You're a project manager calculating a projects TCPI. The EV is $27000, ac is $25000,…
- User
You're a project manager calculating a projects TCPI. The EV is 25000, and bac is 35000. What is the tcpi based on the new each?
- Assistant
TCPI (To-Complete Performance Index) is used to calculate the efficiency needed to complete a project within the budget.
The formula for TCPI is:
TCPI = (BAC - EV) / (BAC - AC)
Where: BAC = Budget at Completion EV = Earned Value AC = Actual Cost
Using the given data:
EV = 25000 BAC = $32000
The formula for TCPI using the original data is:
TCPI = (BAC - EV) / (BAC - AC) TCPI = (27000) / (25000) TCPI = 7000 TCPI = 0.71