Blue mountains Pottery produced 1000 urns during August. Its costing systems showed the…
- User
Blue mountains Pottery produced 1000 urns during August. Its costing systems showed the following: Direct Materials (all materials purchased were used): Standard cost: 5600 Standard cost allowed for units produced was 120 unfavourable Direct Manufacturing labour: Standard cost is 2 urns per hour at 24.50 Labour efficiency variance was $336 favourable Required: A - What is standard direct material amount per ur? B - What is the direct material price variance? C-what is the total numbers of hour worked? D - What is the total actual cost of direct manufacturing labour? E- What is the labour price variance for direct manufacturing labour?
- Assistant
A - The standard direct material amount per urn can be calculated by dividing the standard cost by the number of units produced. Standard direct material amount per urn = Standard cost / Number of units produced Standard direct material amount per urn = 6.00