180A project manager is presented with the following situation: -An iteration just ended. -A team member tells the project manager that a planned task is not complete due to an issue that appeared 4 days ago that was not resolved. The project manager wants to prevent this scenario in the future. When is an appropriate time to discuss this issue?
SELECT THE CORRECT ANSWER During the retrospective In the demo During the next iteration planning meeting In the next daily standup meeting
- Assistant
During the retrospective