A - The standard direct material amount per urn can be calculated by dividing the total standard cost of direct materials by the number of urns produced:
Standard direct material amount per urn = Total standard cost of direct materials / Number of urns produced
= 6000/1000=6.00 per urn
B - The direct material price variance can be calculated using the following formula:
Direct material price variance = (Actual cost per kg - Standard cost per kg) * Actual quantity of materials purchased
Given:
Actual cost per kg = 5600/ActualquantityofmaterialspurchasedStandardcostperkg=6.00 per kg
Actual quantity of materials purchased = ?
Direct material price variance = $120 unfavourable
Solving for Actual quantity of materials purchased:
120=(24.50 - 6.00)∗Actualquantityof120 = 120 / $18.50
≈ 6.486 kg
Therefore, the direct material price variance is $6.486 kg.
C - The actual hours worked can be calculated by rearranging the formula for the labour efficiency variance:
Labour efficiency variance = (Actual hours worked - Standard hours allowed) * Standard rate per hour
Given:
Labour efficiency variance = 6.00) / 2
= 3000 hours
Standard rate per hour = $24.00 per hour
Actual hours worked = ?
336=(Actualhoursworked−3000)∗24.00
336=24.00 * Actual hours worked - 336 + 24.00 * Actual hours worked
Actual hours worked = (24.00 * 3000) / $24.00
≈ 333.333 hours
Therefore, the actual hours worked is approximately 333.333 hours.
D - The total actual cost of direct manufacturing labour can be calculated by multiplying the actual hours worked by the actual cost per hour:
Total actual cost of direct manufacturing labour = Actual hours worked * Actual cost per hour
= 333.333 hours * 24.50perhour≈8166.665
Therefore, the total actual cost of direct manufacturing labour is approximately $8166.665.
E - The labour price variance for direct manufacturing labour can be calculated using the following formula:
Labour price variance = (Actual cost per hour - Standard cost per hour) * Actual hours worked
Given:
Actual cost per hour = 24.50perhourStandardcostperhour=24.00 per hour
Actual hours worked = 333.333 hours
Labour price variance = ?
Labour price variance = (24.50−24.00) * 333.333 hours
= 0.50∗333.333hours≈166.665
Therefore, the labour price variance for direct manufacturing labour is approximately $166.665.