Hanson Inc. has the following direct materials standard to manufacture one Zippy: 1.5…
- User
Hanson Inc. has the following direct materials standard to manufacture one Zippy: 1.5 pounds per Zippy at 6,630. How many pounds of materials should Hanson have used to make 1,000 Zippies? a. 1,700 pounds. b. 1,500 pounds. c. 1,200 pounds. d. 1,000 pounds.
- Assistant
To find out how many pounds of materials Hanson should have used to make 1,000 Zippies, we need to multiply the standard amount of materials per Zippy (1.5 pounds) by the number of Zippies produced (1,000):
1.5 pounds * 1,000 Zippies = 1,500 pounds.
Therefore, the correct answer is b. 1,500 pounds.
- User
Hanson Inc. has the following direct materials standard to manufacture one Zippy: 1.5 pounds per Zippy at 6,630 Hanson’s materials quantity variance (MQV) for the week was: a. 170 favorable. c. 800 favorable.
- Assistant
The materials quantity variance (MQV) can be calculated by subtracting the actual quantity used from the standard quantity and multiplying by the standard price:
MQV = (Standard quantity - Actual quantity) * Standard price
Standard quantity = 1.5 pounds per Zippy * 1,000 Zippies = 1,500 pounds
Actual quantity = 1,700 pounds
Standard price = $4.00 per pound
MQV = (1,500 pounds - 1,700 pounds) * 4.00 per pound = -$800
- User
Hanson Inc. has the following direct materials standard to manufacture one Zippy: 1.5 pounds per Zippy at 6,630 Hanson’s materials price variance (MPV) for the week was: a. 170 favorable. c. 800 favorable
- Assistant
The materials price variance (MPV) can be calculated by subtracting the actual cost from the standard cost and multiplying by the actual quantity used:
MPV = (Standard price - Actual price) * Actual quantity
Standard price = $4.00 per pound
Actual price = total cost / actual quantity = 3.90 per pound
Actual quantity = 1,700 pounds
MPV = (3.90 per pound) * 1,700 pounds = 170
- User
Hanson Inc. has the following direct labor standard to manufacture one Zippy: 1.5 standard hours per Zippy at 18,910 to make 1,000 Zippies. Hanson’s labor rate variance (LRV) for the week was: a. 310 favorable. c. 300 favorable.
- Assistant
The labor rate variance (LRV) can be calculated by subtracting the standard rate from the actual rate and multiplying it by the actual hours worked:
LRV = (Actual rate - Standard rate) * Actual hours worked
Standard rate = $12.00 per hour
Actual rate = total labor cost / actual hours worked = 12.20 per hour
Actual hours worked = 1,550 hours
LRV = (12.00 per hour) * 1,550 hours = 310