Some of the best ways to visualize earned value analysis data are:
-
Earned Value Curve: This shows the planned value, earned value, and actual cost curves over the duration of the project. It provides an intuitive visual of how the project is progressing compared to the plan. If the EV curve is above PV, the project is ahead of schedule. If the AC curve is above EV, the project is over budget.
-
Earned Value Cost and Schedule Variance Charts: This includes two charts:
• Cost Variance Chart: Shows the cost variance (CV) over time. A positive CV means under budget, negative CV means over budget. It highlights when and by how much the project went over or under budget.
• Schedule Variance Chart: Shows the schedule variance (SV) over time. A positive SV means ahead of schedule, negative SV means behind schedule. It highlights when and by how much the project went ahead of or behind schedule.
- Earned Value Performance Indices Charts: This also includes two charts:
• Cost Performance Index (CPI) Chart: A CPI greater than 1 means under budget, less than 1 means over budget. It measures the cost efficiency of the project over time.
• Schedule Performance Index (SPI) Chart: A SPI greater than 1 means ahead of schedule, less than 1 means behind schedule. It measures the schedule efficiency of the project over time.
- Earned Value Dashboard: Provides an overview of key metrics like PV, EV, AC, CV, SV, CPI, SPI at a glance. It gives a high-level summary of where the project stands in terms of cost and schedule performance. Various stoplight colors are used to visually flag metrics that need attention.
These earned value visuals provide insights into project progress and performance to help project managers make better decisions to keep the project on track.