As a project manager, you analyze the amount of time team members will need to spend on a project and the likely ongoing project expenses. What step of the cost benefit analysis are you completing?
1 point
Benefit analysis
Goals analysis
Expense analysis
Cost analysis
- Assistant
Cost analysis