A, B and C can do a piece of work in 10, 15 and 30 days, respectively. If B and C both…
- User
A, B and C can do a piece of work in 10, 15 and 30 days, respectively. If B and C both assist A on every third day, then in how many days can the work be completed?
- Assistant
Let the total work be 60 units (which is the LCM of 10, 15 and 30). A can do 6 units of work in a day (since he can complete the work alone in 10 days) B can do 4 units of work in a day (since he can complete 1/15th of the work in a day) C can do 2 units of work in a day (since he can complete 1/30th of the work in a day) Now, A, B and C work together on every third day. So, on the first two days, A works alone and on the third day all three of them work together. This cycle repeats. On the first two days, A completes 2 * 6 = 12 units of work. On the third day, A, B and C together can complete 6 + 4 + 2 = 12 units of work. So, in every three days, 24 units of work are completed. Therefore, the work of 60 units will be completed in (60/24)*3 = 7.5 * 3 = 22.5 days. However, since we cannot have half a day, we round it up to the next integer. Hence, the work will be completed in 23 days.