5 working days. Seen: Process map PM-PRODENG-01 revision 9/7/2023 Input Sales plan for Annual capacity review/planning dentified PA # 1 – in 7.1.3.1 – The process of implementing the use of multidisciplinary approach including risk identification and risk mitigation methods for developing and improving plant, facility is robust: KPIs are being documented, closely monitored , and improved; milestone chart includes quite a few projects:
Reviewed current projects: HVAC Process plan for new customer BMW SUV X5, X6,X7 and X8 planned to SOPJul 2026. Automation strategy, High variation of product in the production line. Increasing 61/shift with 2 shift running. Production transfer to Denso associate plant e.g. Evaporator line transfer to Denso Mexico Finished in August 2023, for IF38 product transfer to DNMX to eliminates long term capacity risk at DMMI. Utility changed for electricity increasing,
- Assistant
The audit report indicates that the infrastructure planning was based on two working shifts, with each shift lasting nine hours and covering five working days. This information was obtained from the process map PM-PRODENG-01 revision dated September 7, 2023.
The input for the annual capacity review and planning was the sales plan.
In the audit, it was identified that PA #1, as stated in section 7.1.3.1, focuses on the process of implementing a multidisciplinary approach, which includes risk identification and risk mitigation methods, for the development and improvement of the plant and facility. The report states that this process is robust, with KPIs being documented, closely monitored, and improved. Furthermore, the milestone chart reveals several ongoing projects.
The current projects that were reviewed are as follows:
- HVAC Process plan for the new customer, BMW SUV X5, X6, X7, and X8, with a planned start of production in July 2026.
- User
rewrite audit report Document control was generated base on each department, Distribution
ALLPROD-WORKREQUEST-W1 8/2/2023
Record retention e.g. Honda 20 years starting from 2013, Ford record 3 years from date of training, 2 years for inspection data.
Electronic media is recommended.
DOCCONFLOW-W1
The exclusive temporary ECI was written on 11/17/2022 was issued on 12/5/2022, it end on 3/3/2023 and drawing and part revert to previous version.
- Assistant
The audit report states that document control is generated based on each department. The distribution of documents is managed through the ALLPROD-WORKREQUEST-W1 process, which was last revised on August 2, 2023.
Record retention policies are in place for different departments. For example, Honda has a record retention period of 20 years starting from 2013, while Ford retains records for 3 years from the date of training and 2 years for inspection data.
The use of electronic media for document storage and management is recommended.
The document control flow is managed through the DOCCONFLOW-W1 process.
An exclusive temporary Engineering Change Instruction (ECI) was written on November 17, 2022, and issued on December 5, 2022. The temporary ECI is effective until March 3, 2023. During this period, the drawing and part revert to the previous version.
This audit report provides information on the document control processes, record retention policies, recommended electronic media usage, and the management of temporary ECIs.
- User
rewrite audit report Risk analysis: 23MY GM31XX HVAC Milestone#5 Multiple program grease requirement, Action plan Commonize grease between E2 and 31XX program.
PFMEA severity and detection matrix is using for risk prioritization. Mixing risk for assembly process, transfer risk from M5 to M7 level from 56% to 90% process reliability.
CRV program, H-1093 involved with ergonomic of working method, risk level 23 = medium risk. From new improvement machine can reduce RPN from 80 to 40.
M7 milestone meeting on January 7, 2022. -Design changed to communized grease type was accepted. -Revised EOL jig because of GM product’s size. -M5 Molding sub-assembly area Improved process reliability from 30% to 100% at M7 Level.
Vision system was key improvement Poka-yoke system using for eliminate the process risk.
Genba review approved on Jun-21 by Kevin Carson.
M8 found some camera issue to follow up with GRR and light requirement at the inspection area.
FMEA number 15054 revision 9/15/2023, Mass production phase. GM31XX model P/N AA443390-2792-HV2, HVAC2.
SOP February 2023, customer approved in July 1, 2023. DUNS 147754931 for P/N 85625787 Module Asm-Htr & A/C Ever & Blo
DIAM support in Drawing, Engineering change, PFMEA TAC-ESC-007 for project 23MY GM 31XX HVAC / Rank “A” on Dec 17, 2021.
- Assistant
The audit report focuses on risk analysis for the 23MY GM31XX HVAC Milestone#5. One of the identified risks is the requirement for multiple program greases. The recommended action is to commonize the grease between the E2 and 31XX programs. The severity and detection matrix of the PFMEA is used to prioritize risks. Through process changes, the risk of mixing during the assembly process has been transferred from Milestone 5 (M5) to Milestone 7 (M7), increasing process reliability from 56% to 90%.
- User
rewrite audit report Ford Customer claim sampling e.g. on 9/19/2023 for W2005702 claim, Ford accepted for disputed. Toyota Opened 4 issues Closed 13 issues (2 Cancelled) Sampling 6/14/2023 number 02-19500-925W-4097, Inlet wrong size Excess material 4088 5/23/2023 Root cause was process design, Control plan and PFMEA was revised. SIA 14 claims 6 by suppliers and 8 by Denso. Last 1 opened in Sep 13, 2023. In-completed assembly, PCAR-2023-2219 SIA AM Gear meshing, Adding Poke-yoke system to the line since September 21, 2023. Stellantis Complaint number 2023-2141 on 5/19/2023 Complaint number 2023-2179 on 6/5/2023
DIAM support for Warranty claim
- Assistant
The audit report provides an overview of customer claims and warranty issues for different automotive companies.
Ford: On September 19, 2023, a customer claim was sampled for claim W2005702. Ford accepted the claim, resolving the dispute.
Toyota: Four issues were opened and 13 issues were closed, with two of them being cancelled. One sampling on June 14, 2023, with the number 02-19500-925W-4097, revealed a wrong size inlet. The excess material issue number 4088 on May 23, 2023, was identified as a process design problem, leading to revisions in the Control Plan and PFMEA.
SIA (Subaru of Indiana Automotive): Fourteen claims were received, with six claims attributed to suppliers and eight claims attributed to Denso. The most recent claim was opened on September 13, 2023. The issue pertained to incomplete assembly, with claim number PCAR-2023-2219 related to SIA AM Gear meshing. Since September 21, 2023, a Poka-yoke system has been added to the assembly line to address this issue.
Stellantis: Two complaints were logged for Stellantis. Complaint number 2023-2141 was received on May 19, 2023, and complaint number 2023-2179 was received on June 5, 2023.